Linac 4 commissioning Detailed planning Piotr Skowronski Bettina
Linac 4 commissioning Detailed planning Piotr Skowronski, Bettina Mikulec, Luca Timeo
New DRAFT LS 2 Master Schedule (still to be approved!) DSO tests: • § 23/3 Linac 4, 24/3 Switchyard • W 17 ISTs, w 18 -19 HW commissioning • W 20 -21: continue with 2 weeks of 3 Me. V beam tests coordinated by ABP (weekend of 16/17 th May AUG tests!) • From w 22 Linac 4 fast restart test (during an estimated <2 weeks 24 h operation including weekends; piquet coverage requested) • Then continue with M/A shifts until start of PSB beam commissioning • Weeks 35 -36 beam to Linac 4 dump only (Switchyard closed). • Full piquet + Linac 4 supervisor coverage from w 38 (start of PSB beam commissioning) 2 Injectors Performance Panel 5 March 2020
ISTs Ø Pushing as many tests as possible to be done 2 weeks before the IST period. The ones that are: § Likely to need machine access § Not posing safety issues when powered 3
Hardware Tests OP will work through the OP HW Checklist Ø In parallel execute Dry Runs with equipment experts Ø 1 st of May (Friday) – removes 1 day Ø Ø RF: basic setup during ISTs + HW commissioning EPC: during HW commissioning BI: during ISTs and pre-ISTs 4
2020 Dry Runs 5 Injectors Performance Panel 5 March 2020
2020 Linac 4 Beam Restart – w 20&21 (starting 11 th May) 6 When Primary activity 11 -15/5/2019 Start of the source 18 -20/5/2019 Optimization of intensity at 3 Me. V to deliver 25 m. A with min current. Includes recovery time from AUG tests over the week-end. 21/05/2019 Ascension 22/05/2020 Back up Calibration of autopilot 25 -27/5/2020 -Emittance reconstruction with wire scanner at 3 Me. V for I =15 and 25 m. A -RFQ voltage scan (only down) for I =15 and 25 m. A Calibration of autopilot 28 -29/5/2020 Matching and steering studies at the lowest current Injectors Performance Panel Secondary activity 5 March 2020
2020 Linac 4 Beam Restart – w 22 (starting 25 th May) Start Linac 4 beam commissioning to L 4 dump Monday Tuesday Wednesday Thursday Friday Saturday Sunday Pentecôte! M A OP, ABP, RF, BI OP, ABP, RF, BI OP OP LEBT & RFQ transmission (solenoid and steerer scan) MEBT optimisation to chopper dump MEBT setup: measurements on the wire scanner at 3 Me. V Phasing (includes equipment recommissioning with beam and steering) - Continue phasing - BCT/BPM calibrations - Other BI checks OP checklist – remaining checks - Stripping foil measurements - Logging checks LEBT/MEBT equipment commissioning with beam - Phasing bunchers 1&2 Initial chopping: measurements on wire scanner 2 for chopped and unchopped beam - BCT/BPM calibrations - Interlocks DTLPIMS - Continue phasing - BSM 1 equipment calibration + phasing validation measurements - Other BI checks - Stripping foil measurements incl. steering check - Stripping foil measurements Continue phasing - Final steering to dump - OP checklist - Stripping foil measurements - Logging checks Interlock checks; OP checklist N 7 - Autopilot after RFQ OP Checklist Injectors Performance Panel - Logging checks OP checklist – remaining checks 5 March 2020
2020 Linac 4 Beam Restart – w 23 (starting 1 st June) …………. . Monday Tuesday Wednesday Start Linac 4 TL beam commissioning Thursday Friday Saturday Basic beam comm. finished Sunday Lundi de Pentecôte! OP RF, ABP, OP OP, ABP, RF OP, BI, RF OP OP M Profile measurements along linac with Semgrids and wire scanners - FB/FF setup with beam - Offline check of profiles - MCS, RBAC - FB/FF setup with beam - If needed, rematching of MEBT Potentially retuning of phasing, optics checks - Final chopping efficiency check - BI calibrations and checks for TL - Debuncher setup Profile measurements up to LBE with Semgrids and Wire Scanners - Check logging - Kick response measurements A Emittance measurements L 4 Z (Semgrids and wire scanners) - FB/FF setup with beam - Offline check of profiles - MCS, RBAC - FB/FF setup with beam - If needed, rematching of MEBT - Potentially retuning of phasing, optics checks - Clone cycle/ppm - BSM 2 equipment calibration - Debuncher phasing - LBE emittance Finish TL OP measurements checklist (Sem. G & WS) - Optics corrections Set BLM and watchdog thresholds New profile measurements along linac with Semgrids and wire scanners - Beam steering to LBE - Interlock checks - TL OP Checklist - TL OP checklist - Set BLM and watchdog thresholds Check logging N - OP Checklist - Pulse flatness checks 8 Injectors Performance Panel Reference measurements 5 March 2020
2020 Linac 4 Beam Setup (part 1) – focus on optics Long. painting study Week 1 Week 2 Week 3 Optics ready … Week 6 Main activities Week 7 Experts needed W 24 (8 -12 June) RFQ MDs (1 d) Sequencer tests (1 d) BSM 2 vs. debuncher voltage scan, longitudinal emittance (1 d) 2 d spare for outstanding equipment/controls/application issues RF, ABP, OP W 25 (15 -19 June) Study of phase spread (BSM 1 and BSM 2) vs. PIMS quadrupole settings with and without debuncher ABP W 26 (22 -26 June) Study of longitudinal painting; synchronisation of debuncher phase modulation with PIMS energy modulation RF, ABP, OP How to measure dispersion for varying debuncher settings; comparative measurements ABP W 28 (6 -10 July) Clone all later needed beams PS stray field compensation checks Start setting up sequencer for different tasks OP, EPC W 29 (13 -17 July) Verification of matching for 3 debuncher settings ABP, OP W 30 (20 -24 July) Emittance measurements in LBE, dispersion measurements, response matrix measurements for 3 debuncher settings; fine-tuning of optics correction OP, ABP W 27 (29/6 -3/7) 9 Injectors Performance Panel 5 March 2020
2020 Linac 4 Beam Setup (part 2) – cycle preparation Week 8 Week 9 Week 10 … Beam to L 4 dump All beams ready for PSB Weeks 12 -13 Week 14 Main activities Experts needed W 31 (27 -31 July) Set up the following cycles (1 cycle/day including reference measurements, setting management and documentation): PSB comm. beam, LHCPILOT, LHCINDIV, TOF low int. (4 rings), MTE low intensity OP W 32 (3 -7 Aug) Set up the following cycles (1 cycle/day including reference measurements, setting management and documentation): MTE intermediate intensity, LHC 25, BCMS 25, AD, MTE nominal OP W 33 (10 -14 Aug) Set up the following cycles (1 cycle/day including reference measurements, setting management and documentation): NORMGPS, NORMHRS, STAGISO, TOF, EAST 1/2 OP W 34 (17 -21 Aug) Finish setting up all cycles with EAST+parasitic TOF Stability measurements and cleaning up of all remaining issues OP W 35 (24 -28 Aug) Beam to L 4 dump – program tbd. ABP, OP, ? W 36 (31/8 -4/9) Beam to L 4 dump – program tbd. ABP, OP, ? Final verification of all beams before first beam to PSB OP W 37 (7 -11 Sept) 10 Injectors Performance Panel 5 March 2020
Final Remarks Ø Most likely the commissioning start will be delayed by additional 2 days § Tests of General Emergency Stops (Arrêts d’Urgence Généraux) on May 26 § The schedule will adapt Ø Commissioning is scheduled for 2 weeks § Assumes that the source is already operational Remaining time is for setup of all operational beams, machine development and performance optimization Ø Started inserting the schedule to the ASM tool Ø § ASM = Accelerator Schedule Management 11 Injectors Performance Panel 5 March 2020
ASM 12 Injectors Performance Panel 5 March 2020
ASM – extremely cumbersome to use (1) Ø Every event needs to be created from scratch § Should be possible to clone existing ones Ø Can not easily move events: each time one needs to open event, and edit manually end and start date § Should be able to easily shift single events and also groups of events In case of a down time one should be able to insert “downtime block” and all events in selected time range should be automatically postponed Ø Each time one refreshes the page it comes back to the current date. Ø 13
ASM – extremely cumbersome to use (2) Ø Selecting every field requires typing name of desired value. § The worst example are items of the checkout lists: • “LINAC 4 -> beam commissioning -> lebt -> beam instrumentation -> [bct, faraday cup, . . . ]” § One has to add separately all the items in the group bct, faraday cup, etc. One should be able to add only the group “LINAC 4 -> beam commissioning -> lebt -> beam instrumentation” § Each time one needs to type “LINAC 4 -> beam commissioning -> l” to select an item § Selection should be reduced to values defined for given machine § Selection needs to be more clever, f. g. drop down menu(s) § One could copy from the machine checkout list web-tool that offers much better navigation 14