LCLS Commissioning Results Plans P Emma for the

  • Slides: 35
Download presentation
LCLS Commissioning: Results & Plans P. Emma, for the LCLS Commissioning Team LCLS FAC

LCLS Commissioning: Results & Plans P. Emma, for the LCLS Commissioning Team LCLS FAC Meeting June 16, 2008 LCLS Phys. Rev. publication: http: //prst-ab. aps. org/pdf/PRSTAB/v 11/i 3/e 030703 May 13, 2008 LCLS FAC 1 Paul Emma, et al. Emma@SLAC. Stanford. edu

LCLS Accelerator Layout 6 Me. V z 0. 83 mm 0. 05 % 4.

LCLS Accelerator Layout 6 Me. V z 0. 83 mm 0. 05 % 4. 30 Ge. V z 0. 022 mm 0. 71 % 21 -1 b, c, d DL 1 L 12 m R 56 0 Linac-2 L 330 m rf -41° X BC 1 L 6 m R 56 -39 mm Injector Commissioned (‘ 07) 21 -3 b 24 -6 d BC 2 L 22 m R 56 -25 mm 25 -1 a 30 -8 c undulator L =130 m DL 2 L =275 m Commissioned in Jan. 2008 R 56 0 SLAC linac tunnel LCLS FAC Linac-3 L 550 m rf 0° beam parked here , b -a L 0 Linac-1 L 9 m rf -25° . . . existing linac May 13, 2008 13. 6 Ge. V z 0. 022 mm 0. 01 % Linac-X L =0. 6 m rf= -160 Linac-0 L =6 m rf gun 250 Me. V z 0. 19 mm 1. 6 % 135 Me. V z 0. 83 mm 0. 10 % 2 research yard Paul Emma, et al. Emma@SLAC. Stanford. edu

LCLS Injector Layout 6 Me. V in ‘ 0 7 OTR screens (7) YAG

LCLS Injector Layout 6 Me. V in ‘ 0 7 OTR screens (7) YAG screens (7) Wire scanners (7) Dipole magnets (8) Beam stoppers (2) S-band RF acc. sections (5) C om m is si on ed RF Gun Solenoid L 0 a Gun Spectrometer L 0 b Emittance Screens/Wires Emittance Screen/Wires RF Deflector L 1 S 2 -km point in 3 -km SLAC linac X-band RF acc. section 135 -Me. V Spectrometer 135 Me. V May 13, 2008 LCLS FAC BC 1 TD 11 stopper 250 Me. V 3 Paul Emma, et al. Emma@SLAC. Stanford. edu

LCLS BC 2 Area Layout (sector 24/25) OTR screens (3) Collimator jaws (2 Phase

LCLS BC 2 Area Layout (sector 24/25) OTR screens (3) Collimator jaws (2 Phase monitor cavity (1) Dipole magnets (4) Kicker magnet (1) Transverse RF deflector (1) S-band RF acc. sections New installation in fall ‘ 07 4 wire-scanners “de-scoped” 4 wire-scanners in sec-28 (300 m downstream) CE 21 BPMS 21 OTR 21 BC 2 (not to scale) May 13, 2008 LCLS FAC PH 03 BXKIK TCAV 3 (25 -2 d) OTR 22 (25 -3 d) OTR_TCAV (25 -9) 4. 3 Ge. V 4 Paul Emma, et al. Emma@SLAC. Stanford. edu

Commissioning Highlights Injector commissioning: April through August, 2007 (DONE) Phase-II commissioning: Dec. Complete 3/31/08

Commissioning Highlights Injector commissioning: April through August, 2007 (DONE) Phase-II commissioning: Dec. Complete 3/31/08 (BC 2 + Linac) Up to 1 n. C of bunch charge available (mostly 0. 25 & 0. 5 n. C used) Great laser uptime (99%) and good performance (again) Emittances 1 mm after BC 1 at 1 n. C, 250 Me. V (fairly routine) Routine e- to 14 Ge. V (24/7 except Wed. - ~90% up-time) BC 1 dipoles & chicane motion fixed! No emittance growth in X-band RF cavity when best steered BC 2 compression demonstrated (no dipole field quality issues) CSR effects measured in BC 1 & BC 2 – agree with codes so far Many beam (8) & RF (8) feedback systems running well Tested energy switching: 14, 10, 7. 0, 4. 3 Ge. V (<5 min. switch) Coherent OTR observed – compromises nearly all screens Gun RF probes changed in April ’ 08 (allows 120 -Hz) May 13, 2008 LCLS FAC 5 Paul Emma, et al. Emma@SLAC. Stanford. edu

Design and Typical Measured Parameters May 13, 2008 LCLS FAC 6 Paul Emma, et

Design and Typical Measured Parameters May 13, 2008 LCLS FAC 6 Paul Emma, et al. Emma@SLAC. Stanford. edu

“Problems/Issues” from July ‘ 07 DOE Review AL L FI XE D Gun Faraday

“Problems/Issues” from July ‘ 07 DOE Review AL L FI XE D Gun Faraday cup broken Gun toroid shorted during installation Some YAG screens not installed properly BC 1 motion control limited (300 mm 260 mm) Cathode QE about 5 -times lower than design Some controls tools late (orbit displays, fitting, magnet control & alarms) MCOR power supply ADC readback noise (fixed) Laser phase drift and lock trouble until mid-June May 13, 2008 LCLS FAC 7 Paul Emma, et al. Emma@SLAC. Stanford. edu

Laser Spatial and Temporal Shaping 2007 2008 2007 2 R = 1. 4 mm

Laser Spatial and Temporal Shaping 2007 2008 2007 2 R = 1. 4 mm 6. 6 ps 7. 2 ps Temporal shape (6. 6 ps FWHM) Spatial shape on cathode using iris 99% Drive Laser up time! S. Gilevich, G. Hays, P. Hering, A. Miahnahri, W. White May 13, 2008 LCLS FAC 8 Paul Emma, et al. Emma@SLAC. Stanford. edu

Powerful Scanning/Correlation Application Watch profiles as scan proceeds H. Loos Quickly minimize emittance by

Powerful Scanning/Correlation Application Watch profiles as scan proceeds H. Loos Quickly minimize emittance by scanning any parameter May 13, 2008 LCLS FAC 9 Paul Emma, et al. Emma@SLAC. Stanford. edu

Projected Emittance <1. 2 μm at 1 n. C (135 Me. V) s =

Projected Emittance <1. 2 μm at 1 n. C (135 Me. V) s = 60 μm m in ee j go ect ts al or s gex = 1. 07 μm gey = 1. 11 μm May 13, 2008 LCLS FAC 10 Paul Emma, et al. Emma@SLAC. Stanford. edu

inj ec to ri s OTR screen at 135 Me. V st ab le

inj ec to ri s OTR screen at 135 Me. V st ab le Injector Emittance Measured Over 3 Days (0. 25 n. C) wire-scanner at 250 Me. V after BC 1 gex = 0. 91, gey = 1. 01 gex gey gex = 0. 83, gey = 0. 83 J. Welch May 13, 2008 LCLS FAC 11 Paul Emma, et al. Emma@SLAC. Stanford. edu

Laser & Electron-Based Feedback Systems ru no nn w in g Transverse Loops: Laser

Laser & Electron-Based Feedback Systems ru no nn w in g Transverse Loops: Laser spot on cathode (2) Gun launch angle Injector trajectory X-band cavity position Linac trajectory (2 old) Undulator traj. (future) Laser gun (bunch length feedback still needs work) V 0 L 0 D. Fairley J. Wu J. Frisch May 13, 2008 LCLS FAC Longitudinal Loops: DL 1 energy BC 1 bunch length BC 2 energy BC 2 bunch length Final energy (old loop) 0 1 z 2 1 2 V 1 L 1 DL 1 z 1 X 2 V 2 L 2 BC 1 3 V 3 L 3 BC 2 12 BPMs CSR detectors Steering Loop DL 2 Paul Emma, et al. Emma@SLAC. Stanford. edu

Bunch Length & Energy Feedback Systems DL 1 energy BC 1 energy 0. 03%

Bunch Length & Energy Feedback Systems DL 1 energy BC 1 energy 0. 03% rms 0. 05% rms BC 2 energy DL 2 energy 0. 09% rms 0. 03% rms 216 ± 12 A BC 1 peak current 2170 ± 217 A BC 2 peak current Charge feedback: Q = 0. 25 n. C bunch DQ 2 1/2/Q = 1. 5% charge May 13, 2008 LCLS FAC 13 Paul Emma, et al. Emma@SLAC. Stanford. edu

BC 1 Dipole Field Quality Fixed Poles were milled off and wider poles were

BC 1 Dipole Field Quality Fixed Poles were milled off and wider poles were bolted on and then the fields were shimmed. fix ed Nov. ‘ 07 Sext. tolerance Aug. ‘ 07 ± 3 beam J. Welch, S. De. Barger, N. Li, et al. May 13, 2008 LCLS FAC 14 Paul Emma, et al. Emma@SLAC. Stanford. edu

BC 2 Dipole Field Quality OK Beam energy scans confirm BC 2 dipole field

BC 2 Dipole Field Quality OK Beam energy scans confirm BC 2 dipole field quality meets requirements ± 3 beam OK No measurable quad field and sextupole is just at tolerance May 13, 2008 LCLS FAC 15 Paul Emma, et al. Emma@SLAC. Stanford. edu

Operating Point Summary Display Shows operators the main machine parameter targets and their present

Operating Point Summary Display Shows operators the main machine parameter targets and their present settings & includes save/restore files H. -D. Nuhn May 13, 2008 LCLS FAC 16 Paul Emma, et al. Emma@SLAC. Stanford. edu

BPM-Measured CSR Energy Loss in BC 1 at 0. 25 n. C (compares well

BPM-Measured CSR Energy Loss in BC 1 at 0. 25 n. C (compares well with tracking) BPM Bunch length after BC 1 measured with transverse RF L 1 S BC 1 (250 Me. V) BC 2 OFF BSY (14 Ge. V) TCAV (5. 0 Ge. V) A Phase shift of -0. 4 deg is added to the Elegant curves Y. Ding, Z. Huang Elegant CSR energy loss after BC 1 measured with BPM e- operating point g Chicane Bend May 13, 2008 LCLS FAC 17 BPM Paul Emma, et al. Emma@SLAC. Stanford. edu

Hor. CSR Emittance Growth after BC 1 (250 Me. V, 0. 25 n. C)

Hor. CSR Emittance Growth after BC 1 (250 Me. V, 0. 25 n. C) x = 38 mm = -22º x = 55 mm = -26º x = 246 mm = -27º Now plot horizontal emittance after BC 1 Horizontal emittance after BC 1 vs. RF phase Elegant May 13, 2008 LCLS FAC Elegant Meas-1 Meas-2 operating point Data also exists at 1 n. C and BC 2 data (0. 25 n. C) also shows decent results 18 Vertical emittance after BC 1 is almost unaffected Y. Ding, Z. Huang Elegant Paul Emma, et al. Emma@SLAC. Stanford. edu

RF Phase and Amplitude Stability (e. g. , L 0 a) 0. 05% rms

RF Phase and Amplitude Stability (e. g. , L 0 a) 0. 05% rms (<0. 07%) New inj. RF systems meet jitter tolerances RF Feedback Running 20 -second sample at 10 Hz 0. 05º rms (<0. 07º) R. Akre, D. Kotturi, J. Craft, V. Pacak, et al. May 13, 2008 LCLS FAC 19 Paul Emma, et al. Emma@SLAC. Stanford. edu

Normalized phase space centroid jitter after BC 1 (~4% of rms beam size) RMS

Normalized phase space centroid jitter after BC 1 (~4% of rms beam size) RMS Ay. N = 3. 4% RMS Ax. N = 3. 9% Stability is not so far off of our goals (~10%) 1 -s beam size D. Ratner … near end of linac (~12% of rms beam size, but sometimes larger) RMS Ay. N = 9% RMS Ax. N = 14% DE/E jitter 0. 03% DQ/Q jitter 1. 5% Q = 0. 25 n. C May 13, 2008 LCLS FAC Thanks to Controls group for new BPM electronics! 20 Paul Emma, et al. Emma@SLAC. Stanford. edu

BC 2 Chicane in the Linac at 4. 3 Ge. V Bob Fuller Chicane

BC 2 Chicane in the Linac at 4. 3 Ge. V Bob Fuller Chicane length 24 m, 4. 3 Ge. V, 2º bends May 13, 2008 LCLS FAC 21 Paul Emma, et al. Emma@SLAC. Stanford. edu

Bunch Compression Measured after BC 2 (0. 25 n. C) z < 10 mm

Bunch Compression Measured after BC 2 (0. 25 n. C) z < 10 mm Bunch length after BC 2 measured with transverse RF old screen used – poor resolution limit z > 25 mm sz 10 mm -2º shift applied to simulation L 2 May 13, 2008 LCLS FAC BC 2 (4. 3 Ge. V) TCAV (5. 0 Ge. V) 22 550 m BSY (14 Ge. V) Paul Emma, et al. Emma@SLAC. Stanford. edu

Longitudinal Phase Space at 14 Ge. V PR 55 Li. Track simulation Bunch is

Longitudinal Phase Space at 14 Ge. V PR 55 Li. Track simulation Bunch is Over-Compressed L 2 phase = -41 deg Chirp knob = -450 Me. V measurement Vertical scale only approx. Transverse RF is ON PR 55 Bunch is Under-Compressed L 2 phase = -41 deg Chirp knob = +450 Me. V older screen has poor resolution Q = 1 n. C May 13, 2008 LCLS FAC Li. Track simulation measurement 23 Vertical scale only approx. Paul Emma, et al. Emma@SLAC. Stanford. edu

Emittance Measurements at End of Linac Using Wire Scanners x = 76 mm x

Emittance Measurements at End of Linac Using Wire Scanners x = 76 mm x = 38 mm x = 49 mm x = 47 mm wire scans F. -J. Decker R. Iverson Emittance measured 300 m after BC 2 at 10 Ge. V with 10 mm bunch length gey = 0. 9 mm May 13, 2008 LCLS FAC Q = 0. 25 n. C Results still variable – requires careful work 24 Paul Emma, et al. Emma@SLAC. Stanford. edu

Emittance Near End of Linac Over Long Weekend weekend run at 0. 25 n.

Emittance Near End of Linac Over Long Weekend weekend run at 0. 25 n. C, with no tuning g(exey)1/2 = 1. 04 mm Saturates at 1. 5 Å in 100 m (assuming BBA, etc) (3. 3 days) May 24, 2008 00: 01 to May 27 09: 00 May 13, 2008 LCLS FAC 25 Paul Emma, et al. Emma@SLAC. Stanford. edu

Measuring Bunch Arrival Time Jitter Q = 0. 25 n. C S-band (2856 MHz)

Measuring Bunch Arrival Time Jitter Q = 0. 25 n. C S-band (2856 MHz) BPM V (t ) slope = -2. 34 mm/deg BPM Y Position (mm) e- Now measure BPM jitter both with transverse RF OFF, and then ON (at constant phase) TCAV OFF TCAV ON 9 mm rms 110 mm rms Dt ± 0. 6 ps Timing Jitter (w. r. t. RF) = (110 mm)/(2. 34 mm/deg) = 0. 047 deg 46 fsec rms May 13, 2008 LCLS FAC 26 Paul Emma, et al. Emma@SLAC. Stanford. edu

First Light in FEH CD-4 (7/31/2010) X-Rays in NEH FEH Hutch BO FEH Install

First Light in FEH CD-4 (7/31/2010) X-Rays in NEH FEH Hutch BO FEH Install First Light in FEE Und. Seg. Install PPS Cert. LTU/Dump FEE/NEH Install LTU/Und/Dump Install now PEP-II run ends LCLS Installation and Commissioning Time-Line PPS J F M A M J J A S ON D J F M A AM M J J A S ON D J F MAM J J Down 2008 2009 2010 Linac/BC 2 Commissioning May 13, 2008 LCLS FAC Re-commission LTU/Und NEH Operations/ Inj/BC 2 to SL 2 Comm. FEE Commissioning Comm. 27 May 2, 2008 Paul Emma, et al. Emma@SLAC. Stanford. edu

LTU/Undulator/FEE/FEL Commissioning H. Tompkins See break-out presentations: LTU & Undulator Commissioning Plans (H. -D.

LTU/Undulator/FEE/FEL Commissioning H. Tompkins See break-out presentations: LTU & Undulator Commissioning Plans (H. -D. Nuhn) FEL/FEE Overview Commissioning Plans (H. Tompkins) FEE Diagnostics & Commissioning (R. Bionta) May 13, 2008 LCLS FAC 28 Paul Emma, et al. Emma@SLAC. Stanford. edu

Problems/Issues End-of-linac x-emittance difficult to minimize and maintain, especially at 1 n. C (CSR

Problems/Issues End-of-linac x-emittance difficult to minimize and maintain, especially at 1 n. C (CSR + micro-bunching? ) Some wire-scanner vibration issues (~fixed in April ‘ 08) Most OTR screens are unusable due to COTR (laser heater should solve this in FY 2009) Most linac BPMs need upgrade – 22 of 83 done with great resolution improvement (50 5 mm - more on AIP List) BC 2 bunch length monitor noisy or real jitter – (need beam synchronous acquisition for RF & BPMs or m-bunching? ) RF phase jumps/drifts not uncommon – sometimes beyond feedback control range May 13, 2008 LCLS FAC 29 Paul Emma, et al. Emma@SLAC. Stanford. edu

Summary Drive laser very reliable – performs well (great team) Injector in very good

Summary Drive laser very reliable – performs well (great team) Injector in very good shape – runs well after setup Many measurements made – getting to know machine Emittances at end of linac difficult to tune, but nice results are possible with effort (gey is done!) Very encouraging results: e- beam supports 1. 5 -Å SASE We look forward to next phase (LTU, undulator, FEL, …) – preparations have begun (plans, software, checkout, …) Thanks to dedicated Commissioning Team + Controls, RF, Engineering, Operations, ASD, Maintenance, etc May 13, 2008 LCLS FAC 30 Paul Emma, et al. Emma@SLAC. Stanford. edu

DONE May 13, 2008 LCLS FAC 31 Paul Emma, et al. Emma@SLAC. Stanford. edu

DONE May 13, 2008 LCLS FAC 31 Paul Emma, et al. Emma@SLAC. Stanford. edu

gex near end of linac (µm) BC 2 Emittance Growth vs. Peak Current Q

gex near end of linac (µm) BC 2 Emittance Growth vs. Peak Current Q = 0. 5 n. C May 13, 2008 LCLS FAC BC 2 Peak Current Feedback Set-Point (A) 32 Paul Emma, et al. Emma@SLAC. Stanford. edu

COTR After BC 2 OTR screen just after BC 2 OTR 22 with BC

COTR After BC 2 OTR screen just after BC 2 OTR 22 with BC 2 screen OUT (m-bunching present – COTR!) with BC 2 screen inserted (smoothes m-bunching) May 13, 2008 LCLS FAC 33 Paul Emma, et al. Emma@SLAC. Stanford. edu

m-Bunching in BC 2 May Blow up X-Emittance OTR screen in BC 2 OTR

m-Bunching in BC 2 May Blow up X-Emittance OTR screen in BC 2 OTR 21 gex, y measured with gex wire-scanners 320 -m downbeam of BC 2 gey May 13, 2008 LCLS FAC 34 Paul Emma, et al. Emma@SLAC. Stanford. edu

FY 2009 Commissioning Activities Pre-Beam Checkout (Nov-Dec ‘ 08) – check-list in prep. Re-establish

FY 2009 Commissioning Activities Pre-Beam Checkout (Nov-Dec ‘ 08) – check-list in prep. Re-establish injector & linac beam quality (Nov-Dec ‘ 08) – have experience First LTU Commissioning with beam (Jan-Mar ‘ 09) – lots of time ‘Undulator’/Dump Comm. without undulators (Jan-Mar ‘ 09) Calibrate & commission: RF BPMs, Loss Monitors, BFWs, ADS BBA algorithm testing (without segments) Install undulator segments (Mar ’ 09, two wks) – optimize linac again First Undulator Segments Commissioning (Mar-Apr ‘ 09) Care with first transport to minimize radiation on segments Full alignment process (BBA, BFW’s) Commission FEE Diagnostics (Apr-Jun ‘ 09) Direct Imager, Calorimeter, Slit, Solid Attenuator, Gas Detector Beam-Based K Measurement Components Optimization & characterization of SASE (Jun-Jul ‘ 09) Optimize linac beam quality (adjust compression, emittance tuning, BBA) Measure gain length May 13, 2008 LCLS FAC 35 Paul Emma, et al. Emma@SLAC. Stanford. edu