LARP Phase II Secondary Collimator RC 1 Collimator

  • Slides: 9
Download presentation
LARP Phase II Secondary Collimator RC 1 Collimator Test Program LARP LHC PHASE II

LARP Phase II Secondary Collimator RC 1 Collimator Test Program LARP LHC PHASE II COLL RC 1 TESTS - S. Lundgren 26 April 2006 No /9

LARP Phase II Secondary Collimator RC 1 Collimator Test Plan • Near term –

LARP Phase II Secondary Collimator RC 1 Collimator Test Plan • Near term – Jaw/Cooling Tube Joint Development – Single Jaw Thermal Tests • Later this year…… – Design and fab hardware for Mechanical Prototype Tests LARP LHC PHASE II COLL RC 1 TESTS - S. Lundgren 26 April 2006 No /9

Jaw/Cooling Tube Joint Development Purpose: determine appropriate joint configuration & fabrication methods In process.

Jaw/Cooling Tube Joint Development Purpose: determine appropriate joint configuration & fabrication methods In process. . target completion date May 9 th Cooling Tube • Square hollow magnet conductor first test ~ 9 mm x 9 mm Jaw Center Mandrel • Copper jaw and mandrel • Cu-Au braze • After first braze, machine coil o. d. for correct fit to jaw i. d. ~70 mm dia ~100 mm dia • After second braze, section assy to inspect coverage • Round tubing with grooved (? ) mandrel is next ~100 mm LARP LHC PHASE II COLL RC 1 TESTS - S. Lundgren 26 April 2006 No /9

Development/Test Lab LARP LHC PHASE II COLL RC 1 TESTS - S. Lundgren 26

Development/Test Lab LARP LHC PHASE II COLL RC 1 TESTS - S. Lundgren 26 April 2006 No /9 Item availability Chiller existing Vacuum equip’t SLAC misc? Heater controller select/buy Gantry select/buy Tools, table select/buy Instrumentation select/buy Power/water to be installed

Single Jaw Thermal Test Purpose: measure cooling effectiveness and thermal deformations Current focus: purchase

Single Jaw Thermal Test Purpose: measure cooling effectiveness and thermal deformations Current focus: purchase long lead items concurrently with FEA predictions and mechanical design of required test hardware. Next Milestones: Copper Jaw… target is mid June Experiment hardware & test set-up…target early is July • Internal helical cooling tube • Collimator midpoint stop and flexible end supports • Commercial electric resistance heaters, coupled with thermal grease – SS power ~10 k. W, evenly distributed – No transient testing – FE model test => validation of simulations • No Jaw rotation • Perform test under inert gas, insulated in air, or under vacuum…TBD LARP LHC PHASE II COLL RC 1 TESTS - S. Lundgren 26 April 2006 No /9

Single Jaw Thermal Test setup Thermocouples measure temperature distribution Reference bar, water cooled to

Single Jaw Thermal Test setup Thermocouples measure temperature distribution Reference bar, water cooled to maintain straightness (radiation shield ? ) Standoffs fix jaw distance to reference bar at center Capacitive proximity sensors at ends Flexible end mounts Orientation: may be rotated 90 o, or 180 o or on end Water cooling 2 x 5 k. W heaters, coupled with thermal grease LARP LHC PHASE II COLL RC 1 TESTS - S. Lundgren 26 April 2006 No /9

Single Jaw Test Thermocouple Locations 2 x 5 k. W Heaters • Thermocouples recessed

Single Jaw Test Thermocouple Locations 2 x 5 k. W Heaters • Thermocouples recessed into Jaw slightly below the surface • Spaced along Heater length and around Jaw circumference • Should yield the Jaw heating profile predicted by the FE analysis 12 x Thermocouples LARP LHC PHASE II COLL RC 1 TESTS - S. Lundgren 26 April 2006 No /9

RC 1 Mechanical Prototype Test Purpose: bench top testing of the jaw actuating mechanism

RC 1 Mechanical Prototype Test Purpose: bench top testing of the jaw actuating mechanism in CERN orientations Current Focus: Preliminary engineering definition, system analysis & sizing of components. Target completion …. . mid June Next Milestone: Engineering drawings/detailed design. Target. . Dec • CERN adjustment mechanism used • Add’l CERN Phase 1 components as appropriate • Vacuum tank with easy access • Realistic cooling water feed-throughs and flexible connections • Simplistic control system for jaw aperture and rotation • Minimal instrumentation connections for position, temperature, etc. • Probably no heat loading LARP LHC PHASE II COLL RC 1 TESTS - S. Lundgren 26 April 2006 No /9

RC 1 Mechanical Prototype FY 07 RC 1 consists of jaws, tank & actuators

RC 1 Mechanical Prototype FY 07 RC 1 consists of jaws, tank & actuators - evaluated for horizontal (shown), vertical (90 o) and skew (+/- 45 o) orientations. FY 08, RC 2 Variant: use CERN vac tank, dummy jaws of correct weight LARP LHC PHASE II COLL RC 1 TESTS - S. Lundgren 26 April 2006 No /9