Larger Project Implementation Issues and Integration of Storage

  • Slides: 5
Download presentation
Larger Project Implementation Issues and Integration of Storage into the SIR October 24, 2017

Larger Project Implementation Issues and Integration of Storage into the SIR October 24, 2017 IPWG Meeting 1

Larger Project Implementation Issues • Defining Project Requirements Necessary to Lock in Compensation –

Larger Project Implementation Issues • Defining Project Requirements Necessary to Lock in Compensation – Can Projects above 2 MW apply prior to Commission Rule Change and be Eligible for the Value Stack? – What are the Project Requirements to Lock in Compensation? • 25% Payment and Given Utility Approval to Being Interconnection Design • Demonstration that Project is Obtaining All Required Construction Approvals 2

Aggregation of Smaller Projects • Are Existing Projects, 2 MW and Under, Allowed to

Aggregation of Smaller Projects • Are Existing Projects, 2 MW and Under, Allowed to Aggregate into Larger Projects? – If Allowed, at What Point in the Interconnection Process could this occur? – What would be the Project Requirements? • Same PCC for all Projects • Sequential in the Utility SIR Interconnection Queue on both the Circuit and Substation Bus • No other projects from NYISO or Non-SIR Utility Queues between projects that what to aggregate • Pay for any Additional Study and Upgrade Costs 3

Aggregation of Smaller Projects • How is Compensation Determined for these Aggregated Projects? –

Aggregation of Smaller Projects • How is Compensation Determined for these Aggregated Projects? – Do they loose their Tranche Position? – What Happens if the Projects are in Different Tranches? • What is Deemed to be a Material Change of a Project? – Do Material Changes Require a Developer to submit a New Application? – What Happens if Project has already paid 25% and been put in Tranche? 4

Integration of Solar Into the SIR • Should there be a limit of the

Integration of Solar Into the SIR • Should there be a limit of the Storage Nameplate Rating relative to the size of the DG System? • What are the metering requirements for paired systems? – Do metering requirements change based on the use case? – Are separate meters required for paired systems to verify how storage system is being charged? 5