LINAC 2 & 3 EYETS 16 -17 SCHEDULE Linac 2&3/PSB/PS/TT 2 EYETS 2016– 2017

LINAC 2 & 3 EYETS 16 -17 SCHEDULE Linac 2&3/PSB/PS/TT 2 EYETS 2016– 2017 coordination meeting 26/Jan/2017 Indico: 578940 C. Mastrostefano & A. Berjillos

Outline: • Length of EYETS 2016 -2017 • Linac 2 planning in the coming

Outline: • Length of EYETS 2016 -2017 • Linac 2 planning in the coming weeks • Linac 3 planning in the coming weeks 26 -Jan-2017 Linac 2 & 3 machine activities for the EYETS 2016 -2017. C. Mastrostefano & A. Berjillos 2

Stop of the Linac 2 Monday 12 th December 2016 (Source stay ON) LINAC

Stop of the Linac 2 Monday 12 th December 2016 (Source stay ON) LINAC 2 Access to Linac 2 Thursday 5 th January 2017 Close Linac 2 Friday 10 th March 2017 Access to SWY area: Thur 15/12/16 to Thur 22/12/16@16: 00 Thur 05/01/17 to Fri 31/03/17@12: 00 LINAC 3 Stop of the Linac 3 Wednesday 14 th December 2016 26 -Jan-2017 Restart ion source Monday 27 th February 2017 Linac 2 & 3 machine activities for the EYETS 2016 -2017. C. Mastrostefano & A. Berjillos 3

LINAC 2 planning, weeks 4 & 5/ 2017 Lift maintenance proposal: Installation of a

LINAC 2 planning, weeks 4 & 5/ 2017 Lift maintenance proposal: Installation of a beam for the reinforcement of false floor 363/1 -001 ----- 27/01/2017 26 -Jan-2017 Linac 2 & 3 machine activities for the EYETS 2016 -2017. C. Mastrostefano & A. Berjillos 4

SWY area planning, weeks 4 & 5/ 2017 E 0 equipment already in buffer

SWY area planning, weeks 4 & 5/ 2017 E 0 equipment already in buffer zone? • Crane already removed LINAC 2 planning available on: • EDMS 1742697 • www. cern. ch/LS 1 to. LS 2 26 -Jan-2017 Linac 2 & 3 machine activities for the EYETS 2016 -2017. C. Mastrostefano & A. Berjillos 5

LINAC 3 planning (weeks 4&5, 2017) LINAC 3 planning available on: • EDMS 1742692

LINAC 3 planning (weeks 4&5, 2017) LINAC 3 planning available on: • EDMS 1742692 • www. cern. ch/LS 1 to. LS 2 26 -Jan-2017 Linac 2 & 3 machine activities for the EYETS 2016 -2017. C. Mastrostefano & A. Berjillos 6

Contact person: Facility coordinators: • • C. Mastrostefano: Christian. mastrostefano@cern. ch A. Berjillos :

Contact person: Facility coordinators: • • C. Mastrostefano: Christian. mastrostefano@cern. ch A. Berjillos : aurelio. berjillos@cern. ch 167850 26 -Jan-2017 1663067 Linac 2 & 3 machine activities for the EYETS 2016 -2017. C. Mastrostefano & A. Berjillos 7

Thank you for your attention. Q’s? 26 -Jan-2017 Linac 2 & 3 machine activities