LCLS Commissioning P Emma et al LCLS Operations

  • Slides: 29
Download presentation
LCLS Commissioning P. Emma, et al. LCLS Operations Lectures June 7, 2006 LCLS Commissioning

LCLS Commissioning P. Emma, et al. LCLS Operations Lectures June 7, 2006 LCLS Commissioning 1 Paul Emma@SLAC. Stanford. edu

LCLS Accelerator Schematic 6 Me. V z 0. 83 mm 0. 05 % 4.

LCLS Accelerator Schematic 6 Me. V z 0. 83 mm 0. 05 % 4. 30 Ge. V z 0. 022 mm 0. 71 % , b -a L 0 Linac-1 L 9 m rf -25° . . . existing linac 21 -1 b, c, d DL 1 L 12 m R 56 0 X BC 1 L 6 m R 56 -39 mm 21 -3 b 24 -6 d BC 2 L 22 m R 56 -25 mm 2 undulator L =130 m 25 -1 a 30 -8 c Commission in Jan. 2008 SLAC linac tunnel LCLS Commissioning Linac-3 L 550 m rf 0° Linac-2 L 330 m rf -41° Commission in Jan. 2007 June 7, 2006 13. 6 Ge. V z 0. 022 mm 0. 01 % Linac-X L =0. 6 m rf= -160 Linac-0 L =6 m rf gun 250 Me. V z 0. 19 mm 1. 6 % 135 Me. V z 0. 83 mm 0. 10 % DL 2 L =275 m R 56 0 research yard Paul Emma@SLAC. Stanford. edu

Complete & Detailed Optics (cathode to dump) dump cathode L 2 BC 2 L

Complete & Detailed Optics (cathode to dump) dump cathode L 2 BC 2 L 3 LTU sec-30 muon plug wall sec-21 undulator Full MAD files at: http: //www-ssrl. slac. stanford. edu/lcls/linac/optics/ June 7, 2006 LCLS Commissioning 3 Paul Emma@SLAC. Stanford. edu

LCLS Installation and Commissioning Time-Line Drive-Laser Commissioning undulator hall ready Drive-Laser Install LTU/und. Install

LCLS Installation and Commissioning Time-Line Drive-Laser Commissioning undulator hall ready Drive-Laser Install LTU/und. Install linac/BC 2 Install First FEL Light First Spont. Light M J J A SOND J FMAM J J 2006 2007 2008 June 2006 Gun/Inj. /BC 1 Install Commissioning (8/21 – 1/5) June 7, 2006 LCLS Commissioning 4 linac/BC 2 FEL Commissioning LTU/undulator Commissioning Paul Emma@SLAC. Stanford. edu

RF Gun 6 Me. V L 0 a RF section 62 Me. V gun

RF Gun 6 Me. V L 0 a RF section 62 Me. V gun spectrometer Injector Layout L 0 b RF section 135 Me. V Transverse RF deflector L 1 RF section (21 -1 b) main SLAC Linac injector spectrometer sector 20 June 7, 2006 LCLS Commissioning 5 sector 21 Paul Emma@SLAC. Stanford. edu

LCLS Injector Commissioning Dates (’ 06 - ’ 07) July 24: Sector-20 ready for

LCLS Injector Commissioning Dates (’ 06 - ’ 07) July 24: Sector-20 ready for laser installation Aug. 29: Laser installation complete Dec. 18: Virtual cathode fully characterized (ready to install gun) Dec. 19: RF gun installation starts (10 days) + pre-beam checkout Dec. 20 -Jan. 1: Holidays Jan. 2: VVS’s switched on (RF power available) Jan. 12: First laser UV-light on cathode! Jan. 12 -Feb. 4: Electrons in GTL and gun-spect. (RF processing L 0 a, b, L 1, LX) Feb. 5: Beam into L 0 a, L 0 b and down to 135 -Me. V spect. Feb. 20: Beam into main linac (to TD 11 dump) ~June: Take beam down full linac (to BSY SL 2 stopper) June 7, 2006 LCLS Commissioning 6 Paul Emma@SLAC. Stanford. edu

OUT OF DATE Microsoft Project Commissioning Schedule LCLS Commissioning 7 2007 DO W N

OUT OF DATE Microsoft Project Commissioning Schedule LCLS Commissioning 7 2007 DO W N 2006 DO W N June 7, 2006 Paul Emma@SLAC. Stanford. edu

pass-1 OUT OF DATE pass-2 pass-3 LCLS Commissioning 8 pass-2. . . Paul Emma@SLAC.

pass-1 OUT OF DATE pass-2 pass-3 LCLS Commissioning 8 pass-2. . . Paul Emma@SLAC. Stanford. edu 2007 DO W N 2006 DO W N June 7, 2006 pass-1

LCLS Commissioning 9 OUT OF DATE Paul Emma@SLAC. Stanford. edu 2007 DO W N

LCLS Commissioning 9 OUT OF DATE Paul Emma@SLAC. Stanford. edu 2007 DO W N 2006 DO W N June 7, 2006 pass-2. . . pass-3 pass-1

Commissioning Definition and Strategy All components have been installed, aligned, connected, and initially verified

Commissioning Definition and Strategy All components have been installed, aligned, connected, and initially verified by the system engineer, then commissioning starts. Commissioning Sequence (1 -4) 1. Pre-Beam Checkout (tunnel and MCC) Controls/software testing, check cameras, ‘snail’ hunt, etc Magnet polarities, cable connections, verify motion-control, etc 2. Beam-based Hardware and Software Checkout Establish beam transport, RF setup, MPS/BCS tests, etc Checkout of all wires, screens, BPMs, toroids, magnets, etc 3. First-Order Optics: Measurement and Correction Steering, transmission, oscillation data, feedback setup, etc Beta and dispersion matching, beam-base align key quads, etc 4. Full Beam Characterization: Measurement and Correction Measure emittance, energy spread, distributions - correct Measure beam sensitivities, optimize tuning, beam experiments No (serious) emittance measurements until all hardware/software checked out! June 7, 2006 LCLS Commissioning 10 Paul Emma@SLAC. Stanford. edu

Electron Commissioning Organization Project Director J. Galayda Commissioning Don P. Emma Alternating Weekly Run

Electron Commissioning Organization Project Director J. Galayda Commissioning Don P. Emma Alternating Weekly Run Coordinator One Lead Physicist per shift Shift Physicists June 7, 2006 LCLS Commissioning Controls & System Engineers 11 MCC & Laser Operators Paul Emma@SLAC. Stanford. edu

LCLS Injector Commissioning Day 24 -Hour Cycle (7 days/week, 1/2/07 to 9/1/07, 32 total

LCLS Injector Commissioning Day 24 -Hour Cycle (7 days/week, 1/2/07 to 9/1/07, 32 total weeks) DAY SHIFT (8: 00 -16: 00) 1 lead physicist, 1 controls eng. , 1 sys. engineer, 1 LCLS operator, 1 laser operator SWING SHIFT (16: 00 -24: 00) 1 lead physicist, 1 LCLS operator, 1 laser operator OWL SHIFT (0: 00 -8: 00) 1 LCLS operator, 1 laser operator ? June 7, 2006 LCLS Commissioning 12 Paul Emma@SLAC. Stanford. edu

LCLS Commissioning Parameters Parameter Value Comments RF rate 30 Hz in linac (possible short-term

LCLS Commissioning Parameters Parameter Value Comments RF rate 30 Hz in linac (possible short-term 120 -Hz rate in L 0 BC 1 for feedback tests, etc) - 120 Hz in gun for short time to verify full rate Beam rate ≤ 30 Hz e- beam as baseline – possible short term 120 Hz tests in L 0 -BC 1 for feedback tests, etc Drive-laser rate 120 Hz 120 -Hz at all times – shutters provide e- rate as required above Bunch charge 200 -500 p. C depends on QE and diagnostics – some short spans at 10 p. C – later in ’ 07 we explore 1 -n. C Drive-laser pulse length 10 ps fwhm 10 -ps fwhm startup with possibility of 6 -ps at 0. 2 n. C later – early laser tests may provide path to more convenient pulse-length changes Gun gradient Set as goal, although 110 MV/m is adequate in ‘ 07 June 7, 2006 LCLS Commissioning 120 MV/m 13 Paul Emma@SLAC. Stanford. edu

Issues Controls will be mixed (SLC & epics) and capabilities may be limited initially

Issues Controls will be mixed (SLC & epics) and capabilities may be limited initially Most High-Level Applications (emittance, bunch length, feedback) must done through MATLAB as a temporary solution Most LCLS physicists not yet experienced in SLAC control room with SLC controls Help from operations group will be needed LCLS Lecture Series + Workshop in Oct. ? June 7, 2006 LCLS Commissioning 14 Paul Emma@SLAC. Stanford. edu

Q = 1 n. C RF f = 120 Hz G = 120 MV/m

Q = 1 n. C RF f = 120 Hz G = 120 MV/m gex, y = 1 mm Dt = 10 ps I = 100 A E = 6 Me. V Photo-Cathode Gun spec. dipole e- e- UV laser solenoid cathode YAG screens RF gun June 7, 2006 LCLS Commissioning 15 Paul Emma@SLAC. Stanford. edu

RF Gun YAG screen trajectory (BPMs) emittance (+ slice) energy spread (+ slice) bunch

RF Gun YAG screen trajectory (BPMs) emittance (+ slice) energy spread (+ slice) bunch length (+ dist. ) charge (+ dark current) YAG screen Transverse RF deflector OTR & wire gun spectrometer Injector Diagnostics OTR & wire main SLAC Linac injector spectrometer YAG & OTR June 7, 2006 LCLS Commissioning 16 Paul Emma@SLAC. Stanford. edu

Injector Through BC 1 Commissioning no laser-heater until ‘ 08 RF deflector June 7,

Injector Through BC 1 Commissioning no laser-heater until ‘ 08 RF deflector June 7, 2006 LCLS Commissioning gex, y and slice 17 E E Paul Emma@SLAC. Stanford. edu

Injector Through BC 1 Commissioning (2) relative bunch length monitors BC 1 E X-band

Injector Through BC 1 Commissioning (2) relative bunch length monitors BC 1 E X-band RF June 7, 2006 LCLS Commissioning E slice gey 18 gex, y stopper Paul Emma@SLAC. Stanford. edu

Setup of Linac-1, X-band RF Phases 20 -mm res. BC 1 BPM LX RF

Setup of Linac-1, X-band RF Phases 20 -mm res. BC 1 BPM LX RF phase L 1 RF phase Linac-1 RF phase scan (X-band off, BC 1 bends at 295 Me. V) Linac-X RF phase scan (BC 1 bends at 250 Me. V) set phase to -25˚ 0. 5˚ set phase to -160˚ 0. 5˚ rf gun w ne Linac-1 21 -1 b 21 -1 d June 7, 2006 LCLS Commissioning X Turn on BC 1 energy feedback Switch off BC 2 chicane Use sec-25 RF-deflector to meas. bunch length ( z 1) Adjust S-band RF phase ( 0. 5˚) to set z 1 195 10 mm 19 Paul Emma@SLAC. Stanford. edu

Setup of Linac-2 RF 40 -mm res. BC 2 BPM 5 -mm res. LTU

Setup of Linac-2 RF 40 -mm res. BC 2 BPM 5 -mm res. LTU BPM wake-loss scan L 2 RF phase L 2 phase Scan Linac-2 phase & use LTU BPM to find max. wake-induced energy loss across Linac-3 Linac-2 RF phase scan (BC 2 bends at 5. 9 Ge. V, or…) set phase to -41˚ 0. 5˚ L 2 June 7, 2006 LCLS Commissioning L 3 Turn on BC 2 energy feedback Use sec-25 RF-deflector to measure length ( z 2) Adjust L 2 RF phase ( 0. 5˚) to set z 2 20 2 mm Linac-3 phasing is trivial ( 5˚) 20 Paul Emma@SLAC. Stanford. edu

Longitudinal Beam-Based Feedback 0 V 0 gun z 1 z 2 1 2 L

Longitudinal Beam-Based Feedback 0 V 0 gun z 1 z 2 1 2 L 0 1 V 1 L 1 DL 1 June 7, 2006 LCLS Commissioning 2 V 2 L 2 X BC 1 L 3 BC 2 21 V 3 3 DL 2 Paul Emma@SLAC. Stanford. edu

Location of Main Linac Diagnostics 5+ energy spread meas. stations (optimized with small b)

Location of Main Linac Diagnostics 5+ energy spread meas. stations (optimized with small b) 5+ emittance meas. stations designed into optics (Dyx, y) BPMs at or near most quadrupoles and in each bend syst. RF deflectors for slice e and E measurements (L 0 & L 3) rf gun T-cav. L 0 gex, y L 1 . . . existing linac E E June 7, 2006 LCLS Commissioning gex, y T-cav. L 2 X E L 3 E E E 22 gex, y E E Paul Emma@SLAC. Stanford. edu E E

Slice-Emittance Measurement Simulation RF-deflector at 1 MV sy bunch length slice OTR 10 times

Slice-Emittance Measurement Simulation RF-deflector at 1 MV sy bunch length slice OTR 10 times 135 Me. V quad scanned June 7, 2006 LCLS Commissioning 23 Paul Emma@SLAC. Stanford. edu

Slice-Emittance Measurement Simulation Injector (135 Me. V) with S -band RF-deflector at 1 MV

Slice-Emittance Measurement Simulation Injector (135 Me. V) with S -band RF-deflector at 1 MV (same SLAC slice-e code used at BNL/SDL) (slice-y-emittance also simulated in BC 1 -center) = meas. sim. = calc. = y distribution = actual DL 1 slice-emit on WS 02 slice-5 June 7, 2006 LCLS Commissioning 24 Paul Emma@SLAC. Stanford. edu

y-slice-Emittance Measurement in BC 1 “Q 21201” scanned ± 20% June 7, 2006 LCLS

y-slice-Emittance Measurement in BC 1 “Q 21201” scanned ± 20% June 7, 2006 LCLS Commissioning 25 0. 1 mm 3. 9 mm Paul Emma@SLAC. Stanford. edu

Slice ey Measurements at BNL weak quad setting undulators linac (off) 75 Me. V

Slice ey Measurements at BNL weak quad setting undulators linac (off) 75 Me. V dump linac 75 Me. V dump medium quad setting strong quad setting 200 p. C, 100 A, 75 Me. V Data from DUVFEL at BNL: W. Graves, e June 7, 2006 LCLS Commissioning 26 Paul Emma@SLAC. Stanford. edu

Linac-To-Undulator (LTU) vertical bends energy centroid & spread meas. (OTR) (3 10 -5 &

Linac-To-Undulator (LTU) vertical bends energy centroid & spread meas. (OTR) (3 10 -5 & 10 -4) + collimation 4 e-wires, 6 collimators, 1 OTR · · · June 7, 2006 LCLS Commissioning 27 vertical bends horiz. jog 1. 25 m energy diagnostics emit. diagnostics collimators branch points for future undulators Paul Emma@SLAC. Stanford. edu

Slice Energy Spread Measurements in LTU s. E/E 10 -4 LTU at 14 Ge.

Slice Energy Spread Measurements in LTU s. E/E 10 -4 LTU at 14 Ge. V with S-band RF-deflector at 24 MV sx 12 mm FEL goal June 7, 2006 LCLS Commissioning 28 Paul Emma@SLAC. Stanford. edu

Summary Injector commissioning starts very soon (Laser: Aug. ‘ 06, Electrons: Jan. ‘ 07)

Summary Injector commissioning starts very soon (Laser: Aug. ‘ 06, Electrons: Jan. ‘ 07) Phase-II of commissioning comes in Jan. ‘ 08 LCLS group will need continual help from operations group LCLS is a 30 -year machine – this is just the start June 7, 2006 LCLS Commissioning 29 Paul Emma@SLAC. Stanford. edu