LEAFY VEGETABLES WP 5 Coordination Chris Kik CGN
LEAFY VEGETABLES WP 5 Coordination Chris Kik, CGN, Wageningen, the Netherlands Centre for Genetic Resources, the Netherlands
Outline n n WP 5 milestones & deliverables: year 1, 2 & 3 Second annual technical and financial report Dissemination General conclusion Centre for Genetic Resources, the Netherlands
Deliverables Deliverable date Deliverable description D 27, month 01 ✔ Start-up project meeting D 28, month 03 ✔ Leafy Veg website is launched on internet and active. D 29, month 06 ✔ First WP coordinators meeting D 30, month 11 ✔ First annual project meeting D 31, month 14 ✔ First annual progress report D 32, month 18 ✔ Second WP coordinators meeting D 33, month 23 ✔ Second annual project meeting D 34, month 26 ✔ Second annual progress report D 35, month 30 Third WP coordinators meeting Centre for Genetic Resources, the Netherlands
Deliverables Deliverable date Deliverable description D 36, month 35 Third annual project meeting D 37, month 38 Third annual progress report D 38, month 42 Fourth WP coordinators meeting D 39, month 46 Final annual project meeting D 40, month 48 Final annual progress report and workshop Centre for Genetic Resources, the Netherlands
Milestones Milestone date Milestone description Year 1 month 01 month 5 month 10 ✔ ✔ Detailed workplan of the project defined at the start up meeting of the project (time schedules for regeneration, characterisation and evaluation will be established) The project website will be developed First WP coordinators meeting organised The second project meeting (first annual project meeting) will be organised to discuss the progress and discuss the first annual progress report Centre for Genetic Resources, the Netherlands
Milestones Milestone date Milestone description Year 2 month 13 month 17 month 22 ✔ ✔ ✔ First annual progress report will be finalised and submitted to the European Commission Second WP coordinators meeting organised Third project meeting (second annual project meeting) will be organised to discuss the progress and discuss the second annual progress report Centre for Genetic Resources, the Netherlands
Milestones Milestone date Milestone description Year 3 month 25 month 29 month 34 ✔ ✔ Second annual progress report will be submitted to the European Commission Third WP coordinators meeting organised Fourth project meeting (third annual project meeting) will be organised to discuss the progress; this meeting will also review the overall progress of the project (mid-term review) in order to assess whether the following set of milestones have been fulfilled by the project Centre for Genetic Resources, the Netherlands
Milestones Milestone date Milestone description Year 4 month 37 Third annual progress report including a mid-term review of the coordinator will be submitted to the European Commission month 41 Fourth WP coordinators meeting organised month 45 Final project meeting to discuss the progress report of the fourth year and the final overall project report of the project organised. A workshop presenting the results of the project will be connected to this meeting to disseminate information of the project to interesting stake holders. month 48 Fourth annual progress report and the final overall report will be submitted to the European Centre for Genetic Resources, the Netherlands Commission
M&D conclusion n Milestones and deliverables of WP 5 are all met until present. Centre for Genetic Resources, the Netherlands
First annual Leafy Veg progress report n Tech. & Fin. report submitted by April 2 to EU l n Reviewing technical report l l l n May 8: few comments received from EU May 26: reply to EU June 2: accepted by EU Reviewing financial report l n technical reporting was relatively easy; financial reporting took considerable time from the partners’ administrations. June 8: a number of comments received from the EU Expected reimbursement: September Centre for Genetic Resources, the Netherlands
First annual LV progress report conclusions n The technical reporting was OK: relatively easy l n reviewing process did not give much problems, in contrast to last year…. The financial reporting was for most (all) of us a time consuming business. I expected that ‘things’ would run more smoothly, given our first year exercise, but alas… (hopefully next year ‘things’ will be better). l reviewing in progress Centre for Genetic Resources, the Netherlands
New LV contract needed - (already for a year) n Reasons: l l l NGB changed its juridical name into Nord. Gen USOFA (Mihaela Cerne) stopped and their work will be carried out by KIS (Vladimir Meglic), both organizations are established in Ljubjana (Slovenia). 10% budget ceiling is not met for ‘other costs’ item: 55% change, this is due to the fact that a lot of partners decreased this budget item and transferred the budget to personnel costs. Centre for Genetic Resources, the Netherlands
Leafy Veg dissemination n We need to do something about this l Leafy Veg homepage ( summary of annual results + lisst of publications) l Writing papers, giving presentations, etc Centre for Genetic Resources, the Netherlands
General conclusion coordination n project is well on track Centre for Genetic Resources, the Netherlands