Lecture 5 Scheduling Scheduling Scheduling Planning What to
- Slides: 30
Lecture 5 Scheduling
Scheduling
Scheduling Planning: What to do and in what order Scheduling: When to do required actions (given required resources) § Assume we have a partial ordering of actions required to achieve our goals. § Total orders need to be relaxed. (We will not cover this. ) § Actions have: § Duration § Required consumable resources § Required durable/reusable resources § Initial state has a specification of available resources. § The task of scheduling is to provide an optimal schedule for the performance of the required actions. Optimal may be in terms of time (generally shortest) or resources (generally minimal use) or both.
Our Example Continued. . . Go Shopping Initial state Make Cake Eat Cake Wait Goal Go Shopping Make Cake Action Consumes Uses Duration Go Shopping -1 Mix 1 Mike 20 min Wait - - 60 min Make Cake 1 Mix, -1 Cake 1 Oven 30 min Eat Cake 1 Mike 10 min
Resource-Free Scheduling §
Our Example Continued. . . Go Shopping Initial state ES=0 Make Cake Eat Cake Wait Goal Go Shopping Make Cake Action Consumes Uses Duration Go Shopping -1 Mix 1 Mike 20 min Wait - - 60 min Make Cake 1 Mix, -1 Cake 1 Oven 30 min Eat Cake 1 Mike 10 min
Our Example Continued. . . Go Shopping Initial state ES=0 Make Cake ES=0=0+0 Eat Cake Wait Goal Go Shopping Make Cake Action Consumes Uses Duration Go Shopping -1 Mix 1 Mike 20 min Wait - - 60 min Make Cake 1 Mix, -1 Cake 1 Oven 30 min Eat Cake 1 Mike 10 min
Our Example Continued. . . Go Shopping Initial state ES=0 Make Cake ES=0 Eat Cake Wait ES=0=0+0 Go Shopping Goal Make Cake ES=0=0+0 Action Consumes Uses Duration Go Shopping -1 Mix 1 Mike 20 min Wait - - 60 min Make Cake 1 Mix, -1 Cake 1 Oven 30 min Eat Cake 1 Mike 10 min
Our Example Continued. . . Go Shopping Initial state ES=0 Make Cake ES=20=0+20 Eat Cake Wait ES=0 Go Shopping Goal Make Cake ES=0 Action Consumes Uses Duration Go Shopping -1 Mix 1 Mike 20 min Wait - - 60 min Make Cake 1 Mix, -1 Cake 1 Oven 30 min Eat Cake 1 Mike 10 min
Our Example Continued. . . Go Shopping Initial state ES=0 Make Cake ES=20 Eat Cake Wait ES=60=0+60 ES=0 Go Shopping ES=0 Make Cake ES=20 Action Consumes Uses Duration Go Shopping -1 Mix 1 Mike 20 min Wait - - 60 min Make Cake 1 Mix, -1 Cake 1 Oven 30 min Eat Cake 1 Mike 10 min Goal
Our Example Continued. . . Go Shopping Initial state ES=0 Make Cake ES=20 Eat Cake Wait ES=60 ES=0 Go Shopping ES=0 Goal Make Cake ES=70=60+10 ES=20 Action Consumes Uses Duration Go Shopping -1 Mix 1 Mike 20 min Wait - - 60 min Make Cake 1 Mix, -1 Cake 1 Oven 30 min Eat Cake 1 Mike 10 min
Our Example Continued. . . Go Shopping Initial state ES=0 Make Cake ES=20 Eat Cake Wait ES=60 ES=0 Go Shopping ES=0 Goal Make Cake ES=70, LS=70 ES=20 Action Consumes Uses Duration Go Shopping -1 Mix 1 Mike 20 min Wait - - 60 min Make Cake 1 Mix, -1 Cake 1 Oven 30 min Eat Cake 1 Mike 10 min
Our Example Continued. . . Go Shopping Initial state ES=0 Make Cake ES=20 Eat Cake Wait ES=60, ES=0 Go Shopping ES=0 Make Cake Goal LS=60=70 -10 ES=20 Action Consumes Uses Duration Go Shopping -1 Mix 1 Mike 20 min Wait - - 60 min Make Cake 1 Mix, -1 Cake 1 Oven 30 min Eat Cake 1 Mike 10 min ES=70, LS=70
Our Example Continued. . . Go Shopping Initial state ES=0 Wait Make Cake ES=20, LS=30=60 -30 ES=60, LS=60 ES=0 Go Shopping ES=0 Eat Cake Make Cake Goal ES=70, LS=70 ES=20 Action Consumes Uses Duration Go Shopping -1 Mix 1 Mike 20 min Wait - - 60 min Make Cake 1 Mix, -1 Cake 1 Oven 30 min Eat Cake 1 Mike 10 min
Our Example Continued. . . Go Shopping Initial state ES=0 Make Cake ES=20, LS=30 Eat Cake Wait ES=60, LS=60 ES=0 Go Shopping ES=0 Make Cake Goal ES=70, LS=70 ES=20, LS=40=70 -30 Action Consumes Uses Duration Go Shopping -1 Mix 1 Mike 20 min Wait - - 60 min Make Cake 1 Mix, -1 Cake 1 Oven 30 min Eat Cake 1 Mike 10 min
Our Example Continued. . . Go Shopping Initial state ES=0 Make Cake ES=0, LS=10=30 -10 ES=20, LS=30 Eat Cake Wait ES=60, LS=60 ES=0 Go Shopping ES=0 Make Cake Goal ES=70, LS=70 ES=20, LS=40 Action Consumes Uses Duration Go Shopping -1 Mix 1 Mike 20 min Wait - - 60 min Make Cake 1 Mix, -1 Cake 1 Oven 30 min Eat Cake 1 Mike 10 min
Our Example Continued. . . Go Shopping Initial state ES=0, LS=10 Make Cake ES=20, LS=30 Eat Cake Wait ES=60, LS=60 ES=0, LS=0=60 -60 Go Shopping ES=0 Make Cake Goal ES=70, LS=70 ES=20, LS=40 Action Consumes Uses Duration Go Shopping -1 Mix 1 Mike 20 min Wait - - 60 min Make Cake 1 Mix, -1 Cake 1 Oven 30 min Eat Cake 1 Mike 10 min
Our Example Continued. . . Go Shopping Initial state ES=0, LS=10 Make Cake ES=20, LS=30 Eat Cake Wait ES=60, LS=60 ES=0, LS=0 Go Shopping Make Cake Goal ES=70, LS=70 ES=0, LS=20=40 -20 ES=20, LS=40 Action Consumes Uses Duration Go Shopping -1 Mix 1 Mike 20 min Wait - - 60 min Make Cake 1 Mix, -1 Cake 1 Oven 30 min Eat Cake 1 Mike 10 min
Our Example Continued. . . Go Shopping Initial state ES=0, LS=0 ES=0, LS=10 Make Cake ES=20, LS=30 Eat Cake Wait ES=60, LS=60 ES=0, LS=0 Go Shopping ES=0, LS=20 Make Cake Goal ES=70, LS=70 ES=20, LS=40 Action Consumes Uses Duration Go Shopping -1 Mix 1 Mike 20 min Wait - - 60 min Make Cake 1 Mix, -1 Cake 1 Oven 30 min Eat Cake 1 Mike 10 min
Our Example Continued. . . Go Shopping Initial state ES=0, LS=10 Make Cake ES=20, LS=30 ES=60, LS=60 ES=0, LS=20 The critical path is the path from origin to goal where all nodes have slack=0 Eat Cake Wait Go Shopping Slack= LS-ES Make Cake Goal ES=70, LS=70 ES=20, LS=40 Action Consumes Uses Duration Go Shopping -1 Mix 1 Mike 20 min Wait - - 60 min Make Cake 1 Mix, -1 Cake 1 Oven 30 min Eat Cake 1 Mike 10 min
Priority based scheduling with resource constraints 1. Set T (Start)=0. 2. Select highest priority action from those whose predecessors have had their T scheduled, set its T as early as possible given resource constraints. When doing so, record which resources used and effects on consumed resources. 3. Repeat step 2 until all actions T scheduled. What should our priority function be? One idea: Minimum slack § We prioritize actions based on their slack (LS-ES) in the resource free schedule. We can redo the resource free algorithm, given (resource constrained) scheduled actions at each iteration of this algorithm.
Initial state TIME: 0 Mike Oven Cakes 0 Mixes 0
Initial state TIME: 0 Mike Oven Cakes 0 Mixes 0
Initial state TIME: Wait 0 60 Cakes 0 0 Mixes 0 0 Mike Oven
Initial state Wait Shop TIME: 0 20 60 Cakes 0 0 0 Mixes 0 1 1 Mike Oven
Initial state Wait Make Shop TIME: 0 20 50 60 Cakes 0 0 1 1 Mixes 0 (1) 0 0 0 Mike Oven
Initial state Wait Make Shop TIME: Eat 0 20 50 60 70 Cakes 0 0 1 (1) 0 0 Mixes 0 (1) 0 0 0 Mike Oven 0
Initial state Wait Eat Make Shop TIME: 0 20 40 50 60 70 Cakes 0 0 0 1 (1) 0 0 Mixes 0 (1) 0 1 1 1 Mike Oven 1
Initial state Wait Eat Make Shop TIME: 0 20 40 50 60 70 80 Cakes 0 0 0 1 (1) 0 0 1 Mixes 0 (1) 0 1 0 0 0 Mike Oven 0
Scheduling with Resources § Resource Free times are lowest bounds only. § Minimum slack algorithm is not always optimal. § No scalable optimal algorithm exists. (As far as I know. )
- 01:640:244 lecture notes - lecture 15: plat, idah, farad
- Land use planning '' lecture notes
- Land use planning lecture notes
- Contemporary management ppt
- Land use planning lecture notes
- Project planning and management lecture notes ppt
- Sjn scheduling
- Carlsberg supply chain
- Inventory management and production planning and scheduling
- Pulsing scheduling examples
- Factors affecting media planning
- Aggregate planning and master scheduling
- Detailed scheduling
- Examples of aggregate planning
- Strategic planning vs tactical planning
- Long medium and short term planning in primary schools
- Role segmentation workforce planning
- Planning balance sheet in urban planning
- Figurative language slideshare
- Proactive planning and reactive planning
- Aggregate planning is capacity planning for
- Perencanaan kapasitas dan agregat
- Chest oblique view
- Microprocessus en lecture
- Introduction to ofdm
- Lecture sound systems
- C data types with examples
- Lecture 4
- Fundamental deviation table
- End of lecture
- Lecture 14