LS 2 planning meeting A Tauro LS 2
- Slides: 96
LS 2 planning meeting A. Tauro
LS 2 master plan (v 31) LS 2 planning meeting 2
EN-EL interventions • CERN wide 66 k. V maintenance: 28 May 2019 to 19 July 2019 – reduced consumption (i. e. no magnets) – almost done • Maintenance machine network: from 11 to 14 June 2019 – done • Test secours (10 min): 19 Dec 2019 from 8: 00 AM to 11: 00 AM • 18 k. V, 3. 3 k. V and LV network maintenance: • • Mon 20 to Wed 22 Jan 2020: 3 days no general services - no access on site (both surface and underground) Thu 23 to Fri 24 Jan 2020: 2 days ‘’Limited access’’ details being worked out • AUG on Monday 27 January 2020 - no access on site (both surface and underground) • Auto transfer test: 27 -29 Apr 2020 • BIW test: 5 and 6 Oct 2020 from 18: 00 to 00: 00 – no access underground 5/7/19 LS 2 planning meeting 3
EN-CV interventions • Big maintenance: • • • SF: from Nov 2019 to mid Jan 2020. NO impact on ALICE as both magnets will be OFF. UW: stop UX mixed water for 2 days in week 40/2019 (October). SU: various small perturbations + 1 day stop all cooling UX + 1 day stop all cooling SXL 2 in week 16/2020 (April). • Small maintenance: • • UW: from mid Aug 2020 to mid Sep 2020. Stop mixed water UX for 1 day in week 37/2020 (September). SF+SU: weeks 45 -47/2020: cleaning towers (stop SF 1 week) + 1 day stop all cooling UX. • Ventilation: • • • SG 2: w 7/2019 - Done Gas extraction: w 8/2019 - Done UX 25 cavern: May 2020 (tbc) MCH and MTG: Apr 2020 (tbc) L 3: Apr 2020 (tbc) ITS: Apr 2020 (tbc) • Raw water: • Test after Apr 2019. Short interruption (1 day), can be used tap water during the test. 5/7/19 LS 2 planning meeting 4
UX access • Cavern lift not available from Friday 26 July 12: 00 to Saturday 27 July 18: 00 no access to cavern no underground visits 5/7/19 LS 2 planning meeting 5
CERN Open Days • Sat 14 and Sun 15 September 2019 • Open Low-Beta platform and put scaffolding 5/7/19 LS 2 planning meeting 6
TRD schedule to be shifted by 1 w Remove 12, 13, 14 (counter weights) Reinstall 7, 1, 0, 8 Reinstall 12, 13, 14 Remove 10, 16 Reinstall 10, 16 5/7/19 LS 2 planning meeting 7
TPC upgrade sequence v 34 A side done Done Remove Services and FEE (outside cleanroom) A side done Uninstall MWPC ROC Install GEM ROC Done A-side done TPC in cleanroom. Cleaning & irradiation tests FC HV infrastructure modification 7 Mar 11 Apr TPC schedule v 34 25 Apr (A) 30 Jul (C) 27 May (A) 13 Aug (C) Install new FEC + test Survey, sealing, overpressure test 17 Jun (A) 21 Aug (C) 2 Jul (A) 4 Sep (C) LS 2 planning meeting Transportation to SX 2 Pre-commissioning with cosmic, Laser, pulser, Xray 2 Oct (A) 23 Oct (C) 31 Oct (A) 4 Dec (C) 21 Jan (Xray) 18 Feb 2020 8
schedule v 34 Near term TPC sequence De-installation and preparation A side ROC swapping, alignment and sealing C side ROC swapping, alignment and sealing FEC and services installation and testing. Pre-commissioning 5/7/19 LS 2 planning meeting 99
Copper cables (EN-EA) – new dates 5/7/19 LS 2 planning meeting 10
Copper cables (EN-EA) – progress 24% 5/7/19 LS 2 planning meeting 11
Optical fibers (EN-EL) – new dates 5/7/19 LS 2 planning meeting 12
Miniframe planning – new dates 5/7/19 LS 2 planning meeting 13
CR 0 planning Automation proposes to advance IT 4 SAT to w 35 5/7/19 LS 2 planning meeting 14
Day-by-day sequence w 25 ALICE technicians Institutes Transport Pakistani team EN-EL Rampower 5/7/19 Scaffolding EN-EA LS 2 planning meeting Other CERN groups 15
UX 25 activities w 25 – Mon 17 Jun 2019 CR 0: install CR 1 -CR 0 trunks and SR 2 -CR 0 trunk – whole week (COMSA) CR 0: connect IT 3 to power (Conect) Pressure test PHOS M 2 (Meyrin, Yannick) Remove frames Install TPC cooling pipes Miniframe (whole week) TPC/TR D/TOF LV cables ITS/MFT inox pipes MCH FEE cables TOF-A fibers Cedric, Samuel 5/7/19 Need scaffolding of LV cables + ladder inside L 3 LS 2 planning meeting 16
5/7/19 LS 2 planning meeting GEM install. TRD 7 A-side TRD 1 C-side SXL 2 activities w 25 – Mon 17 Jun 2019 17
UX 25 activities w 25 – Tue 18 Jun 2019 ALTEAD: transport PHOS M 4 to Meyrin and M 2 to P 2 MCH TPC/TR D/TOF LV cables ITS/MFT inox pipes 5/7/19 LS 2 planning meeting MCH FEE cables 18
5/7/19 LS 2 planning meeting GEM install. TRD 7 A-side TRD 1 C-side SXL 2 activities w 25 – Tue 18 Jun 2019 19
UX 25 activities w 25 – Wed 19 Jun 2019 ALTEAD: extract TPC pump and PMD gas rack (CR 5) EP-DT (gas): cut TPC gas pipes CR 5 (install Y for cleanroom) MCH TPC/TR D/TOF LV cables ITS/MFT inox pipes 5/7/19 LS 2 planning meeting MCH FEE cables 20
5/7/19 LS 2 planning meeting GEM install. TRD 7 A-side TRD 1 C-side SXL 2 activities w 25 – Wed 19 Jun 2019 21
UX 25 activities w 25 – Thu 20 Jun 2019 MCH TPC/TR D/TOF LV cables ITS/MFT inox pipes MCH FEE cables Remove both nacelles 5/7/19 LS 2 planning meeting 22
TRD 7 5/7/19 LS 2 planning meeting A-side TRD 1 C-side SXL 2 activities w 25 – Thu 20 Jun 2019 23
UX 25 activities w 25 – Fri 21 Jun 2019 Floor painting TPC/TR D/TOF LV cables ITS/MFT inox pipes 5/7/19 LS 2 planning meeting Floor painting 24
TRD 7 5/7/19 LS 2 planning meeting A-side TRD 1 C-side SXL 2 activities w 25 – Fri 21 Jun 2019 25
Day-by-day sequence w 26 ALICE technicians Institutes Transport Pakistani team EN-EL Rampower 5/7/19 Scaffolding EN-EA LS 2 planning meeting Other CERN groups 26
UX 25 activities w 26 – Mon 24 Jun 2019 Install TPC cooling pipes Miniframe (whole week) CR 0: network connection and wi-fi IT 3 (whole week) (IT) CR 0: install DCS monitoring inside IT 3 (whole week) Evacuate frames CR 0: open Roxtec IT 3 (Philippe) Extract TRD 0 (PM) TPC/TR D/TOF LV cables ITS/MFT inox pipes FIT-A cables Preparations (AM), extraction (PM) and move rotator to low-beta if possible 5/7/19 LS 2 planning meeting Cedric, Samuel Stop between 14: 00 and 16: 00 Install nacelle I-side 27
SXL 2 activities w 26 – Mon 24 Jun 2019 TRD 7 GEM install. SPD A-side TRD 1 C-side ALTEAD: transport ITS, SPD and FMD 3 to SX 2 and transport SPD to SXL 2 Klaus, install perimeter 5/7/19 LS 2 planning meeting 28
UX 25 activities w 26 – Tue 25 Jun 2019 Nacelle needed TRD fences TRD table ITS/MFT inox pipes TPC/TR D/TOF LV cables FIT-A cables MID test TRD survey (PM) Modify TRD table in SX 2 + put new fences (Didier) Remove fences (8: 00), remove table, modify table in SX 2, reinstall table 5/7/19 LS 2 planning meeting 29
TRD 7 GEM install. TRD 1 A-side SPD Gamma-ray C-side SXL 2 activities w 26 – Tue 25 Jun 2019 TRD 0 Bring TRD 0 to SXL 2, modify LV patch panel 5/7/19 Starts at 11: 00 Background in the night after removing SPD LS 2 planning meeting 30
TPC/TR D/TOF LV cables ITS/MFT inox pipes Put TRD rotator (PM) FIT-A cables MID test TRD scaffolding UX 25 activities w 26 – Wed 26 Jun 2019 Modify access (14: 00) 5/7/19 LS 2 planning meeting 31
TRD 7 GEM install. TRD 1 A-side ITS-FMD 3 Gamma-ray C-side SXL 2 activities w 26 – Wed 26 Jun 2019 TRD 0 Extract TRD 0 from rotator, put it inside blue frame 5/7/19 ALTEAD: bring FMD 3 in the area (9: 00), then remove FMD 3 and put ITS (14: 00) LS 2 planning meeting 32
UX 25 activities w 26 – Thu 27 Jun 2019 TN router replacement (S. Casenove) Put FIT-A cable drums ITS/MFT inox pipes 5/7/19 LS 2 planning meeting TPC/TR D/TOF LV cables FIT-A cables Stop between 13: 00 and 15: 00 MID test Extract TRD 8 (PM) 33
SXL 2 activities w 26 – Thu 27 Jun 2019 GEM install. A-side TRD 7 C-side ALTEAD: swap TRD 1 and 0. Transfer TRD 1 to rotator and back to blue frame TRD 1 TRD 0 5/7/19 LS 2 planning meeting 34
UX 25 activities w 26 – Fri 28 Jun 2019 TRD 8 TRD survey (PM) Scaffolding LV cables TPC/TR D/TOF LV cables ITS/MFT inox pipes Requires to remove TRD table 5/7/19 Floor painting LS 2 planning meeting Floor painting Remove nacelle I-side 35
SXL 2 activities w 26 – Fri 28 Jun 2019 5/7/19 LS 2 planning meeting GEM install. TRD 7 A-side TRD 0 C-side ALTEAD: Move TRD 8 & 1 to cavern 36
Day-by-day sequence w 27 ALICE technicians Institutes Transport Pakistani team EN-EL Rampower 5/7/19 Scaffolding EN-EA LS 2 planning meeting Other CERN groups 37
UX 25 activities w 27 – Mon 1 Jul 2019 Lift maintenance (AS-724): no access to UX 25 from 6: 00 AM to 8: 00 AM Install TPC cooling pipes Miniframe (whole week) CR 0: close roxtec IT 2 (Philippe) TRD 1 Reinstall frames TRD 8 TPC/TR D/TOF LV cables ITS/MFT inox pipes FIT-C cables Cedric, Samuel 5/7/19 LS 2 planning meeting Install nacelle 38
5/7/19 LS 2 planning meeting GEM install. TRD 7 A-side TRD 0 C-side SXL 2 activities w 27 – Mon 1 Jul 2019 39
UX 25 activities w 27 – Tue 2 Jul 2019 TRD survey (AM) CR 0: modbus testing (RO plant) TPC/TR D/TOF LV cables ITS/MFT inox pipes FIT-C cables Install nacelle 5/7/19 LS 2 planning meeting 40
5/7/19 LS 2 planning meeting GEM install. TRD 7 A-side TRD 0 C-side SXL 2 activities w 27 – Tue 2 Jul 2019 41
UX 25 activities w 27 – Wed 3 Jul 2019 TPC/TR D/TOF LV cables ITS/MFT inox pipes FIT-C cables ALTEAD: put 2 nacelles 5/7/19 LS 2 planning meeting Install nacelle 42
5/7/19 LS 2 planning meeting GEM install. TRD 7 A-side TRD 0 C-side SXL 2 activities w 27 – Wed 3 Jul 2019 43
UX 25 activities w 27 – Thu 4 Jul 2019 ALTEAD: displace nacelle ITS/MFT inox pipes Fix floor TPC/TR D/TOF LV cables FIT-C cables Install nacelle 5/7/19 LS 2 planning meeting 44
5/7/19 LS 2 planning meeting GEM install. TRD 7 A-side TRD 0 C-side SXL 2 activities w 27 – Thu 4 Jul 2019 45
UX 25 activities w 27 – Fri 5 Jul 2019 Install Miniframe scaffolding Disconnect ACO modules TPC/TR D/TOF LV cables ITS/MFT inox pipes Install nacelle 5/7/19 LS 2 planning meeting 46
SXL 2 activities w 27 – Fri 5 Jul 2019 Survey A-side TRD 7 C-side TRD 0 I-bars Fill TPC with dry air and test GEM (leakage current test) And end plates adjustment 5/7/19 LS 2 planning meeting 47
Day-by-day sequence w 28 ALICE technicians Institutes Transport Pakistani team EN-EL Rampower 5/7/19 Scaffolding EN-EA LS 2 planning meeting Other CERN groups 48
UX 25 activities w 28 – Mon 8 Jul 2019 CR 0: connect IT 3 to water (Rampower) – whole week MCH RO connectors (racks) MCH TPC/TR D/TOF LV cables ITS/MFT inox pipes FIT-C cables Install filter boxes, need both nacelles 5/7/19 LS 2 planning meeting 49
Miniframe activities w 28 – Mon 8 Jul 2019 Install TPC cooling pipes 11/1/19 LS 2 preparatory meeting 50
SXL 2 activities w 28 – Mon 8 Jul 2019 TRD 0 Survey A-side TRD 7 C-side TRD 8 I-bars ALTEAD: take out TRD 0 from swimming pool and bring TRD 8 to SXL 2 SSD/SDD frame And end plates adjustment Yannick: appointment at 10: 30 for new scaffolding (Alu-It) 5/7/19 LS 2 planning meeting 51
UX 25 activities w 28 – Tue 9 Jul 2019 ALTEAD: load test P 2 cranes Scaffolding MCH RO connectors (racks) Disconnect ACO modules TPC/TR D/TOF LV cables ITS/MFT inox pipes 5/7/19 MCH LS 2 planning meeting FIT-C cables 52
Miniframe activities w 28 – Tue 9 Jul 2019 Install TPC cooling pipes 11/1/19 LS 2 preparatory meeting 53
ROC survey TRD 7 A-side TRD 8 C-side SXL 2 activities w 28 – Tue 9 Jul 2019 TRD 0 5/7/19 LS 2 planning meeting 54
UX 25 activities w 28 – Wed 10 Jul 2019 ALTEAD: load test P 2 cranes MCH RO connectors (racks) Disconnect ACO modules TPC/TR D/TOF LV cables ITS/MFT inox pipes 5/7/19 MCH LS 2 planning meeting FIT-C cables 55
Miniframe activities w 28 – Wed 10 Jul 2019 Install TPC cooling pipes 11/1/19 LS 2 preparatory meeting 56
ROC survey TRD 7 A-side TRD 8 C-side SXL 2 activities w 28 – Wed 10 Jul 2019 TRD 0 5/7/19 LS 2 planning meeting 57
UX 25 activities w 28 – Thu 11 Jul 2019 MCH RO connectors (racks) Remove ACO modules MCH TPC/TR D/TOF LV cables ITS/MFT inox pipes FIT-C cables Remove top modules, start at 9: 00 5/7/19 LS 2 planning meeting 58
Miniframe activities w 28 – Thu 11 Jul 2019 Install ITS/MFT cooling pipes Install TPC cooling pipes 11/1/19 LS 2 preparatory meeting 59
Shims TRD 7 A-side TRD 8 C-side SXL 2 activities w 28 – Thu 11 Jul 2019 TRD 0 Uninstall, machine and re-install shims 5/7/19 LS 2 planning meeting 60
UX 25 activities w 28 – Fri 12 Jul 2019 MCH RO connectors (ST 1 -2 -3) TPC/TR D/TOF LV cables 5/7/19 LS 2 planning meeting FIT-C cables 61
Miniframe activities w 28 – Fri 12 Jul 2019 Install ITS/MFT cooling pipes Install TPC cooling pipes 11/1/19 LS 2 preparatory meeting 62
SXL 2 activities w 28 – Fri 12 Jul 2019 5/7/19 LS 2 planning meeting Shims TRD 7 A-side TRD 8 C-side ALTEAD: bring TRD 0 to UX 25 63
Day-by-day sequence w 29 ALICE technicians Institutes Transport Pakistani team EN-EL Rampower 5/7/19 Scaffolding EN-EA LS 2 planning meeting Other CERN groups 64
UX 25 activities w 29 – Mon 15 Jul 2019 ITS cables from A-racks to PP 0 Move TPC laser onto platform (Borge) 5/7/19 Remove ACO modules MCH RO connectors (ST 1 -2 -3) TPC/TR D/TOF LV cables LS 2 planning meeting 65
Miniframe activities w 29 – Mon 15 Jul 2019 Install ITS/MFT cooling pipes Install TPC cooling pipes 11/1/19 LS 2 preparatory meeting 66
SXL 2 activities w 29 – Mon 15 Jul 2019 ROC survey TRD 7 A-side TRD 0 C-side Wrap blocks for TPC laser Second survey and shimming 5/7/19 LS 2 planning meeting 67
UX 25 activities w 29 – Tue 16 Jul 2019 ITS cables from A-racks to PP 0 Move TPC laser onto platform (Borge) 5/7/19 Remove ACO modules CPV cables LS 2 planning meeting MCH RO connectors (ST 1 -2 -3) TPC/TR D/TOF LV cables 68
Miniframe activities w 29 – Tue 16 Jul 2019 Install ITS/MFT cooling pipes Install TPC cooling pipes 11/1/19 LS 2 preparatory meeting 69
5/7/19 LS 2 planning meeting ROC survey TRD 7 A-side TRD 0 C-side SXL 2 activities w 29 – Tue 16 Jul 2019 70
ITS cables from A-racks to PP 0 UX 25 activities w 29 – Wed 17 Jul 2019 5/7/19 MCH RO connectors (ST 1 -2 -3) CPV cables LS 2 planning meeting TPC/TR D/TOF LV cables 71
Miniframe activities w 29 – Wed 17 Jul 2019 Install ITS/MFT cooling pipes Install TPC cooling pipes 11/1/19 LS 2 preparatory meeting 72
ROC survey TRD 7 A-side TRD 0 C-side SXL 2 activities w 29 – Wed 17 Jul 2019 Final survey (optional further iteration of shimming) 5/7/19 LS 2 planning meeting 73
UX 25 activities w 29 – Thu 18 Jul 2019 ITS cables from A-racks to PP 0 MCH FEE connectors (racks) 5/7/19 CPV cables LS 2 planning meeting TPC/TR D/TOF LV cables MCH FEE connectors (racks) 74
Miniframe activities w 29 – Thu 18 Jul 2019 Install ITS/MFT cooling pipes Install TPC cooling pipes 11/1/19 LS 2 preparatory meeting 75
5/7/19 LS 2 planning meeting Sealing TRD 7 A-side TRD 0 C-side SXL 2 activities w 29 – Thu 18 Jul 2019 76
UX 25 activities w 29 – Fri 19 Jul 2019 ITS cables from A-racks to PP 0 MCH FEE connectors (racks) 5/7/19 CPV cables LS 2 planning meeting TPC/TR D/TOF LV cables MCH FEE connectors (racks) 77
Miniframe activities w 29 – Fri 19 Jul 2019 Install ITS/MFT cooling pipes Install TPC cooling pipes 11/1/19 LS 2 preparatory meeting 78
SXL 2 activities w 29 – Fri 19 Jul 2019 Sealing TRD 7 A-side TRD 0 C-side Topnet: cleanroom roof (rent special nacelle) Ovp test with air over the weekend 5/7/19 LS 2 planning meeting 79
Day-by-day sequence w 30 ALICE technicians Institutes Transport Pakistani team EN-EL Rampower 5/7/19 Scaffolding EN-EA LS 2 planning meeting Other CERN groups 80
TPC/TR D/TOF LV cables MID FEE test MCH RO cables test (ST 1 -2 -3) MCH FEE connectors (ST 4 -5) ITS cables from A-racks to PP 0 UX 25 activities w 30 – Mon 22 Jul 2019 Need both nacelles 5/7/19 LS 2 planning meeting 81
Miniframe activities w 30 – Mon 22 Jul 2019 Install ITS/MFT cooling pipes Install TPC cooling pipes 11/1/19 LS 2 preparatory meeting 82
Open roof 8. 30 5/7/19 LS 2 planning meeting Dismantle and take away YP 11: 00 12: 00 13: 00 Put stairs A-side Modify ITS and SPD for expo. Need crane! Take out manipulator ITS A-side C-side SXL 2 activities w 30 – Mon 22 Jul 2019 17: 00 17: 30 83
ITS cables from A-racks to PP 0 5/7/19 TPC/TR D/TOF LV cables LS 2 planning meeting MID FEE test MCH RO cables test (ST 1 -2 -3) MCH FEE connectors (ST 4 -5) UX 25 activities w 30 – Tue 23 Jul 2019 84
Miniframe activities w 30 – Tue 23 Jul 2019 Install ITS/MFT cooling pipes Install TPC cooling pipes 11/1/19 LS 2 preparatory meeting 85
Put nacele A-side ITS Install I-bars A-side 5/7/19 Remove I-bars C-side LS 2 planning meeting Remove scaffolding C-side Put GEM C-side Take out MWPC 8. 30 A-side C-side SXL 2 activities w 30 – Tue 23 Jul 2019 12: 00 13: 00 17: 30 86
ITS cables from A-racks to PP 0 5/7/19 TPC/TR D/TOF LV cables LS 2 planning meeting MID FEE test MCH RO cables test (ST 1 -2 -3) MCH FEE connectors (ST 4 -5) UX 25 activities w 30 – Wed 24 Jul 2019 87
Miniframe activities w 30 – Wed 24 Jul 2019 Install ITS/MFT cooling pipes Install TPC cooling pipes 11/1/19 LS 2 preparatory meeting 88
ITS Put YP C-side 8. 30 5/7/19 A-side C-side SXL 2 activities w 30 – Wed 24 Jul 2019 Reinstall YP accessories: extensions, handrails, FFU, green crane and manipulator 10: 00 LS 2 planning meeting 17: 30 89
ITS cables from A-racks to PP 0 5/7/19 TPC/TR D/TOF LV cables LS 2 planning meeting MID FEE test MCH RO cables test (ST 1 -2 -3) MCH FEE connectors (ST 4 -5) UX 25 activities w 30 – Thu 25 Jul 2019 90
Miniframe activities w 30 – Thu 25 Jul 2019 Install ITS/MFT cooling pipes Install TPC cooling pipes 11/1/19 LS 2 preparatory meeting 91
ITS Install laser blocks and laser A-side C-side SXL 2 activities w 30 – Thu 25 Jul 2019 Close roof Install scaffolding A-side 8. 30 5/7/19 10: 30 LS 2 planning meeting 12: 00 13: 00 16: 00 92
UX 25 activities w 30 – Fri 26 Jul 2019 5/7/19 TPC/TR D/TOF LV cables LS 2 planning meeting MID FEE test MCH RO connectors (ST 4 -5) ITS cables from A-racks to PP 0 Lift maintenance (AS-724): no access to UX 25 from Friday 26. 7 12: 00 to Saturday 27. 7 18: 00 93
Miniframe activities w 30 – Fri 26 Jul 2019 Install ITS/MFT cooling pipes Install TPC cooling pipes 11/1/19 LS 2 preparatory meeting 94
5/7/19 LS 2 planning meeting A-side ITS C-side SXL 2 activities w 30 – Fri 26 Jul 2019 Cleaning TPC and cleanroom 95
AOB • No LS 2 planning meeting / daily meetings next week 5/7/19 LS 2 planning meeting 96
- Aries tabla de compatibilidad
- Proposal kickoff meeting agenda
- What is meeting and types of meeting
- Types of meeting
- Today meeting or today's meeting
- Initial planning meeting
- Proactive planning and reactive planning
- Aggregate planning is capacity planning for
- Strategic planning vs tactical planning
- Perencanaan agregat
- Examples of aggregate planning
- Goal achievement matrix
- Short, medium and long term planning in education
- Role segmentation workforce planning
- Language policy and planning slideshare
- Aries odia
- Tauro+
- Tauro+
- Tauro+
- Dpg spring meeting
- Student council agenda
- First meeting of the year
- Nara bridg meeting
- Meeting point
- Roslab
- Peraturan technical meeting online
- Meeting ideas
- Introduction meeting agenda
- Clas
- Kinds of company meetings
- Command and staff meeting
- Shiproom meeting
- Meeting point
- Iep meeting script
- Meeting individual care and support needs
- Meeting will begin shortly
- Aua meeting 2018
- Lt meeting
- Paul smith football manager
- Trenching and excavation safety meeting
- Meeting wise checklist
- Webex event breakout rooms
- Bobolhs
- Meeting ground rules
- Intranet upt
- Meeting the needs of guests with kindness and goodwill.
- Welcome to our first meeting
- Iep meeting quotes
- Sum meeting
- Prayer after meeting
- Meeting illustration
- Hero's journey in mulan
- Closing prayer for catechism class
- Housekeeping items meeting
- Engineering meeting topics
- Microelectronics integrity meeting
- Meeting mechanics
- Meeting evaluation
- Math department meeting agenda
- Minus of meeting
- Sales meeting
- Habr
- Type b meeting requests
- Meeting jesus again for the first time
- Clas collaboration meeting
- Medical meeting
- Meeting traffic
- Barbara gustaffe
- Kira & nadine
- Torrance unified school district board meeting
- Navug discussion
- Pid meeting
- _____ you see jody's new dog yesterday?
- Types of company meeting
- Individual needs examples
- Bagley-keene open meeting act
- Touch point meeting
- Care of carm
- Genesys meeting center
- Invitation to stakeholders meeting
- Panda collaboration meeting
- Mpd collaboration meeting
- Transfer of command
- Morning meeting
- Technical meeting agenda
- Email instead of meeting
- Meeting will begin shortly
- Prior lake wrestling schedule
- What bombshell does peeta drop in his interview?
- The meeting will begin shortly
- Condeco room booking panel
- Lithium valley commission meeting
- How to conduct jad sessions
- Lvk meeting
- All in favor say aye gif
- Senior class meeting
- Vista