Large Transmission Pipeline Operations Optimization under Future Uncertainty

  • Slides: 53
Download presentation
Large Transmission Pipeline Operations: Optimization under Future Uncertainty Richard G. Carter and Henry H.

Large Transmission Pipeline Operations: Optimization under Future Uncertainty Richard G. Carter and Henry H. Rachford, Advantica Todd Dupont, U. Chicago

Oil and Gas Pipelines

Oil and Gas Pipelines

Taxonomies • Liquid Pipelines • Natural Gas Pipelines • Gathering systems • Cross-country Transmission

Taxonomies • Liquid Pipelines • Natural Gas Pipelines • Gathering systems • Cross-country Transmission systems • Distribution systems

General Themes for this Talk • Gas Transmission Pipeline • Transient vs steady state

General Themes for this Talk • Gas Transmission Pipeline • Transient vs steady state analysis • Optimal planning for operation under stressful conditions • Optimal Preparation under Uncertainty

Overview • Today’s Goal: Describe a class of problems that occur in our industry

Overview • Today’s Goal: Describe a class of problems that occur in our industry and some of the results that can be obtained. • We first present a Sample Pipeline, some of the physical aspects of the problem, and show optimal operation given 2 different scenarios • Robust solution that allows for either scenario. • What does uncertainty mean to us? Recourse? • Observations and Conclusions

What is a pipeline? Pipes Compressors Sources and deliveries

What is a pipeline? Pipes Compressors Sources and deliveries

Frictional Pressure Losses Compressor Pipe Frictional Pressure Drop – Function of Flow rate, diameter,

Frictional Pressure Losses Compressor Pipe Frictional Pressure Drop – Function of Flow rate, diameter, coating, etc Station Pressure Added – Costs Energy and $ Pipe Frictional Pressure Drop

Many Physical Constraints Compressor Pipe Station Pipe Installed Power, Shaft Torque, Case Pressures, etc

Many Physical Constraints Compressor Pipe Station Pipe Installed Power, Shaft Torque, Case Pressures, etc MAOP, MINP, ETC

Operational Implications Compressor Pipe Station Pipe Constraints MAOP, MINP, ETC

Operational Implications Compressor Pipe Station Pipe Constraints MAOP, MINP, ETC

Operational Implications Some days it’s easy to satisfy constraints Some days it’s hard or

Operational Implications Some days it’s easy to satisfy constraints Some days it’s hard or impossible

What is Line Pack?

What is Line Pack?

Redistribution of Mass and Energy

Redistribution of Mass and Energy

Visualization of Line Pack by bar chart

Visualization of Line Pack by bar chart

New loads always draw on line pack Gas does not instantaneously transport itself 600

New loads always draw on line pack Gas does not instantaneously transport itself 600 miles when the side load comes online!

Sample problem attributes We have 1000 Miles of pipe initially operating at about 95%

Sample problem attributes We have 1000 Miles of pipe initially operating at about 95% of maximum attainable steady state flow. 25 Compressor stations of 25, 000 HP each operating in a time dependent manner to overcome frictional pressure losses while avoiding maximum and minimum pressure limits. To put this into perspective, note that this sample transmission pipeline has installed compressor power roughly equivalent to the power plants of 200 locomotives, or of 2 Nimitz class nuclear aircraft carriers. The work that can be performed over a one day period is also comparable to that expended in 2 space shuttle launches. Construction costs for such a pipeline are on the order of 2 billion dollars. For further perspective, note that this example is small compared to major North American lines, which may have an order of magnitude more capacity.

Sample problem attributes We consider a transient side load that temporarily puts the pipeline

Sample problem attributes We consider a transient side load that temporarily puts the pipeline at over 115% of it’s steady capacity. This “insanely difficult” challenge is actually becoming common due to the increased usage of natural gas fired “peaking electric power plants. ” This is possible because of “line-pack” manipulation – mass and energy stored in the pipeline itself.

Today’s example: 25 Station Pipeline TWO POTENTIAL SIDE DELIVERIES

Today’s example: 25 Station Pipeline TWO POTENTIAL SIDE DELIVERIES

Technical Assumptions • As always, we use full nonlinear partial differential equation model for

Technical Assumptions • As always, we use full nonlinear partial differential equation model for pipeline hydraulics. • Realistic equipment models are used including realistic system limitations.

First: Scheduled Side Loads • Assume an upcoming plant load is completely predictable. •

First: Scheduled Side Loads • Assume an upcoming plant load is completely predictable. • For success, the load must be delivered fully and smoothly using only available compression, without violating any pressure limitations anywhere in the system, and the desired final state must be achieved by the end of the day.

Optimal Pack Redistribution • We know with certainty that the power plant at Station

Optimal Pack Redistribution • We know with certainty that the power plant at Station 17 is coming online at 2 PM. • Where should we place line pack to get ready? • How do we get it there using only available compression and without violating limits? • How do we use it after the load comes on?

Initially 95% loaded, Jumps to over 115% during side delivery LOAD COMING AT 2

Initially 95% loaded, Jumps to over 115% during side delivery LOAD COMING AT 2 PM AT STATION 17 Always remember gas does not instantaneously transport itself 600 miles when the side load comes online!

General problem form – minimize f(S) s/t • S = s(x; L) where –

General problem form – minimize f(S) s/t • S = s(x; L) where – S is the system state (pressures in space and time) – s is the simulation (coupled system of PDEs) – x is the control vector (compressor settings in space and time) – L is the set of boundary conditions (upcoming load patterns in space and time) • Equipment Constraints • Min and Max Pressure Constraints, etc.

Initially 95% loaded, Jumps to over 115% during side delivery LOAD COMING AT 2

Initially 95% loaded, Jumps to over 115% during side delivery LOAD COMING AT 2 PM AT STATION 17

Why does pack redistribution help? • Puts the mass at the right place at

Why does pack redistribution help? • Puts the mass at the right place at the right time. • Energy stored as compression can have the effect of (temporarily) geographically redistributing the power available to move gas.

How do we achieve this pack? • The software provides operators with a schedule

How do we achieve this pack? • The software provides operators with a schedule of set points. • Discharge pressure is used in our example but other controls are trivially available. • The set points are our control plan and the evolving line pack is the hydraulic consequence of following this plan.

Set point changes needed to achieve pack preparation

Set point changes needed to achieve pack preparation

Pack redistribution during preparation

Pack redistribution during preparation

Twenty four hours of Set point changes in One Minute

Twenty four hours of Set point changes in One Minute

Twenty Four Hours of Line Pack Changes

Twenty Four Hours of Line Pack Changes

Another possible side load SIDE LOAD, 20% TOTAL SYSTEM CAPACITY, 384 miles from previous

Another possible side load SIDE LOAD, 20% TOTAL SYSTEM CAPACITY, 384 miles from previous example

Power Plant at Station 7 • Example 2 – Suppose the upcoming load is

Power Plant at Station 7 • Example 2 – Suppose the upcoming load is at station 7 rather than station 17. – This is 384 miles (640 KM) from the load in our previous example. – How would our optimal line pack preparation differ?

Difference in Optimal Preparation is Dramatic

Difference in Optimal Preparation is Dramatic

Peaking Gas-Fired Power Plant Loads TWO POTENTIAL SIDE DELIVERIES Which actually occurs will depend

Peaking Gas-Fired Power Plant Loads TWO POTENTIAL SIDE DELIVERIES Which actually occurs will depend on weather, electric spot market prices, stock market, etc

Uncertainty • Assume we only know what loads are possible later today rather than

Uncertainty • Assume we only know what loads are possible later today rather than having absolute certainty. • Preparing for one particular eventuality, even if it is most likely, may be exactly the wrong thing to do to prepare effectively for other possibilities. • Transient optimization with hedging can be used to optimally position line pack to prepare for such loads.

General problem form – minimize f(S, T) s/t • S = s(x; L) for

General problem form – minimize f(S, T) s/t • S = s(x; L) for control x and boundary conditions L • T = s(y; M) for control y and boundary conditions M • x and y are forced to be identical before the load onset but recourse is allowed afterwards • Plus other normal constraints on S, T, equipment, etc.

Difference in Optimal vs Hedged Preparation is Dramatic

Difference in Optimal vs Hedged Preparation is Dramatic

Uncertainty • “Uncertainty” in today’s talk doesn’t mean we don’t know what range of

Uncertainty • “Uncertainty” in today’s talk doesn’t mean we don’t know what range of events is likely to happen. • It just means we don’t really know whether any particular event will unfold at a precisely predictable time and place. • Terminology: Epistemic or Aleatory?

Discussion • Comparison with other engineering approaches to dealing with uncertainty • An Analogy

Discussion • Comparison with other engineering approaches to dealing with uncertainty • An Analogy

HEDGING TO PLAN FOR UNCERTAIN FUTURE EVENTS Mt Fuji WEST TOKYO AN ANALOGY EAST

HEDGING TO PLAN FOR UNCERTAIN FUTURE EVENTS Mt Fuji WEST TOKYO AN ANALOGY EAST TOKYO

ARMY Mt Fuji PLAN A WEST TOKYO MAKE BEST GUESS AND COMMIT YOUR FORCES

ARMY Mt Fuji PLAN A WEST TOKYO MAKE BEST GUESS AND COMMIT YOUR FORCES EAST TOKYO

ARMY WEST TOKYO Mt Fuji PREPARATION USING 50 -50 SPLIT MAY FARE NO BETTER

ARMY WEST TOKYO Mt Fuji PREPARATION USING 50 -50 SPLIT MAY FARE NO BETTER ARMY EAST TOKYO

ARMY WEST TOKYO Mt Fuji INCREASING SIZE OF ARMY DOES NOT NECESSARILY TRANSLATE INTO

ARMY WEST TOKYO Mt Fuji INCREASING SIZE OF ARMY DOES NOT NECESSARILY TRANSLATE INTO MORE SAFETY. ARMY EAST TOKYO

Observations • Planning for only one eventuality can lead to poor performance or even

Observations • Planning for only one eventuality can lead to poor performance or even failure should another one occur. • Naïve planning for several eventualities can also lead to poor performance. • Increasing operational safety margins increases cost, but may or may not help with dependability.

ARMY Mt Fuji ARMY WEST TOKYO HEDGED SOLUTION AFTER DEFENSIVE PLAN EXECUTED EAST TOKYO

ARMY Mt Fuji ARMY WEST TOKYO HEDGED SOLUTION AFTER DEFENSIVE PLAN EXECUTED EAST TOKYO

Other examples of optimal preparation • First two examples showed optimal preparation for two

Other examples of optimal preparation • First two examples showed optimal preparation for two different, challenging scenarios where possible loads were separated in space. • Third example showed a hedged solution that effectively prepared for either example. • What else might we profitably hedge against? How about uncertainty in both space and time?

Paying the Piper • In hedging, you traditionally have to give up something to

Paying the Piper • In hedging, you traditionally have to give up something to get your benefits. • This is expected in hedged transient pipeline optimization as well. • In our enclosed examples, the extra energy cost for a hedged solution versus a known-future solution was tiny. • We don’t expect that to always be true.

Conclusions • Transient optimization allows some rather remarkable things to be done with pack

Conclusions • Transient optimization allows some rather remarkable things to be done with pack management. • For the applications of most interest to us, “optimization under uncertainty” is about defensive preparation for large discrete events that we know may happen, rather than optimization over a distribution of possibilities. • Hedging is a promising tool for managing this type of uncertainty.

The End

The End

ARMY Mt Fuji ARMY WEST TOKYO UNCERTAINTY CAN ALSO BE IN TIME. WE CAN

ARMY Mt Fuji ARMY WEST TOKYO UNCERTAINTY CAN ALSO BE IN TIME. WE CAN HEDGE AGAINST THAT TOO EAST TOKYO

ARMY Mt Fuji ARMY WEST TOKYO Hedged preparation against uncertainty in onset time EAST

ARMY Mt Fuji ARMY WEST TOKYO Hedged preparation against uncertainty in onset time EAST TOKYO