Mission Valley Elementary School Valley View Middle School

  • Slides: 19
Download presentation
Mission Valley Elementary School Valley View Middle School Community Meeting May 30, 2017

Mission Valley Elementary School Valley View Middle School Community Meeting May 30, 2017

2

2

VALLEY VIEW MS / MISSION VALLEY ES

VALLEY VIEW MS / MISSION VALLEY ES

Architect: Design: Bidding: Procurement: Construction Mgr. : BP 08 Mijares-Mora Architects May 2016 -

Architect: Design: Bidding: Procurement: Construction Mgr. : BP 08 Mijares-Mora Architects May 2016 - May 2017 May & June 2017 Construction Manager at Risk Buford-Thompson Co. New Valley View MS | Mission Valley ES Combo Design Charrette • Day 1 Tuesday, May 3, 2016 and Day 2 Tuesday, May 24, 2016 Design state-of-the-art 21 st century learning environment with shared key core spaces. Front Façade -Mission Valley ES Front Façade–Valley View MS 4

Front Façade -Mission Valley ES Front Façade–Valley View MS 7

Front Façade -Mission Valley ES Front Façade–Valley View MS 7

Architect: Design: Bidding: Procurement: Construction Mgr. : BP 08 Mijares-Mora Architects May 2016 -

Architect: Design: Bidding: Procurement: Construction Mgr. : BP 08 Mijares-Mora Architects May 2016 - May 2017 May & June 2017 Construction Manager at Risk Buford-Thompson Co. New Valley View MS | Mission Valley ES Combo SCOPE OF WORK • Replacement of 25 -year-old Camino Real MS and Valley View MS and 30 -year-old Mission Valley Elementary School. • Capacity for 1, 500 MS students and 810 ES students • State-of-the-art 21 st century learning environment with shared key core spaces. Front Façade -Mission Valley ES Ø Bid Pkg. #1 (Earthwork & Early Demo): Procurement 03/2017 - 05/2017 Board Approval of GMP #1: May 17, 2017 Phase 1 Construction Start: June 2017 Ø Bid Pkg. #2 (All Other): Construction Documents Phase: 12/ 2016 – 05/ 2017 Front Façade–Valley View MS Board Approval of GMP #1: Anticipated July 19, 2017 Phase 2 Construction Start: August 2017 8

Mission Valley Front Entrance 9

Mission Valley Front Entrance 9

Mission Valley Administration Areas 10

Mission Valley Administration Areas 10

Mission Valley Central Stair Area 11

Mission Valley Central Stair Area 11

Mission Valley Collaboration Areas 12

Mission Valley Collaboration Areas 12

Valley View Middle Front Entrance 13

Valley View Middle Front Entrance 13

Valley View Middle School Main Stairs 14

Valley View Middle School Main Stairs 14

Shared Spaces Library and Maker Space 15

Shared Spaces Library and Maker Space 15

Collaborative Environments Representative images for informational purposes only. 16

Collaborative Environments Representative images for informational purposes only. 16

Valley View|Mission Valley Overall Site Plan MS Classroom Building BKB ES Classroom Building Gymnasiums

Valley View|Mission Valley Overall Site Plan MS Classroom Building BKB ES Classroom Building Gymnasiums Tennis Football Track Softball Baseball 17

Valley View|Mission Valley Overall Floor Plans 18

Valley View|Mission Valley Overall Floor Plans 18