MATTEO SOLFAROLI and MIRKO POJER HARDWARE COMMISSIONING DURING

  • Slides: 15
Download presentation
MATTEO SOLFAROLI and MIRKO POJER HARDWARE COMMISSIONING DURING WINTER TECHNICAL STOP Acknowledgements: R. Schmidt,

MATTEO SOLFAROLI and MIRKO POJER HARDWARE COMMISSIONING DURING WINTER TECHNICAL STOP Acknowledgements: R. Schmidt, M. Zerlauth, H. Thiesen, N. Catalan, K. Foraz, R. Giachino

CRYO-INTERVENTION PLANNING 10/15/2021 Mirko Pojer – LHCBCWG 2

CRYO-INTERVENTION PLANNING 10/15/2021 Mirko Pojer – LHCBCWG 2

POWERING TEST PLANNING S 12 2 shifts 5/7 days for access S 34 S

POWERING TEST PLANNING S 12 2 shifts 5/7 days for access S 34 S 45 S 56 S 67 S 78 S 81 1 18 CRYO MAINTAIN 1 ELQA 19 1 1 20 1 1 21 1 1 MIC 1 POWERING 1 22 23 24 1 25 1 1 1 26 1 27 1 1 1 28 1 1 1 Chamonix January Chamonix: No shifts (Access covered by TI? ) S 23 17 29 30 3 shifts 7/7 days 31 1 1 2 1 3 4 1 1 1 5 6 7 8 February 9 10 11 12 13 DSO tests 14 15 16 17 18 20 21 10/15/2021 BEAM OPERATION Mirko Pojer – LHCBCWG 3

GENERAL LAYOUT PC condemnation El. QA monitoring of multi-k. A circuits and spool pieces

GENERAL LAYOUT PC condemnation El. QA monitoring of multi-k. A circuits and spool pieces RRR measurements during warm-up/cool-down El. QA after re-cooldown PC de-condemnation QPS-IST with selective quench heater firing (only where disconnected) • Powering tests (special tests on RB. A 56 to validate simulations) • Heat runs and GPM test • • Cycling, cycling…. 10/15/2021 Mirko Pojer – LHCBCWG 4

KEY-DRIVERS FOR ELQA • It was decided to perform the electrical integrity validation only

KEY-DRIVERS FOR ELQA • It was decided to perform the electrical integrity validation only on high current circuits, despite thermal excursions • The MSs and ITs will certainly go (far) above 80 K → full El. QA • MIC will be done on MSs and ITs The El. QA team and equipment: • Equipment for testing up to 4 sectors in parallel • 5 teams available inside the El. QA team (2 teams per sector + 1 (per MIC) needed) –> up to 2 sectors in parallel 10/15/2021 Mirko Pojer – LHCBCWG 5

POWERING TEST STREAMLINING Circuit type PIC 2 RB (8) Estimation ~30 min ~10 min

POWERING TEST STREAMLINING Circuit type PIC 2 RB (8) Estimation ~30 min ~10 min ~15 min ~35 min ~15 min 600 A no IT PNO. b 2 Energy Extraction from QPSat. Bipolar PNO. d 3 Powering EE crow PNO. d 12 PC Failure +10% of PNO~30 min ~10 min ~20 min PIC 2 PLI 3. d 2 Unipolar. PIC 2 Powering Failure ~10 min ~15 min Failure 600 A (136) PNO. d 13 PC Failure at -10% of PNO ~30 min (per ~10 min circuit) PIC 2 ~2 min PIC 2 ~15 min 80 – 120 A IPD PLI 2. b 3 Energy Extraction from QPS 13 k. A ~20 min PNO. d 1 Bipolar Powering PNO. c 2 Fast Power Abort IPD (284) (16) Failure PNO. b 3 Energy Extraction from QPS 13 k. A ~30 min PIC 2 PNO. d 1 Bipolar Powering PLI 3. b 1 Energy Extraction from QPS 600 A Failure 600 A EE (202) 600 A no EE (72) 60 A (752) ~10 min ~20 min ~10 min ~5 min PNO. d 3 Bipolar Powering Failure 600 A ~15 min PIC 2 ~10 min PNO. d 3 Bipolar Powering Failure 600 A TOT 3/6 PIC tests 1/7 other tests (+ 4/13 other tests PNO. a 7) (+2 if 4 Te. V) 3/6 PIC tests 1/4 other tests 2/16 other tests 5/8 Estimation ~20 min PIC 2 (16) Sector PIC 2 Circuit PLI 1. d 2 Unipolar Powering Failure IPQs Sector type PNO. c 3 Fast Power Abort IPQ (78) PLI 2. b 2 Energy Extraction from QPS I_Interm_1 (8) RQD/F Test ~15 min 5/8 PIC 1/3 PIC 3/6 tests PICtests 2/12 1/4 other tests 2/4 other tests 3/6 other PIC tests 1/3 tests 2/6 other tests 3/6 PIC tests 1792/3672 PIC tests - 49% 1/4 other tests 1690/5878 other tests - 29% • Main focus on protection interlocks (QPS/EE, PIC, PC) --> Almost all tests to verify the correct operation of interlock loops will be performed • Reduced number of other tests, according to expert requirements • Heat run for all circuits will be performed (8 hours) as last step 10/15/2021 Mirko Pojer – LHCBCWG 6

POWERING PROCEDURES (MP 3) • Optimization • Modularity to be applied to all kind

POWERING PROCEDURES (MP 3) • Optimization • Modularity to be applied to all kind of situations (full commissioning, technical stop, components replacement, …) • Example: PCC. 4 PIC 2 PLI 1 PLI 2. f 3 PLI 2. c 3 PNO. c 2 PNO. f 3 PNO. c 4 Intervention Change of a magnet Re-work of the interconnection Warm up above 80 K Change of power module Change of FGC software Change of QPS hardware QPS firmware update Regular interventions (1 x year) Courtesy of N. Catalan 10/15/2021 Mirko Pojer – LHCBCWG 7

CIRCUIT SPECIFICITIES AND NCS List of non-conformities and powering singularities • – – –

CIRCUIT SPECIFICITIES AND NCS List of non-conformities and powering singularities • – – – – RQTD and RQTF validation time extended to 190 ms, can it remain for 4 Te. V? RQS validation time extended to 190 ms, can it remain for 4 Te. V? Higher order correctors in triplet? for higher E, lower beta? RU RCBX, limited to 350 A due to difficulties to make the interlock on the square sum operating, issue with d. I/dt RPMBA. UA 83. RQT 13. L 8 B 1 RPMBA. UA 27. RQTL 11. R 2 B 1 RQS. A 45 B 1 and RQS. A 45 B 2 have a high value Large part of 600 A circuits were commissioned to the value required for 5 Te. V A few circuits have some issues, and were operated at lower current The IPQ and IPD circuits were limited to 3. 5 Te. V because of the missing splice resistance measurements RB. A 81 d. I/dt needs to be set correctly RQ 6 – RQ 10. R 6 parameters HW limit set differently RCBYHS 5. R 8 B 1 has an issue and is limited to 20 A RQX. R 1: QHPS voltage reduction and capacitance increase • • Re-visiting and taking a critical look (new current limits for 4/5 Te. V operation) 10/15/2021 Mirko Pojer – LHCBCWG 8

RESOURCES • 2 -3 weeks with 24/7: can the experts operate like that? –

RESOURCES • 2 -3 weeks with 24/7: can the experts operate like that? – – – 10/15/2021 EPC will provide full support PIC will be on best effort (most is automated) QPS will mainly be on extended working hours MP 3 on full time (to be confirmed) OP is already organizing the shifts Mirko Pojer – LHCBCWG 9

WHAT LMC HAS RECENTLY ENDORSED • Installation of the snubber-capacitors on DQS for the

WHAT LMC HAS RECENTLY ENDORSED • Installation of the snubber-capacitors on DQS for the dipole circuits – Discussion ongoing about their connection (to be tested for one sector, to be decided for the others) – Experts says they are needed for 4 Te. V operation – Not needed for the RQD/F Energy change and snubbers → extraction time to be increased to 68 s (12. 5 s for the RQs) • Upgrade of all IPQ’s and IPD’s for 10 V input and 500 Hz PM acquisition frequency • Decommissioning of the existing main bus-bar protection systems and respective reconfiguration of the main circuit protection. • Various software upgrades for the DQGPU’s • RRR measurements 10/15/2021 Courtesy of K. Foraz Mirko Pojer – LHCBCWG 10

SAFETY-RELATED ASPECTS 10/15/2021 Mirko Pojer – LHCBCWG 11

SAFETY-RELATED ASPECTS 10/15/2021 Mirko Pojer – LHCBCWG 11

AUG AND TRANSFORMERS REPLACEMENT AUG tests Point 1 : Sunday 19 th December Point

AUG AND TRANSFORMERS REPLACEMENT AUG tests Point 1 : Sunday 19 th December Point 18: Wednesday 5 th January Point 2: Thursday 20 th January Point 3: Wednesday 8 th December Point 4: Thursday 6 th January Point 5: Tuesday 4 th January Point 6: Monday 10 th January Point 7: Tuesday 11 th January Point 8: Monday 20 th December – No access from point 1 to mid-arcs – No access in PM 18, UJ 18 – No access from point 2 to mid-arcs – No access from point 3 to mid-arcs – No access from point 5 to mid-arcs – No access from point 6 to mid-arcs – No access from point 7 to mid-arcs – No access from point 8 to mid-arcs Stop of ventilation in the arcs (transformer exchange) Arc 34 and arc 45: From Monday 17 th January to Friday 21 st January Arc 56 and arc 67: From Tuesday 11 th January to Friday 15 st January 10/15/2021 Mirko Pojer – LHCBCWG 12

WORK ACCEPTANCE TOOL Virtually, no more need for access operators Courtesy of K. Foraz

WORK ACCEPTANCE TOOL Virtually, no more need for access operators Courtesy of K. Foraz 10/15/2021 Mirko Pojer – LHCBCWG 13

BEYOND HWC S 12 S 23 S 34 S 45 S 56 17 S

BEYOND HWC S 12 S 23 S 34 S 45 S 56 17 S 67 S 78 S 81 1 18 CRYO MAINTAIN 1 ELQA 19 1 1 20 1 1 21 1 1 MIC 1 POWERING 1 23 24 1 25 1 1 1 26 1 27 1 1 1 28 1 1 1 Chamonix January 22 29 30 31 1 1 2 1 3 4 1 1 1 5 6 7 8 February 9 10 11 12 13 DSO tests 14 15 16 Machine check-out 17 18 20 21 10/15/2021 BEAM OPERATION Mirko Pojer – LHCBCWG BIS RF LBDS MKI/injection/TLs Collimators BI instrumentation Controls 14

CONCLUDING REMARKS • Tough planning (profitez bien des vacances!) • HC team is working

CONCLUDING REMARKS • Tough planning (profitez bien des vacances!) • HC team is working on all test-related aspects: – – – Powering test streamlining Powering procedures (MP 3) NCs Implications of energy increase Almost regular meetings with experts • Safety aspects are being considered • WAT will keep people away from the access consoles • Tracking of performed activity in the tunnel is the key for a fast restart • Machine check-out can start after the DSO tests 10/15/2021 Mirko Pojer – LHCBCWG 15