Lafayette New Terminal Program Update March 13 2019

  • Slides: 14
Download presentation

Lafayette New Terminal Program Update March 13, 2019

Lafayette New Terminal Program Update March 13, 2019

FAA Terminal Program Update • On site FAA Resident Inspector • Currently managing grants

FAA Terminal Program Update • On site FAA Resident Inspector • Currently managing grants LA DOTD • Currently managing grants

LA FP&C • Coordinating with FP&C to confirm bid process and eligible items for

LA FP&C • Coordinating with FP&C to confirm bid process and eligible items for terminal contribution • 2019 Capital Outlay Application submitted Terminal Program Update • Applying for $7 million towards terminal construction to be available next Fall EDA Grant Application Revised EDA grant application submitted and received decision that the application meets further consideration TSA OTA Application Submitted Grant Application, waiting on feedback

Airlines Working with Airlines to discuss leasable space and an Terminal Program Update agreement

Airlines Working with Airlines to discuss leasable space and an Terminal Program Update agreement to buildout space in New Terminal QTA Ready Return Continued to meet with Rental Car Companies, moving forward on QTA Lease Rates Rental cars agreement to move to Short Term Lot - completed Concessions

Enabling Demo • Demolition - Complete • AOA fencing and gates – Complete •

Enabling Demo • Demolition - Complete • AOA fencing and gates – Complete • Fill Material and Asphalt – Complete Terminal Program Update • Seeding/Sod – Complete • Substantially Complete • Reviewing completion paperwork and waiting on 45 -day lienfree period • Final Acceptance - upcoming

Rental Car Quick Turn Around Facility Timeline: Oct. 2018: Commission Approved Updated CFC Nov.

Rental Car Quick Turn Around Facility Timeline: Oct. 2018: Commission Approved Updated CFC Nov. 2018: Construction Bids Due Dec. 2018: Approved Bids Terminal Program Update Jan. 2019: FP&C Construction Concurrence Feb. 2019: Award Contract Preconstruction meeting completed 2/20/19 Apr. 2019: NTP Feb. 2020: Construction Complete

GMP 1: Approved 9/25/18, Notice to Proceed 11/12/18 Terminal Program Update Description Est. Start

GMP 1: Approved 9/25/18, Notice to Proceed 11/12/18 Terminal Program Update Description Est. Start Sub. Comp. Project 1 - RTR Cable Relocation Nov. 2018 Mar. 2019 Project 2 – RTR Facility Nov. 2018 Jun. 2019 Project 3 – Terminal Foundations Jan. 2019 Jul. 2019 Project 5 – Enabling Parking Nov. 2018 Mar. 2019 GMP 2: Approved 1/15/19, Notice to Proceed 1/15/19 Description Est. Start Sub. Comp. Terminal Structural Steel, Elev. and Escalators Jan. 2019 Nov. 2019 GMP 3: Terminal Building Shell, MEP and Finishes 100% Design to complete in Feb. 2019 – Presentation in April Bidding in Mar. 2019 Approval by LAC May 2019

New Terminal Construction Update Project 1 – RTR Cable Relocation Cable wire pulled, spliced,

New Terminal Construction Update Project 1 – RTR Cable Relocation Cable wire pulled, spliced, and FAA cutover complete Manholes 1 through 4 set and backfilled, asphalt placement upcoming GMP 1 – Project 1

New Terminal Construction Update Project 2 – RTR Facility Duct banks for the RTR

New Terminal Construction Update Project 2 – RTR Facility Duct banks for the RTR cable from the building to tower – complete Building walls and roof trusses– complete GMP 1 – Project 2 RTR Facility

New Terminal Construction Update Project 2 – RTR Facility RTR tower foundations – ongoing

New Terminal Construction Update Project 2 – RTR Facility RTR tower foundations – ongoing Facility ice and water shield – ongoing GMP 1 – Project 2 RTR Facility

New Terminal Construction Update Project 3 – Terminal Foundations Test Pile Program – installed

New Terminal Construction Update Project 3 – Terminal Foundations Test Pile Program – installed and testing Milling and fence moving – ongoing GMP 1 – Project 3 Terminal Foundations

New Terminal Construction Update Project 5 – Enabling Parking Economy lot – site grading

New Terminal Construction Update Project 5 – Enabling Parking Economy lot – site grading and compaction – ongoing Short-term parking lot re-striping – completed Substantial completion for short term parking lot (Phase 3 B) GMP 1 – Project 5 Enabling Parking