Ladder Assembly @ HEPHY Christian Irmler (HEPHY Vienna) 12 th Open Meeting of the Belle II Collaboration 23 July 2012
Status • Plan to build a full L 5 ladder in 2012 • (Re-) Design & production of front-end components – Origami hybrids (CE, -z, +z) – Single layer pitch adapters (PA 0, PA 1, PA 2) – Edge hybrids (L 4 -6) • Assembly of 2 -DSSD module • Electrical test of new hybrids • … 23 July 2012 Christian Irmler (HEPHY Vienna) 2
Quality of single layer pitch adapters • Two companies – Origami hybrids: Taiyo / PAs: Azuma • Single layer design (Azuma) – pro: thinner, more flexible, easy to bend – contra: • PA 0 has to be glued by us requires dedicated jigs • very small bond pads at APV side • wire bonding needs to be very precise • cover layer of PA 0 peeled off after gluing! • shape of cover layer is not precisely cut 23 July 2012 Christian Irmler (HEPHY Vienna) 3
Ladder assembly plans • Ladder production starts in summer 2013! – will take roughly 1 year, depending on layer • SVD assembly (ladder mount) starts Sept. 2014 23 July 2012 Christian Irmler (HEPHY Vienna) 4
Ladder assembly plans • 2 -DSSD module tests (source, cooling, beam) • Additional tests of single layer pitch adapters – gluing and bonding tests – final decision whether single- or double-layer design should be used • • Adopt the L 6 jigs for L 5 assembly Build another 2 -DSSD module (before beam test) Beam test and irradiation of 2 -DSSD modules Build a full ladder of L 5 (end of 2012) 23 July 2012 Christian Irmler (HEPHY Vienna) 5