JASPERS Framework Contract Development of an Investment Programme

  • Slides: 19
Download presentation
JASPERS Framework Contract Development of an Investment Programme for Buildings Rehabilitation – Romania PUBLIC

JASPERS Framework Contract Development of an Investment Programme for Buildings Rehabilitation – Romania PUBLIC BUILDINGS An engine for growth and jobs: EU Funds for energy efficiency International Conference Budapest, 6 November 2013 Project implemented by member of the Consortium 1

Purpose and content of the presentation Purpose: To present the key issues analysed and

Purpose and content of the presentation Purpose: To present the key issues analysed and solutions identified for the design of a Scheme for EE in Public buildings (under the ERDF / Regional Operational Programme of Romania). The proposed scheme follows the general concept of the Scheme elaborated for the Residential buildings. Therefore, this presentation focuses on the main differences and special features of the Scheme for EE in Public buildings. This presentation is based on the JASPERS study. The proposals to be presented do not necessarily reflect the final decisions that are currently under reconsideration by the Ministry. Content: A. Key options for the design and issues to be addressed B. Elaboration of solutions C. Conclusions - Proposals 2

A: Key options for the design of the Scheme and issues to be addressed

A: Key options for the design of the Scheme and issues to be addressed 3

Key options for the design of the scheme - 1 1. Energy Performance Contracting

Key options for the design of the scheme - 1 1. Energy Performance Contracting (EPC) vs traditional public financing of investments The advantages of EPC are recognised, but there were no choice: • ESCO market is at an “embryonic state”, in Romania; despite all efforts so far there is a number of strong barriers; • Procurement officers are not ready to tender out EPC contracts. Short-term launching of a scheme under the ERDF should be based on solutions applicable in practice i. e. public financing; possible involvement of ESCOs at later stage. 4

Key options for the design of the scheme - 2 2. Scheme designed and

Key options for the design of the scheme - 2 2. Scheme designed and applied at regional level (by LPAs) for various types of public buildings vs a set of nationwide schemes, each one addressing a different category of public buildings • The scheme should follow the ownership structure; the majority of public buildings at local level are under the responsibility of the LPAs • A regional scheme fits within a Regional Operational Programme; Complication: different types of buildings/energy systems to be accommodated under rather uniform rules of a Scheme. • The existing structures (PIUs of the LPAs) can be used. 3. The Scheme supports exclusively EE measures that produce direct and measurable energy savings vs major renovation of energy systems combined with EE measures • The second option was proposed (to improve also functionality, safety, lifetime prolongation and reliability) 5

Key issues for the successful implementation Implementation of a Scheme for EE in Public

Key issues for the successful implementation Implementation of a Scheme for EE in Public Buildings through the Local Public Authorities (LPAs) will have to address almost all key issues identified for the residential buildings: • Lack of capacity of public institutions operating public buildings (with few possible exceptions e. g. large hospitals) • Limited capacity of the PIUs – lack of TA • Questionable quality of energy audits (EA) /Energy Performance Certificates (EPCs) • Questionable quality of works- supervision • Increase of investment costs during construction • Lack of an effective monitoring and verification mechanism (local and central) 6

B: Elaboration of solutions 7

B: Elaboration of solutions 7

Approach for the analysis of the investments - 1 The problems for the analysis

Approach for the analysis of the investments - 1 The problems for the analysis of the technical and cost-benefit analysis of the investments are mainly: • Unlikely the residential blocks of flats, there is no “typical public building”, not even “typical hospital” to analyse; • There is a general lack of statistics for public buildings in Romania. 8

Approach for the analysis of the investments - 2 The Consultant, following a rather

Approach for the analysis of the investments - 2 The Consultant, following a rather unsuccessful survey aiming at collecting data from LPAs, : • critically analysed 10 application files with studies for implementation of large scale EE measures in hospitals (supported by the current ROP); hospitals are considered the most “favourable cases” (large energy saving potential and favourable cost/benefit indicators as they operate continuously); • Analysed the virtual case of an administration public building operating about 8 hours/day, 5 days per week i. e. a building with “unfavourable” cost/benefit indicators The comparative results from the “favourable” and “unfavourable” cases provided an assessment for almost the whole spectrum of public buildings. 9

Cost-Benefit Analysis - 1 CBA analysis (financial and economic) was performed from the point

Cost-Benefit Analysis - 1 CBA analysis (financial and economic) was performed from the point of view of the State. It confirmed that: • the investment is financially non-viable, while at the same time it is viable from the economic point of view for both the “favourable” and the “unfavourable” cases, therefore • the Scheme is eligible for EC support. Results – Favourable case (hospitals) Unfavourable case [Assumption: 50% of the investment (excluding TA) is allocated to main EE measures] [Assumption: 60% of the investment (excluding TA) is allocated to main EE measures] Description FRR FNPV ERR ENPV Unit % Th. Euro Amount -1, 5 % -486 10, 8% 482. 1 FNPV<0 Unit % Th. Euro ENPV<0 Amount -4, 8 % -658, 7 8, 4% 255. 7 ENPV>0 Risk analysis for the unfavourable case: • Probability of FNPV>0 is 0% • Probability of ENPV<0 is 13% 10

Cost-Benefit Analysis -2 Financial analysis was performed from the LPA’s point of view to

Cost-Benefit Analysis -2 Financial analysis was performed from the LPA’s point of view to identify the break-even point (level of LPA’s contribution to have no-loss no-profit). The analysis confirmed that: • LPAs must have a quite significant contribution to the investment costs in all cases (otherwise they will get profit from the energy cost savings). Financial NPV for the LPA for different co-financing levels LPA co-financing level % 10 20 30 40 50 60 100 Total investment k€ 1000 1000 Investment for the LPA k€ 100 200 300 400 500 600 1000 FNPV- Favourable case k€ 414 314 214 14 -86 -486 FNPV- Unfavourable case k€ 241. 3 141. 3 -58. 7 -158. 7 -258. 7 -658. 7 11

Cost-Benefit Analysis CBA analysis (financial and economic) was performed from the point of view

Cost-Benefit Analysis CBA analysis (financial and economic) was performed from the point of view of the State: The CBA and the related sensitivity and risk analysis confirmed that: • the investment is financially non-viable, while at the same time it is viable from the economic point of view for both the “favourable” and the “unfavourable” cases, therefore • the Scheme is eligible for EC support. Financial analysis was performed from the LPA’s point of view to identify the break-even point (level of LPA’s contribution to have no-loss noprofit). The analysis confirmed that: • LPAs must have a quite significant contribution to the investment costs in all cases (otherwise they will get profit from the energy cost savings). 12

C: Conclusions - Proposals 13

C: Conclusions - Proposals 13

Conclusions – Proposals 1 Proposed key features: Ø The scheme for EE in Public

Conclusions – Proposals 1 Proposed key features: Ø The scheme for EE in Public buildings, under ROP, runs in parallel with the scheme for the Residential buildings, utilising the same implementation structures Ø Beneficiaries of the Scheme: Local Public Authorities (LPAs); fully responsible for implementation Ø Management of investment project cycle: Project Implementation Units (PIUs) of the LPAs; maximum involvement of technical services of the institutions Ø Approval of Applications / Financing Agreements with LPAs: Regional Development Agencies Ø System of selection: “First Come, First Served” based on strict eligibility criteria Ø Technical assistance/capacity building for PIUs (supported by consultants) Ø Harmonised reporting, monitoring and verification scheme (supported by consultants)

Conclusions – Proposals 2 Proposed targeted public buildings Ø Ownership: buildings owned by and

Conclusions – Proposals 2 Proposed targeted public buildings Ø Ownership: buildings owned by and operating under the authority of LPAs Ø Categories of buildings (in order of priority): 1. Hospitals and health care institutions operating 24 hours per day, 7 days per week; 2. Buildings delivering social services on a non-stop basis; 3. Buildings offering health care and social services during working hours; 4. Nurseries, schools, universities and vocational training buildings, including campuses and dormitories; 5. Administration buildings providing services to citizens (therefore visited by many citizens); 6. other. 15

Conclusions – Proposals 3 a Proposed scope of interventions A. EE interventions (that produce

Conclusions – Proposals 3 a Proposed scope of interventions A. EE interventions (that produce direct energy savings) in the building envelope and technical energy systems / major energy consuming equipment; Requirements for integrated solutions and minimum acceptable technical specifications B. Renovation and safety improvement measures associated with EE improvement measures; “renovation” can be implemented only in systems where large scale EE measures are applied (to exclude fragmental application of maintenance works) C. Energy Management measures; certain EM measures to be obligatory D. Information dissemination and visibility E. Thresholds in investment cost breakdown between the above categories have been proposed. 16

Conclusions – Proposals 3 b Proposed budget structure thresholds per project investment plan Measure

Conclusions – Proposals 3 b Proposed budget structure thresholds per project investment plan Measure type % of budget (indicative) A. Main EE interventions 60% minimum (50% for hospitals or other buildings with complex energy systems including mechanical ventilation) B. Associated renovation and safety improvement measures 35% maximum (45% for hospitals) C. and D. Energy management and information dissemination measures 7% maximum Technical assistance (audit, design, supervision) 7% (10% for hospitals or other buildings with complex energy systems including mechanical ventilation) 17

Conclusions – Proposals 4 Ø Ø Ø Other important proposed key requirements: Energy class

Conclusions – Proposals 4 Ø Ø Ø Other important proposed key requirements: Energy class before the investment D or lower; after the investment B or A (in exceptional justified cases class C) Minimum final energy savings: 35%; savings are calculated on the total energy consumption of the building incl. space heating, DHW, cooling, electricity); savings from “soft” energy management measures are not taken into account Availability of operation and maintenance services Buildings with special characteristics (architectural, historical, etc. ) are excluded Buildings with structural problems or built before 1950 are excluded 18

For info or further questions on this presentation, please contact: George Chavdarov Energy Engineer

For info or further questions on this presentation, please contact: George Chavdarov Energy Engineer g. chavdarov@eib. org Tero Makela Senior Engineer t. makela@eib. org www. jaspers-europa-info. org jaspersnetwork@eib. org 19