LAB Test Modules components inventory and procurement schedule
LAB Test Modules components inventory and procurement schedule In LAB testing facility A. Bartalesi 16. 05. 2012
Updates of the last two weeks � The first half of the TM 0 accelerating structure has been assembled, together with the RF network, vacuum network and compact loads. � TM 0 DBQ mock-up heaters have been received. � The TM 1 MB girder with integrated V-shaped supports for the LAB has been technically validated. Offers are now being evaluated. � TM 4 DB additional V-shaped support delivery date shifted due to a technical failure during fabrication. New delivery date is the week 22 at the latest. A. Bartalesi 16. 05. 2012
Procuring overview TM 0 s Priotity 0 Priority 1 • Floor interface • MB girders plate • V-shaped • Floor interface supports plate • Cradles • Actuators • DB girders • V-shaped supports • Cradles • Actuators Priority 2 • Accelerating structures • Damping material • Cooling interfaces • RF flanges • Interconn. bellows • PETS • Damping material • Cooling interfaces • RF flanges • Interconn. flanges • DB QUADS • BPM • Vacuum chamber • Support plate • Interconn. bellows Priority 3 • Vacuum • Supports • Vacuum reservoir • Interconn. bellows Priority 4 Priority 5 • RF distribution • Vacuum • Waveguides network • RF components • RF flanges • RF loads Priority 6 • Cooling system R Priority 7 • Heating device • Transport device c e v i e d e Labels: 3 D done 2 D done Ordered Delivered A. Bartalesi 16. 05. 2012
Procuring overview TM 1 Priotity 0 Priority 1 Priority 2 • MB Floor • MB girders • Accelerating interface plate structures • V-shaped • DB Floor interface supports • Damping plate material • Cradles • Cooling • Actuators interfaces • MBQ prealignment system • RF flanges • MBQ stabilization • Interconn. flanges system • Interconn. • DB girders bellows • V-shaped • PETS supports • Damping • Cradles material • Actuators • Cooling interfaces • RF flanges • Interconn. flanges • MBQ BPM • DBQ • BPM • Vacuum chamber • Support plate • Interconn. bellows • Drift tube a V a d li d te Priority 3 • RF distribution • Waveguides • RF components • RF flanges • RF loads Priority 4 Priority 5 • Vacuum support • Cooling system • Vacuum reservoir • Interconn. bellows • Mini-pumps Priority 6 • Heating device • Transport device Labels: 3 D done 2 D done Ordered Delivered A. Bartalesi 16. 05. 2012
Procuring overview TM 4 Priotity 0 Priority 1 • MB Floor • MBQ preinterface alignment plates system • DB Floor • MBQ interface plate stabilization system • DB girder • V-shaped supports • Cradles • Actuators Priority 2 • MBQ • Vacuum chamber • MBQ BPM • DBQ • BPM • Vacuum chamber • Support plate • Interconn. bellows • Drift tubes Priority 3 • Cooling system Priority 4 • Transport device Labels: 3 D done 2 D done Ordered Delivered A. Bartalesi 16. 05. 2012
Thank you! A. Bartalesi 16. 05. 2012