Limiting Oxygen Concentration LOC Work Update Steve Summer

  • Slides: 31
Download presentation
Limiting Oxygen Concentration (LOC) Work Update Steve Summer Project Engineer Federal Aviation Administration Fire

Limiting Oxygen Concentration (LOC) Work Update Steve Summer Project Engineer Federal Aviation Administration Fire Safety Branch, AAR-440 IASFPWG – Ottawa, Canada International Aircraft Systems Fire Protection Working Group Ottawa, Canada July 8 - 9, 2003 07 -08 -03

LOC Testing – Work Update Ø Conducted sea level (SL) testing with a J-57

LOC Testing – Work Update Ø Conducted sea level (SL) testing with a J-57 engine igniter Ø Conducted SL testing with a short duration arc from oil burner transformer Ø Measured voltage/current at spark gap and calculated energy for both spark/arc generator Ø Composed report of all data generated to date with the various ignition sources (AR-02/79)—due out shortly IASFPWG – Ottawa, Canada 07 -08 -03

Facilities – Pressure Chamber IASFPWG – Ottawa, Canada 07 -08 -03

Facilities – Pressure Chamber IASFPWG – Ottawa, Canada 07 -08 -03

Facilities – Pressure Chamber Ø 353 ft 3 pressure vessel • Working pressure of

Facilities – Pressure Chamber Ø 353 ft 3 pressure vessel • Working pressure of 650 psi. • Attached vacuum pump used to evacuate chamber to reduced pressures seen at altitude. • Not capable of simulating temperatures seen at altitude. IASFPWG – Ottawa, Canada 07 -08 -03

Facilities - LOC Test Article Ø 9 ft 3 simulated fuel tank placed inside

Facilities - LOC Test Article Ø 9 ft 3 simulated fuel tank placed inside of vessel equipped with: • Bottom surface heaters. • 12 thermocouples. • 2 piezoresistive pressure transducers mounted behind sintered porous metal discs. • Interchangeable pressure relief mechanism. F¼-in. aluminum plate. FFoil diaphragm. • Spark gap. F 2 tungsten electrodes with controllable gap alignment and spacing IASFPWG – Ottawa, Canada 07 -08 -03

Apparatus – LOC Testing IASFPWG – Ottawa, Canada 07 -08 -03

Apparatus – LOC Testing IASFPWG – Ottawa, Canada 07 -08 -03

Apparatus – LOC Testing IASFPWG – Ottawa, Canada 07 -08 -03

Apparatus – LOC Testing IASFPWG – Ottawa, Canada 07 -08 -03

Ullage Vapor Sampling IASFPWG – Ottawa, Canada 07 -08 -03

Ullage Vapor Sampling IASFPWG – Ottawa, Canada 07 -08 -03

LOC Testing Apparatus Ø Ignition Sources • 10 k. V Oil burner transformer operating

LOC Testing Apparatus Ø Ignition Sources • 10 k. V Oil burner transformer operating at ~30 m. A provided both long (~1 second) and short (~0. 1 second) arcs • J-57 Engine spark igniter provided a very short (~175 msecond) spark • 3" x 6" x 1" metal block heated by two cartridge heaters to temperature in excess of 1400°F Ø Energy Measurements • Voltage and current traces were taken using a HV and current probe at the spark gap connected to oscilloscope IASFPWG – Ottawa, Canada 07 -08 -03

Oil Burner Transformer Voltage & Current Traces IASFPWG – Ottawa, Canada 07 -08 -03

Oil Burner Transformer Voltage & Current Traces IASFPWG – Ottawa, Canada 07 -08 -03

Test Program Ø JP-8 LOC Tests • Mass Loading ~ 4. 5 kg/m 3

Test Program Ø JP-8 LOC Tests • Mass Loading ~ 4. 5 kg/m 3 • Ambient pressure corresponding to altitudes of 0, 10, 20, 30 and 38 kft • Ullage oxygen concentrations ranging from 21% to below the determined LOC • Tests conducted with two different pressure relief mechanisms F¼-in. aluminum plate – Ignition = movement of plate FFoil diaphragm – Ignition = rupture of foil IASFPWG – Ottawa, Canada 07 -08 -03

Test Program (cont. ) Ø Tests conducted initially at all altitudes with long duration

Test Program (cont. ) Ø Tests conducted initially at all altitudes with long duration oil burner transformer arc (~0. 5 J, 1 s) Ø Subsequent tests conducted with various ignition sources at sea level in effort to determine any variation of LOC with ignition source • Short duration oil burner transformer arc (~0. 08 J, 0. 1 s) • J-57 Engine igniter spark (~0. 5 J, 175 ms) • Hot surface vapor ignition (HSVI) IASFPWG – Ottawa, Canada 07 -08 -03

LONG DURATION OIL BURNER TRANSFORMER ARC TEST RESULTS IASFPWG – Ottawa, Canada 07 -08

LONG DURATION OIL BURNER TRANSFORMER ARC TEST RESULTS IASFPWG – Ottawa, Canada 07 -08 -03

Aluminum Plate Relief Mechanism IASFPWG – Ottawa, Canada 07 -08 -03

Aluminum Plate Relief Mechanism IASFPWG – Ottawa, Canada 07 -08 -03

Foil Diaphragm Relief Mechanism IASFPWG – Ottawa, Canada 07 -08 -03

Foil Diaphragm Relief Mechanism IASFPWG – Ottawa, Canada 07 -08 -03

IASFPWG – Ottawa, Canada 07 -08 -03

IASFPWG – Ottawa, Canada 07 -08 -03

IASFPWG – Ottawa, Canada 07 -08 -03

IASFPWG – Ottawa, Canada 07 -08 -03

IASFPWG – Ottawa, Canada 07 -08 -03

IASFPWG – Ottawa, Canada 07 -08 -03

IASFPWG – Ottawa, Canada 07 -08 -03

IASFPWG – Ottawa, Canada 07 -08 -03

IASFPWG – Ottawa, Canada 07 -08 -03

IASFPWG – Ottawa, Canada 07 -08 -03

IASFPWG – Ottawa, Canada 07 -08 -03

IASFPWG – Ottawa, Canada 07 -08 -03

J-57 ENGINE SPARK IGNITER TEST RESULTS IASFPWG – Ottawa, Canada 07 -08 -03

J-57 ENGINE SPARK IGNITER TEST RESULTS IASFPWG – Ottawa, Canada 07 -08 -03

IASFPWG – Ottawa, Canada 07 -08 -03

IASFPWG – Ottawa, Canada 07 -08 -03

IASFPWG – Ottawa, Canada 07 -08 -03

IASFPWG – Ottawa, Canada 07 -08 -03

SHORT DURATION OIL BURNER TRANSFORMER ARC TEST RESULTS IASFPWG – Ottawa, Canada 07 -08

SHORT DURATION OIL BURNER TRANSFORMER ARC TEST RESULTS IASFPWG – Ottawa, Canada 07 -08 -03

Short Duration Test Results IASFPWG – Ottawa, Canada 07 -08 -03

Short Duration Test Results IASFPWG – Ottawa, Canada 07 -08 -03

HOT SURFACE VAPOR IGNITION TESTING (HSVI) IASFPWG – Ottawa, Canada 07 -08 -03

HOT SURFACE VAPOR IGNITION TESTING (HSVI) IASFPWG – Ottawa, Canada 07 -08 -03

HSVI Testing Ø Test Setup • Setup was identical to the spark/arc ignition testing.

HSVI Testing Ø Test Setup • Setup was identical to the spark/arc ignition testing. • In place of spark, a 3" x 6" x 1" metal block was heated by two cartridge heaters for use as the ignition source. • Conducted only at sea level conditions. IASFPWG – Ottawa, Canada 07 -08 -03

HSVI Test Results Ø At 21% O 2, ignition was achieved at a hot

HSVI Test Results Ø At 21% O 2, ignition was achieved at a hot surface temperature (HST) of approximately 1350ºF. Ø A half-dozen other tests were conducted at O 2 concentrations ranging from ~11. 5 – 14%. • Though some “puffs” of smoke could be seen as the HST approached ~1200º F, no ignitions occurred. Ø Therefore, HSI within the fuel tank provides no more of a threat than spark ignition. IASFPWG – Ottawa, Canada 07 -08 -03

Conclusions Ø LOC at SL through 10 kft is ~12%, increasing linearly through 40

Conclusions Ø LOC at SL through 10 kft is ~12%, increasing linearly through 40 kft to ~14. 5% Ø Little effect seen on SL LOC due to ignition source • • Long duration arc: 12% High powered spark: 12. 3% Short duration arc: 12. 9% HSVI: ? ? IASFPWG – Ottawa, Canada 07 -08 -03

Future LOC Work Ø Currently working with a very high energy spark (>20 J)

Future LOC Work Ø Currently working with a very high energy spark (>20 J) • 120 Vac, 400 cycle hard short to ground • Will be placing in the tank within the next week. • To commence testing shortly thereafter. Ø Technote AR-02/79 due out shortly IASFPWG – Ottawa, Canada 07 -08 -03