LHC Access System Status and Planning August 2006

  • Slides: 17
Download presentation
LHC Access System – Status and Planning August 2006 Elena Manola-Poggioli Eva Sanchez-Corral TS-CSE

LHC Access System – Status and Planning August 2006 Elena Manola-Poggioli Eva Sanchez-Corral TS-CSE on behalf of the LHC Access Project Team August 2006

LHC Access System • LHC Access Control System – LACS – Supports the physical

LHC Access System • LHC Access Control System – LACS – Supports the physical equipment regulating the access to the accelerator – Allows operation of access equipment • LHC Access Safety System – LASS – Provides interlock between EIS-faisceau and EIS-acces – Ensures the collective protection of personnel from the radiation hazards August 2006

LHC Access System LHC Access Control • • • 34 Access Points 95 controlled

LHC Access System LHC Access Control • • • 34 Access Points 95 controlled sector doors 65 interlocked end-of-zone doors 26 interlocked ‘portes crionolines + ventilation’ 17 interlocked movable shielding walls 200 junction boxes 170 racks 110 surveillance cameras 200 controllers (PLCs, PCs) Control system from CCC and experiments Supervision system August 2006

LHC Access System LHC 0: design validation August 2006

LHC Access System LHC 0: design validation August 2006

LHC Access System Installation Status: sector doors and junction boxes • Sector doors: –

LHC Access System Installation Status: sector doors and junction boxes • Sector doors: – Point 8: 90% – Point 7: 90% – Point 1: 75% August 2006 • Junction Boxes: – – Point 8: 7: 1: 6: 100% 90%

LHC Access System August 2006

LHC Access System August 2006

LHC Access System Access points - Underground • Installation of the access points in

LHC Access System Access points - Underground • Installation of the access points in UX 85, UJ 83 and UJ 87 in progress • Complete test of the access point UX 85, including the IHM and control from the CCC, supervision and maintenance procedures -> mid September • Circulation of personnel not affected August 2006

LHC Access System Installation Strategy – Underground Access Points • • Not used for

LHC Access System Installation Strategy – Underground Access Points • • Not used for personnel passage before the definite closure of the area (installation of the grids) Configured for biometric recognition and RFID badge identification August 2006

LHC Access System August 2006

LHC Access System August 2006

LHC Access System Access for the Pits Head • Prerequisites: • Constraints: minimize the

LHC Access System Access for the Pits Head • Prerequisites: • Constraints: minimize the impact on the personnel flow during the LHC installation period • Strategy: – – – Access points UX 85, UJ 83 and UJ 87 integrated and validated Access Help Desk manned and operational User information: • Posters, group secretariats, TCC, bulletin – Biometric recognition disabled – Use of the new CERN site access cards (equipped with MIFARE RFID chips) for the personal identification – Under validation • Current CERN site ACCESS magnetic cards is being progressively replaced by the new RF cards (TS/CSE responsibility) – – Dosimeters not required during the LHC installation Before LHC start-up, users shall be requested to get a dosimeter equipped with the RFID chips August 2006

LHC Access System • New CERN Site Access Cards: August 2006

LHC Access System • New CERN Site Access Cards: August 2006

LHC Access System • Persons working on the Points 7 and 8 will be

LHC Access System • Persons working on the Points 7 and 8 will be asked to retrieve the new access cards at the Building 55 already in September • Access to the LHC interlocked areas in the LHC operation phase: personnel dosimeter equipped with the RFID chip and biometric identification August 2006

LHC Access System • Short term objectives Points 7 and 8: – PM 85:

LHC Access System • Short term objectives Points 7 and 8: – PM 85: • Dismantling of the existing system: beginning October (1 week) • Installation and integration of the new system (1 week) • Presence of the security guardian required during dismantling and installation • Operational mid October – PM 76 operational end October – PZ 85 operational beginning November August 2006

LHC Access System Global Planning • Installation and Commissioning detail planning – – Integrated

LHC Access System Global Planning • Installation and Commissioning detail planning – – Integrated within the LHC IC General plan (TS/IC) • EDMS 769853 Machine and Experiments • Deployment: • Tests: • Follow-up with MTF – – – – P 8, P 7, P 4 -> 2006 P 1: January 2007 P 5: February 2007 P 3: March 2007 P 6: April 2007 P 2: May 2006 Final installation (inter-site doors, biometric identification, dosimeters with RFIDs, grids) June 2007 • Site functional tests per site at the end of the site installation; in coordination with machine groups concerned • Global and Final tests – at the end of the installation during summer 2007 – special requirements (coordination with different groups concerned, access restricted to personnel involved in tests) August 2006

LHC Access System Tests • Tests strategy defined all along the I&C phases till

LHC Access System Tests • Tests strategy defined all along the I&C phases till transfer to Operation and Maintenance – EMDS 497865 – HW, SW Functional and Safety (INB requirements !) • Tests Phases: • • • Local acceptance Integration Functional Site Functional Inter-site Global Tests and Final Tests AB/DSO INB Tests • Roles and Responsibilities being defined with different groups concerned – project team, contractors, HC, equipment groups, experiments, AB August 2006

LHC Access System LASS General Status • Safety software under development • Functional software

LHC Access System LASS General Status • Safety software under development • Functional software (Man machine interfaces. . ) under development • Electrical design: power supplies, rack installation drawings, LASS command interface (Pupitre), cable loop – delays, but progressing well recently • Goal: follow-up with the installation the pace of the LACS installation in order to synchronize the testing August 2006

LHC Access System Conclusions • Objectives: – LASS and LACS operational in LHC 7,

LHC Access System Conclusions • Objectives: – LASS and LACS operational in LHC 7, LHC 8, CCC by mid November 2006 • All pieces of the ‘LEGO’ are there or under production • Planning relies on: – No major technical issues during integration – Contractors and subcontractors respect the deadlines August 2006