Linac Coherent Light Source LCLS Project Management Control
- Slides: 22
Linac Coherent Light Source (LCLS) Project Management Control System Trish Mast May 14, 2008 Talk NEVMS Status & Overview 1 Trish Mast pmast@slac. stanford. edu
Project Management Controls System (PMCS) Project Controls Team PMCS Structure Rates, Escalation, Burdens Resource Loaded Schedule PMCS Utility Demonstration May 14, 2008 Talk NEVMS Status & Overview 2 Trish Mast pmast@slac. stanford. edu
PMCS Team The PMCS group is composed of 6 Project Controls/Scheduling analysts The PMCS group supports the LCLS Division LCLS LUSI The PMCS group is a mix of contract labor through Deltek, Inc. , and SLAC employees. May 14, 2008 Talk NEVMS Status & Overview 3 Trish Mast pmast@slac. stanford. edu
PMCS Team The PMCS team supports the Project Office and CAMs The team supports both the LCLS and LUSI projects The same tools and processes are used for both the LCLS and LUSI projects May 14, 2008 Talk NEVMS Status & Overview 4 Trish Mast pmast@slac. stanford. edu
Rebaseline! LCLS just completed a rebaseline of the project Lengthy FY 07 Continuing Resolution resulted in approval to rebaseline. LCLS CD 4 moved from March 2009 to July 2010 Total Project Cost (TPC) went from $379 M to $420 M Total Estimated Cost (TEC): $315 M to $352 M Other Project Cost (OPC): $64 M to $68 M Rebaseline completed and approved January 2008 Data for this review is from month ending February 2008 May 14, 2008 Talk NEVMS Status & Overview 5 Trish Mast pmast@slac. stanford. edu
PMCS System Architecture May 14, 2008 Talk NEVMS Status & Overview 6 Trish Mast pmast@slac. stanford. edu
Rates, Escalation, Burdens Rates, Escalation and Burdens are reviewed regularly and updated as needed to provide the most accurate cost baseline. Have defined SLAC, ANL, and LLNL rate structures (for LCLS). Buildup of fully burdened rate is performed in Cobra Overhead: OPC Labor @ 40% Overhead: TEC Non-Labor @ 4. 32%, OPC Non-Labor @ 5. 04% SLAC/LLNL Escalation rates @ 4. 0%/Year ANL Escalation rates @ 4. 5%/Year M&S Escalation Rates use DOE guidelines Basis for Escalation Rates consist of: Laboratory published escalation rates DOE Escalation guidelines P 3 provides the budgeted quantities for each planned resource to Cobra. May 14, 2008 Talk NEVMS Status & Overview 7 Trish Mast pmast@slac. stanford. edu
Resource Breakdown Structure 1 2 3 1 RBS BE WBS 2 3 4 4 5 5 1 2 3 May 14, 2008 Talk NEVMS Status & Overview 8 FUND Trish Mast pmast@slac. stanford. edu
EVMS Statistics The LCLS P 3 Schedule Database consists of 5426 activities Cobra Database consists of 602 control accounts and 2921 workpackages Every resource loaded task in P 3 becomes a work package in Cobra (exception is Turner schedule) Turner Schedule uploaded into P 3 database for critical path analysis only. May 14, 2008 Talk NEVMS Status & Overview 9 Trish Mast pmast@slac. stanford. edu
Resource Loaded Schedules May 14, 2008 Talk NEVMS Status & Overview 10 Trish Mast pmast@slac. stanford. edu
Configuration Controlled Milestones Defined Level 1, 2, 3 Milestones Level 1 controlled by DOE Acquisition Executive Level 2 controlled by DOE Federal Project Director Level 3 controlled by LCLS Project Manager Level 1 -3 Milestones are under formal configuration control. May 14, 2008 Talk NEVMS Status & Overview 11 Trish Mast pmast@slac. stanford. edu
Integrated Schedules May 14, 2008 Talk NEVMS Status & Overview 12 Trish Mast pmast@slac. stanford. edu
Critical Path Analysis Top three critical paths are run and analyzed All constraints removed from database except Funding constraints Shutdown constraints Top three paths to CD 4 are calculated and reviewed each month. May 14, 2008 Talk NEVMS Status & Overview 13 Trish Mast pmast@slac. stanford. edu
PMCS Utility Demo PMCS Utility Reports Monthly Status Reviews Variance Analysis Bottoms Up Contingency Analysis May 14, 2008 Talk NEVMS Status & Overview 14 Trish Mast pmast@slac. stanford. edu
Backup Slides (Note: These backup slides are provided to demonstrate samples of output and reports. The data contained in these samples does not necessarily represent the current PMB) May 14, 2008 Talk NEVMS Status & Overview 15 Trish Mast pmast@slac. stanford. edu
Detailed Cost Estimate Report (DCE) May 14, 2008 Talk NEVMS Status & Overview 16 Trish Mast pmast@slac. stanford. edu
CPR Drilldown (Level 2) May 14, 2008 Talk NEVMS Status & Overview 17 Trish Mast pmast@slac. stanford. edu
BCWS, BCWP, ACWP Report (SPA) May 14, 2008 Talk NEVMS Status & Overview 18 Trish Mast pmast@slac. stanford. edu
Obligation Report (OSCUM) May 14, 2008 Talk NEVMS Status & Overview 19 Trish Mast pmast@slac. stanford. edu
Milestone Dictionary May 14, 2008 Talk NEVMS Status & Overview 20 Trish Mast pmast@slac. stanford. edu
WBS Dictionary May 14, 2008 Talk NEVMS Status & Overview 21 Trish Mast pmast@slac. stanford. edu
Responsibility Assignment Matrix (RAM) May 14, 2008 Talk NEVMS Status & Overview 22 Trish Mast pmast@slac. stanford. edu