LHC Installation Status Master Schedule Content Global Installation
LHC Installation Status & Master Schedule Content Global Installation Status Tour of the LHC: detailed status and plans Summary 24 October 2006 Sylvain Weisz - LEMIC
Global Installation Status Sector QRL Magnet Interconnection Straight sections Closure 7 -8 Cold tested 100% in place In progress November 06 8 -1 Cold tested 100% in place In progress January 07 4 -5 Pressure tested 99% in place In progress January 07 3 -4 Pressure tested 97% in place In progress 5 -6 Pressure tested 95% in place Starts November 06 6 -7 Pressure tested In progress 2 -3 Pressure tested In progress 1 -2 Installed 24 October 2006 Sylvain Weisz - LEMIC
Sector 7 -8 n n All cold elements in place, including DFBAN(7 R) & DFBAO (8 L) Interconnections in progress: 8 sub-sectors (out of 14) are completed Line N cables inserted in Dispersion Suppressor 7 R: ELQA Ok LSS 8 L Ø Ø Cold parts § Interconnection DFBAO-HCM/LCM in progress § Interconnections done for low-β/DFBX/D 1, Q 4 -D 2/DFBMA, Q 5/DFBMC Warm parts § All components in place (except large beam pipe between D 1 -D 2) § NEG activated in Q 4. L 8 -Q 5. L 8 sub-sector 10 -11 mbar 24 October 2006 Sylvain Weisz - LEMIC
LSS 8 Left 24 October 2006 Sylvain Weisz - LEMIC
Interconnection ends week 45 ~2 Wk delay on DFBAP 3 weeks: global leak and pressure test DFBLA on critical path for Sector 8 -1 ELQA and flushing Start cool-down week 51 Let 7 -8 floating to Connect 8 -1 to QUI Start power tests mid-March 2007 24 October 2006 Sylvain Weisz - LEMIC
Sector 4 -5 n LSS 4 R Ø Ø n RF installation in progress: cavities (ACS), damper (ADT) and pick-up (APWL) in place RF wave guides in place, connection to cavities in progress Klystron installation in progress Interconnection D 4 -Q 5/DFBML and Q 6/DFBMG in progress Arc 4 -5 and DS Ø All cryo-magnets (except SSS 184) are in place: n Ø n SSS 184 was reloaded and is now in SMI 2 for repair (expected back in place on 29/10) Interconnections in progress, nominal rate consolidated Cryostat closed by mid-January LSS 5 L Ø Ø Short circuit tests done in RR 53 and USC 55 Low-β, DFBX, D 1(6 MBXW), TAN and D 2 in place 24 October 2006 Sylvain Weisz - LEMIC
Interconnection ends week 02 DFBLD is late for Sector 4 -5 DFBLD connected for pressure test Start cool-down late March 2007 Start power tests early June 2007 24 October 2006 Sylvain Weisz - LEMIC
Sector 5 -6 & 6 -7 n LSS 5 R Ø Ø n Arc 5 -6 and DS Ø n Ø Ø UA 63: short circuit tests in progress (8 th zone out of 15) US/UX 65: installation of QULA in progress UA 67: power converters in place, cabling (AC, DC, Control & Water cooled) in progress Arc 6 -7 and DS Ø n Cryo-magnet transport in progress: 153 MB and 49 SSS in place LSS 6 L/LSS 6 R Ø n Low-β, DFBX, D 1(6 MBXW) and TAN in place UJ 56 -RR 57: power converters & energy extraction systems (DQR/DQS) in place short circuit tests start mid-November Cryo-magnet installation: 52 dipoles and 26 SSS in place (24/10/2006) No passage through 7 -8 & 8 -1 from Monday to Thursday due to interconnection work transport of cryo-dipoles and special SSS during week-ends, arc SSS via UX 65 LSS 7 L/R Ø Ø Straight section: all services completed UJ 73 & UJ 76: power converters and energy extraction systems in place short circuit tests start mid-December 24 October 2006 Sylvain Weisz - LEMIC
No dipole transport from mid-December to January: Cool-down of sector 7 -8 (ambiant temp. to 80 K) No time to perform nominal Hardware Commissioning in 2007 4 weeks for cool-down: crude calibration & tuning of cryo. loops 4 weeks for power tests: restrict to injection energy 24 October 2006 Sylvain Weisz - LEMIC
Sector 1 -2 & 2 -3 n Sector 1 -2 Ø Ø n LSS 2 L/LSS 2 R Ø Ø Ø n Water cooled cables installation in progress in UA 23, done in UA 27 Air treatment and cooling units installation close to completion in UA 23/27 Installation of power converters in progress in UA 23, done in UA 27 Arc 2 -3 and DS Ø Ø n QRL installation completed: pressure tests scheduled October 28 th QRL work behind us! Installation of support jacks in progress Cryo-magnet installation in progress: 40 dipoles and 6 SSS in place QRL jumper preparation done LSS 3 L/R Ø Ø 24 October 2006 Installation of Power Converters in UJ 33 completed, PC cabling just started DSLC (cryogenic power line) installation in progress Sylvain Weisz - LEMIC
Last DFB’s in May 07 Delays installation of low-β in LSS 2 L Other cryo-magnets in place by March 07 Closure of LHC by end of August 07 (incl. leak & pressure tests) Global operation tests with 7 Sectors in // Preparation for beam 1 week for Sector 1 -2 24 October 2006 Sylvain Weisz - LEMIC
Main Installation Milestones o o o o End of interconnect in Sector 7 -8: week 45 (mid-November) Start of cool-down of Sector 7 -8: week 51 (mid-December) Start of power tests in Sector 7 -8: mid-March 07 End installation of cryo-magnets (except LSS 2 L low-β): end of March 07 LHC Closure (including leak & pressure tests): end of August 07 End of power tests up to injection energy: mid-November 07 Ready for beam commissioning at 450 Ge. V: end of November 07 24 October 2006 Sylvain Weisz - LEMIC EDMS document #102509
Summary n n n n n QRL: all sectors ready, pressure test of last sector on October 28 th Magnet transport: on track to install most LHC magnets by March 07 (861 MB, 249 Arc SSS and 58 Special SSS in place today) Interconnection: on-going at nominal rate in 4 sectors Sector 7 -8 closed by mid-November Installation of power converters (>80%) and short-circuit test (>50%) DFB delivery: DFBA (4/16), DFBM (10/23), DBX (5/8) Warm beam-pipe installation in progress in LSS 8 L/R, LSS 1 L & LSS 4 R 2006 objective: cool-down Sector 7 -8 by the end of the year LHC Master Schedule very challenging and without contingency Time allocated to cool-down and power tests is too short to achieve a complete hardware commissioning in 2007 24 October 2006 Sylvain Weisz - LEMIC
- Slides: 13