LS 2 Baseline Planning Marine Pace for BECO
LS 2 Baseline Planning Marine Pace for BE-CO. CO 3 Meeting 27 September 2018
LS 2 BASELINE in EDMS • BE-CO LS 2 Plans (EDMS 1997812): version 1 approved with comments. • Technical note, with presentation of SW and HW choices and work plan for LS 2, has been released as version 2. • Our partner groups are invited to read and provide comments. • This note will be kept up to date with the latest technical decisions. A new EDMS version will be released after approval of the new decisions at CO 3. https: //edms. cern. ch/document/1997812/2 CO 3 Meeting 27 September 2018
LS 2 PLANNING : Key Dates January 2019 Need to accommodate these conflicting guys in January 2019: • Magnet tests PS + SPS from 7 th to 18 th with operational controls • BE-CO annual maintenance days (computer security, OS upgrade, HP HW upgrade) • Preparation of SW releases for LS 2 baseline January 14 th CO 3 Meeting 27 September 2018
LS 2 PLANNING : Key Dates January 2019 • • • PS/SPS Magnet tests with pre-LS 2 controls. LS 2 Baseline milestone (Jan 14 th ) unchanged. 4 days for BE-CO Maintenance to be integrated into the Master Schedule. CO 3 Meeting 27 September 2018
LS 2 PLANNING: Deployment slot for new Timing Generation • Complete dismantling + new installation of GMT racks in Building 874. • Work duration: 2 weeks • Impact on timing distribution to equipment group labs & running machines in LS 2 (except CLEAR and LN 4 which run a dedicated GMT). • Planning options to minimize the impact: Plan A: January 2020, extending BE-CO Maintenance days. ÞOne-week perturbations expected for EQ GP labs. ÞNo perturbation on operation as no running machines during this period. Plan B: January 2019, extending BE-CO days (4 days). Depends on GMT HW procurement. CO 3 Meeting 27 September 2018
Controls Availability during LS 2 Controls OFF Maintenance: 21 to 24 Jan Controls OFF Maintenance + GMT Renovation 2019 22020 LN 3 LEI LN 4 Controls AVAILABLE for Magnets tests: PSB + ISO ->15 Jan 2019 PS ->18 Jan 2019 SPS ->10 Dec 2018 LHC CLEAR AWAKE Continuous operation in sync with LN 4 CO 3 Meeting 27 September 2018 in sync with LN 4 2021
Deployment Strategy of post-LS 2 infrastructure in LS 2 BE-CO Proposal • Libraries and dev tools are released at the coordinated release date. • When do we switch (deploy) from the pre-LS 2 to the post-LS 2 infrastructure? • BE-CO proposal: deploy post-LS 2 CO infrastructure for LN 4 Beam tests (July -Sept 2019) • Aim: validate as much as possible the new post-LS 2 releases • Except for the JDK. Version (8 or 11) to be later decided. • => Constraint on partner groups: by June 2019: • Move OS to CENTOS 7 for all LN 4 FECs • Move all classes to FESA 3 • Release Java applications with post-LS 2 libraries • Is this proposal realistic? CO 3 Meeting 27 September 2018
JDK (Java Development Kit) Problematic • Technical study ongoing in BE-CO for the JDK transition from (current) version 8 to 11. • Testing of JDK 11 components, evaluation of impact. • JDK 11 impact on developers expected high (many changes with respect to JDK 8) • Constraints from Oracle support: • Not possible to migrate to intermediate versions 9 or 10, to minimize the impact on our clients, as those have NO long term support. • JDK 8 Oracle support stops in 2021 => not possible to keep JDK 8 for the whole Run 3. • BE-CO strategy will be proposed at CO 3 by Nov-Dec 2018. • Preliminary idea: • Use of JDK 8 with post-LS 2 releases until end 2019. • Deploy JDK 11 for the latest LS 2 coordinated release before Injectors startup (Jan 2020). CO 3 Meeting 27 September 2018
CO 3 Meeting 27 September 2018