JLEIC Engineering Status T Michalski June 15 2017

  • Slides: 11
Download presentation
JLEIC Engineering Status T. Michalski June 15, 2017

JLEIC Engineering Status T. Michalski June 15, 2017

JLEIC Interaction Region Status: R&D Plans for SC Magnets Proposal, schedule and budget for

JLEIC Interaction Region Status: R&D Plans for SC Magnets Proposal, schedule and budget for TAMU Model Dipole completion IR Magnets – collaboration with BNL IR Magnets – TOSCA designs at JLab (Started) LDRD Proposal for 6 T SC Dipoles and 3 T Fast Ramping SC Dipoles Design and Layout IR Layout – initial layout – awaiting further detail on magnets and vacuum pipe design requirements Tunnel size and cross section validation – underway Staffing 2

TAMU Model Dipole Plan for using supplemental R&D funds to complete the design of

TAMU Model Dipole Plan for using supplemental R&D funds to complete the design of the model dipole during FY’ 18 Testing cannot be afforded until FY’ 19, based on supplemental R&D budget TAMU anxiously awaiting funding to get things started Further details from Peter Mc. Intyre 3

IR Magnet – BNL Collaboration We have assessed opportunities to collaborate with BNL on

IR Magnet – BNL Collaboration We have assessed opportunities to collaborate with BNL on aspects of the IR magnet designs Focus will be on higher field magnets – looking at Nb 3 Sn as the conductor Preliminary assessment is there is an Ion Ring FFQ which has similar requirements for both JLEIC and e. RHIC Plan to review requirements in FY’ 17 and start concept design Neither lab sees this fitting into FY’ 18 supplemental R&D funding 4

IR Magnet – TOSCA Modeling Paul Brindza has completed a first design of the

IR Magnet – TOSCA Modeling Paul Brindza has completed a first design of the SB 1 dipole – working to get it modeled in NX (CAD) Renuka is working on QFFB 1, with preliminary results 5

SC Magnet LDRD Probir has submitted a LDRD focused on: 6 T SC dipoles

SC Magnet LDRD Probir has submitted a LDRD focused on: 6 T SC dipoles for the Ion Collider Ring Needed for 100 Ge. V center of mass energy Alternate technology solution to SF magnets for 3 T fast ramping dipoles for the Booster Ring 3 T slower ramping dipoles for the Ion Collider Ring Based on R&D Committee recommendations – insure we have backups for SF magnets Will collaborate with LBNL on LDRD 6

JLEIC Interaction Region IR magnets SB 1 IP QFFB 2 QFFB 1 SB 1

JLEIC Interaction Region IR magnets SB 1 IP QFFB 2 QFFB 1 SB 1 QFFB 1_US QFFB 2_US s n o i QFFB 3_US 7 QFFB 3

JLEIC Interaction Region 8

JLEIC Interaction Region 8

All views are from above IP Purple – Electron Final Focus Quads Red –

All views are from above IP Purple – Electron Final Focus Quads Red – Ion Final Focus Quads Green – Spectrometer Dipoles Brown – Detector solenoid anti-solenoids Rectangular & Red – PEP-II HER Quads Rectangular & Blue – PEP-II Dipoles First cut has a variety of “trouble spots” which need to be addressed 9

Design and Layout Site layout with all available rings exists Adding tunnel, based on

Design and Layout Site layout with all available rings exists Adding tunnel, based on FML dimensions and cross section – in process, awaiting further MD availability IR Layout – adding details to IR magnets in NX as information comes available – in process, awaiting further MD availability Adding PEP-II RF Cavity to layout – expect more space behind the beamline is required 10

Staffing Engineering staffing has been spotty, at best Lab priorities have delayed moving staff

Staffing Engineering staffing has been spotty, at best Lab priorities have delayed moving staff to JLEIC SC Magnet Engineers – Hall B Solenoid LCLS-II Cryo and CM requiring bulk of MEs and MDs Anticipate adding the following staff in the next 4 -6 weeks ME – Mark Wiseman – focus on IR (mechanical layout, cryostating FFQs, etc. ) Magnet Engineers – Renuka Rajput-Ghoshal – focus on modeling IR magnets Probir Ghoshal – LDRD and SF Model Dipole MDs – beamline layout, IR beam pipe 11