Lafayette New Terminal Program Update May 8, 2019

Lafayette New Terminal Program Update May 8, 2019

FAA • Currently managing grants • White paper sent requesting funds for 2019 LA

FAA • Currently managing grants • White paper sent requesting funds for 2019 LA DOTD Terminal Program Update - Funding • Currently managing grants • 2019 Program reviewed by State Legislature Joint Transportation Committee LA FP&C • Coordinating with FP&C on eligible items for terminal construction • • Preparing individual FP&C packages for terminal construction 2019 Capital Outlay Application submitted • Applying for $10 million towards terminal construction to be available in the Fall

EDA Grant Application Funding Approved Coordinating additional information TSA OTA Application Terminal Program Update

EDA Grant Application Funding Approved Coordinating additional information TSA OTA Application Terminal Program Update - Funding Submitted Grant Application, unfunded in 2019 Airlines Working with airlines to discuss leasable space and an agreement to buildout space QTA/Ready Return Concessions

Enabling Demo • Construction Complete. Final Acceptance upcoming Rental Car Quick Turn Around Facility

Enabling Demo • Construction Complete. Final Acceptance upcoming Rental Car Quick Turn Around Facility (QTA) Construction: Notice to Proceed (NTP) 4/15/19; Scheduled Completion Q 1 2020 Upcoming Construction Activities Terminal Program Update – Projects Earthwork, demo existing utilities, tie in new utilities

Program Package 1: RTR, Enabling Projects and Terminal Foundations Approved 9/25/18, Notice to Proceed

Program Package 1: RTR, Enabling Projects and Terminal Foundations Approved 9/25/18, Notice to Proceed 11/12/18 Terminal Program Update – Projects Description Actual Start Planned Sub. Comp. Project 1 - RTR Cable Relocation Nov. 2018 Apr. 2019 (actual) Project 2 – RTR Facility Nov. 2018 Jun. 2019 Project 3 – Terminal Foundations Jan. 2019 Jul. 2019 Project 4 – Airside Improvements TBD Project 5 – Enabling Parking Nov. 2018 May. 2019 Project 6 – Terminal Landside TBD Program Package 2: Structural Steel, Elevators and Escalators Approved 1/15/19, Notice to Proceed 1/15/19 Description Planned Start Planned Sub. Comp. Construction Jul. 2019 Nov. 2019 Program Package 3: Terminal Building Shell, MEP and Finishes - Bid and Award March – June 2019 Description Projected Start Planned Sub. Comp. Construction Nov. 2019 2022

New Terminal Program Progress: Day 176

New Terminal Program Progress: Day 176

Project 2 – RTR Facility Final interior finishes (VCT floor, paint, testing/commissioning equipment) Seeding

Project 2 – RTR Facility Final interior finishes (VCT floor, paint, testing/commissioning equipment) Seeding laydown areas May/June completion GMP 1 – Project 2 RTR Facility

Project 3 – Terminal Foundations Construction piers, grade beam, pilasters and anchor bolts –

Project 3 – Terminal Foundations Construction piers, grade beam, pilasters and anchor bolts – ongoing Underground utilities – ongoing GMP 1 : Project 3 Terminal Foundations

Project 3 – Terminal Foundations Completion July 2019 GMP 1 : Project 3 Terminal

Project 3 – Terminal Foundations Completion July 2019 GMP 1 : Project 3 Terminal Foundations

Project 5 – Enabling Parking Phase 3 B - Substantial completion short term parking

Project 5 – Enabling Parking Phase 3 B - Substantial completion short term parking lot Phase 3 A Soil Stabilization – under engineer/PM review GMP 1 – Project 5 Enabling Parking Asphalt and fencing – ongoing