MICE Coupling Coil Update MICE CM 34 at
- Slides: 24
MICE Coupling Coil Update MICE CM 34 at RAL, UK October 17, 2012 Allan De. Mello Lawrence Berkeley National Laboratory
Current Status of Coupling Coil • Cold Mass • Reservoir welded onto cold mass • Cooling pipes welded into cold mass slots • Epoxy impregnation of gap between coil and cover plate complete • LTS lead stabilization complete • Quench protection mounted • Instrumentation mounted • Pressure test of cooling pipe complete • Vacuum check of pipe (discovered leak) • High-pot test of coil complete MICE Coupling RFCC Module MICE Schedule RAL, UK MICE Coil–Update – MICE Review CM 34 atat. RAL, UK Derun Li. Lawrence - Lawrence. Berkeley National – May 24, 2011 Allan De. Mello. National. Lab – October 17, 2012 Page 22 Page
Current Status of Coupling Coil • Cryostat • Drawings from SINAP (China) complete • Work order has been approved for the LBNL mechanical shop to start fabricating the first cryostat MICE Coupling RFCC Module MICE Schedule RAL, UK MICE Coil–Update – MICE Review CM 34 atat. RAL, UK Derun Li. Lawrence - Lawrence. Berkeley National – May 24, 2011 Allan De. Mello. National. Lab – October 17, 2012 Page 33 Page
Coupling Coil General Dimensions MICE Coupling RFCC Module MICE Schedule RAL, UK MICE Coil–Update – MICE Review CM 34 atat. RAL, UK Derun Li. Lawrence - Lawrence. Berkeley National – May 24, 2011 Allan De. Mello. National. Lab – October 17, 2012 Page 44 Page
Major Sub-Assemblies MICE Coupling RFCC Module MICE Schedule RAL, UK MICE Coil–Update – MICE Review CM 34 atat. RAL, UK Derun Li. Lawrence - Lawrence. Berkeley National – May 24, 2011 Allan De. Mello. National. Lab – October 17, 2012 Page 55 Page
A Brief History of the Cold Mass • Unfinished cold mass from China arrives at LBNL October 2011 • Design of cooling scheme, LTS lead stabilization and quench protection still incomplete • LBNL engineers met with Brad Smith and his team at the Massachusetts Institute of technology (MIT) in March of 2012 • MIT group designed and LBNL implemented an LTS lead stabilization system and a quench protection system • MIT group refined the cooling system designed by Tapio Niinikoski (CERN) and Li Wang (SINAP) MICE Coupling RFCC Module MICE Schedule RAL, UK MICE Coil–Update – MICE Review CM 34 atat. RAL, UK Derun Li. Lawrence - Lawrence. Berkeley National – May 24, 2011 Allan De. Mello. National. Lab – October 17, 2012 Page 66 Page
Cooling Pipes Welded onto Cold Mass • Pipes welded into the slots of the cold mass Cross-section view MICE Coupling RFCC Module MICE Schedule RAL, UK MICE Coil–Update – MICE Review CM 34 atat. RAL, UK Derun Li. Lawrence - Lawrence. Berkeley National – May 24, 2011 Allan De. Mello. National. Lab – October 17, 2012 Page 77 Page
Reservoir Welded onto Cold Mass • Dual – action actuator Finished tuner arm Jan. 25 -26, 2012 in Fermilab • Flexure tuner arm • Helium reservoir welded onto cold mass MICE Coupling RFCC Module MICE Schedule RAL, UK MICE Coil–Update – MICE Review CM 34 atat. RAL, UK Derun Li. Lawrence - Lawrence. Berkeley National – May 24, 2011 Allan De. Mello. National. Lab – October 17, 2012 Page 88 Page
Cold Mass Preparation • Cold mass on milling machine for drilling and taping of holes for the lead stabilization and quench protection hardware mounting bolts MICE Coupling RFCC Module MICE Schedule RAL, UK MICE Coil–Update – MICE Review CM 34 atat. RAL, UK Derun Li. Lawrence - Lawrence. Berkeley National – May 24, 2011 Allan De. Mello. National. Lab – October 17, 2012 Page 99 Page
LTS Lead Stabilization • Met with Brad Smith and his team in March 2012 • MIT group designed and LBNL implemented LTS lead stabilization HTS to LTS thermal intercept (Bert Wang design) LTS lead stabilizers MICE Coupling RFCC Module MICE Schedule RAL, UK MICE Coil–Update – MICE Review CM 34 atat. RAL, UK Derun Li. Lawrence - Lawrence. Berkeley National – May 24, 2011 Allan De. Mello. National. Lab – October 17, 2012 Page 10
Quench Protection • MIT group designed and LBNL implemented quench protection system Diodes LTS loops secured to the cold mass MICE Coupling RFCC Module MICE Schedule RAL, UK MICE Coil–Update – MICE Review CM 34 atat. RAL, UK Derun Li. Lawrence - Lawrence. Berkeley National – May 24, 2011 Allan De. Mello. National. Lab – October 17, 2012 Page 11
Epoxy Impregnation Cold mass in the paint shop oven for epoxy cure Cross section view Gap between cover plate and aluminum banding was filled with epoxy MICE Coupling RFCC Module MICE Schedule RAL, UK MICE Coil–Update – MICE Review CM 34 atat. RAL, UK Derun Li. Lawrence - Lawrence. Berkeley National – May 24, 2011 Allan De. Mello. National. Lab – October 17, 2012 Page 12
Cooling Pipe Pressure Test • Cooling pipe was hydrostatically tested, in steps, to a pressure of 300 psi • No leaks detected MICE Coupling RFCC Module MICE Schedule RAL, UK MICE Coil–Update – MICE Review CM 34 atat. RAL, UK Derun Li. Lawrence - Lawrence. Berkeley National – May 24, 2011 Allan De. Mello. National. Lab – October 17, 2012 Page 13
Instrumentation Heater Strain Gauges Voltage Taps Cernox Sensor MICE Coupling RFCC Module MICE Schedule RAL, UK MICE Coil–Update – MICE Review CM 34 atat. RAL, UK Derun Li. Lawrence - Lawrence. Berkeley National – May 24, 2011 Allan De. Mello. National. Lab – October 17, 2012 Page 14
Cooling Pipe Vacuum Leak The vacuum leak was determined to be in this area behind pipe Section View MICE Coupling RFCC Module MICE Schedule RAL, UK MICE Coil–Update – MICE Review CM 34 atat. RAL, UK Derun Li. Lawrence - Lawrence. Berkeley National – May 24, 2011 Allan De. Mello. National. Lab – October 17, 2012 Page 15
Cooling Pipe Vacuum Leak Welding was done to attempt to seal the leak Plastic cover clamped into place over opening for vacuum check The vacuum leak was determined to be at the back of pipe. An opening was cut into pipe so welding could be done, from the inside, to the back area of the pipe MICE Coupling RFCC Module MICE Schedule RAL, UK MICE Coil–Update – MICE Review CM 34 atat. RAL, UK Derun Li. Lawrence - Lawrence. Berkeley National – May 24, 2011 Allan De. Mello. National. Lab – October 17, 2012 Page 16
Cooling Pipe Vacuum Leak determined to be towards the top of the pipe and welding was done, outside, to attempt to seal it A permanent cover was welded into place over opening Several attempts to seal the vacuum leak have failed. LBNL is currently waiting for guidance from Fermilab safety review panel for a by-pass repair MICE Coupling RFCC Module MICE Schedule RAL, UK MICE Coil–Update – MICE Review CM 34 atat. RAL, UK Derun Li. Lawrence - Lawrence. Berkeley National – May 24, 2011 Allan De. Mello. National. Lab – October 17, 2012 Page 17
Fermilab Test Setup MICE Coupling RFCC Module MICE Schedule RAL, UK MICE Coil–Update – MICE Review CM 34 atat. RAL, UK Derun Li. Lawrence - Lawrence. Berkeley National – May 24, 2011 Allan De. Mello. National. Lab – October 17, 2012 Page 18
Coupling Coil Cryostat Single Cavity Vacuum Vessel Exploded View MICE Coupling RFCC Module MICE Schedule RAL, UK MICE Coil–Update – MICE Review CM 34 atat. RAL, UK Derun Li. Lawrence - Lawrence. Berkeley National – May 24, 2011 Allan De. Mello. National. Lab – October 17, 2012 Page 19
Coupling Coil Cryostat • Cryostat design is complete • Drawings from SINAP (China) complete • LBNL mechanical shop will fabricate the first cryostat • Estimated to take 6 months to complete fabrication • Drawings will be updated to reflect the “as built” cryostat MICE Coupling RFCC Module MICE Schedule RAL, UK MICE Coil–Update – MICE Review CM 34 atat. RAL, UK Derun Li. Lawrence - Lawrence. Berkeley National – May 24, 2011 Allan De. Mello. National. Lab – October 17, 2012 Page 20
Coupling Coil Thermal Shield Drawings • Drawings have been red lined but not updated • Thermal shield design is nearly complete • Some SINAP parts/drawings will need to be revised for better manufacturability MICE Coupling RFCC Module MICE Schedule RAL, UK MICE Coil–Update – MICE Review CM 34 atat. RAL, UK Derun Li. Lawrence - Lawrence. Berkeley National – May 24, 2011 Allan De. Mello. National. Lab – October 17, 2012 Page 21
Cooling Circuit Cryo cool First ers Stag e Co ppe r Pla Heliu m Fil tes l Line • Finalize design • Update drawings • Generate any new drawings as needed Thermal Siphon Manifold MICE Coupling RFCC Module MICE Schedule RAL, UK MICE Coil–Update – MICE Review CM 34 atat. RAL, UK Derun Li. Lawrence - Lawrence. Berkeley National – May 24, 2011 Allan De. Mello. National. Lab – October 17, 2012 Page 22
Coupling Coil Future Work • Cold Mass: • Determine plan to repair the leaking cooling pipe with guidance from Fermilab safety review committee • Vacuum check the two remaining pipes – Done • Pressure test the remaining 2 pipes to 240 psi • Implement the repair plan for the leaking pipe • Pressure test the previously leaking pipe to 300 psi • Vacuum check all of the pipes • Ship to Fermilab for magnetic tests MICE Coupling RFCC Module MICE Schedule RAL, UK MICE Coil–Update – MICE Review CM 34 atat. RAL, UK Derun Li. Lawrence - Lawrence. Berkeley National – May 24, 2011 Allan De. Mello. National. Lab – October 17, 2012 Page 23
Coupling Coil Future Work • Cryostat: • Fabricate first cryostat – 6 months to complete • Update any drawings to reflect changes generated for “as built” • Determine fabricator for the additional 2 cryostats • Thermal Shield: • Update red lined drawings • Modify some parts for better manufacturability • LBNL shops may fabricate the first thermal shield • Cooling Circuit: • Finalize design • Update drawings • Generate any new drawings as needed MICE Coupling RFCC Module MICE Schedule RAL, UK MICE Coil–Update – MICE Review CM 34 atat. RAL, UK Derun Li. Lawrence - Lawrence. Berkeley National – May 24, 2011 Allan De. Mello. National. Lab – October 17, 2012 Page 24
- Multi turn coil
- Alternative of log based recovery
- Low coupling in software engineering
- Spin orbit coupling
- Expanding stage of family life cycle
- Udsdc
- Factors influencing chemical shift
- What is step 16 when coupling a tractor to a trailer
- Cardiac excitation-contraction coupling
- Cross frequency coupling
- Unsw
- Stamp coupling in software engineering
- Mtj tmr
- Hereditary units
- Carbon fibre coupling
- Berendsen pressure coupling
- Low coupling in software engineering
- Oscillating fifth wheel
- Geminal coupling
- Energy coupling
- A dbms reduces data redundancy and inconsistency by
- J coupling constant
- Gauge coupling unification
- Excitation contraction coupling
- Geminal and vicinal coupling constants