Lessons Learned from Commissioning of Advanced Detectors May

  • Slides: 16
Download presentation
Lessons Learned from Commissioning of Advanced Detectors May 18, 2015 Daniel Sigg LIGO Hanford

Lessons Learned from Commissioning of Advanced Detectors May 18, 2015 Daniel Sigg LIGO Hanford Observatory G 1500643 Lessons learned from commissioning of Advanced Detectors

Lessons q q Good QA & experience lead to quick progress Locking Ø Arm

Lessons q q Good QA & experience lead to quick progress Locking Ø Arm Length Stabilization (ALS) is working Ø Dual Recycled Michelson Locking (DRMI) is working (3 f technique) Ø Alignment stability is important with low frequency seismic systems q q q q Low frequency seismic isolation systems at Virgo Squeezing at GEO Underground and cryogenic at KAGRA Low finesse cavities causes alignment offset problems High Q resonances and uncontrolled DOFs Thermal adjustments not needed at 20 W input ESD charging Issues Parametric Instabilities G 1500643 Lessons learned from commissioning of Advanced Detectors 2

Progress 100 90 80 70 60 50 40 30 20 10 0 LLO LHO

Progress 100 90 80 70 60 50 40 30 20 10 0 LLO LHO O 1 -lower O 1 -upper 0 20 40 60 80 10 0 12 0 14 0 16 0 18 0 20 0 22 0 24 0 26 0 28 0 30 0 32 0 34 0 36 0 Inspiral Range, Mpc a. LIGO Commissioning Progress Days since start of commissioning G 1500643 Lessons learned from commissioning of Advanced Detectors 3

Sensitivity y ar n i m i l Pre G 1500643 Lessons learned from

Sensitivity y ar n i m i l Pre G 1500643 Lessons learned from commissioning of Advanced Detectors 4

Preliminary G 1500643 Lessons learned from commissioning of Advanced Detectors 5

Preliminary G 1500643 Lessons learned from commissioning of Advanced Detectors 5

L 1 Noise Model G 1500643 Lessons learned from commissioning of Advanced Detectors 6

L 1 Noise Model G 1500643 Lessons learned from commissioning of Advanced Detectors 6

Full Lock DRMI 3 f Arm Length Stabilization Switching to Nominal Sensors & Adjusting

Full Lock DRMI 3 f Arm Length Stabilization Switching to Nominal Sensors & Adjusting operating point Refl. Locking Refl. Power [W] Intensity Power [W] Locking G 1500643 Lessons learned from commissioning of Advanced Detectors Time [s] 7

Squeezing at GEO q q q Squeezing long term stable around 3 d. B

Squeezing at GEO q q q Squeezing long term stable around 3 d. B After researching phase control and auto-alignment now focus on losses Data taking runs well, fully automated locking G 1500643 Lessons learned from commissioning of Advanced Detectors 8

Underground & Cryogenic at KAGRA G 1500643 Lessons learned from commissioning of Advanced Detectors

Underground & Cryogenic at KAGRA G 1500643 Lessons learned from commissioning of Advanced Detectors 9

Parametric Instabilities G 1500643 Lessons learned from commissioning of Advanced Detectors 10 Evans et

Parametric Instabilities G 1500643 Lessons learned from commissioning of Advanced Detectors 10 Evans et al. , Phys. Rev. Lett. 114, 161102 (2015)

Parametric Instabilities (3) Mechanical G 1500643 Lessons learned from commissioning of Advanced Detectors Optical

Parametric Instabilities (3) Mechanical G 1500643 Lessons learned from commissioning of Advanced Detectors Optical 11

Parametric Instabilities (2) Number of Unstable Modes Depends on ROC Thermal control of ROC

Parametric Instabilities (2) Number of Unstable Modes Depends on ROC Thermal control of ROC can work for small N G 1500643 Lessons learned from commissioning of Advanced Detectors 12

Electro Static Drive 250 V Recharging G 1500643 Lessons learned from commissioning of Advanced

Electro Static Drive 250 V Recharging G 1500643 Lessons learned from commissioning of Advanced Detectors 13

Electro Static Drive (2) q Charge is a problem, can be 10 s (even

Electro Static Drive (2) q Charge is a problem, can be 10 s (even >100) of Volts Ø Ø q First contact leaves a charge behind Field lines must terminate somewhere (e. g. ring heater) Drive strength depends on charge, adds a linear term Charge is not uniform Injecting ions into the vacuum did not fix the problem Ø Hard to reach the back surface q Recharging does occur Ø Ion pump main culprit, needs to be shielded or removed q Test masses need to be discharged before pumping Ø Seems to stay discharged without an ion pump G 1500643 Lessons learned from commissioning of Advanced Detectors 14

Electro Static Drive (4) G 1500643 Lessons learned from commissioning of Advanced Detectors 15

Electro Static Drive (4) G 1500643 Lessons learned from commissioning of Advanced Detectors 15

Summary q q q Sensitivity of initial detectors surpassed quickly Robust locking achieved Squeezing

Summary q q q Sensitivity of initial detectors surpassed quickly Robust locking achieved Squeezing is now ready and robust (GEO) Parametric instabilities are real; need to be dealt with Test mass charge is a problem Ø Discharging effort underway q What’s left? Ø Ø Ø High power operations: thermal control, PI, alignment instability Low frequency noise hunting & controls optimization Make the seismic system work during bad weather Damping of high Q modes Backscatter mitigation G 1500643 Lessons learned from commissioning of Advanced Detectors 16