ISTs in the PS Fernando PEDROSA Unclear if

  • Slides: 17
Download presentation
ISTs in the PS Fernando PEDROSA

ISTs in the PS Fernando PEDROSA

 • Unclear if controls means the same to all groups • Links and

• Unclear if controls means the same to all groups • Links and dependencies not defined • High risk to discover the D day that some equipment is not available F. Pedrosa 01 -Nov-2019

PS planning file organization Pre-requisites = Things that you need to be completed before

PS planning file organization Pre-requisites = Things that you need to be completed before starting the tests Needs = Things that you need during the tests Tests Risks = risks during the tests F. Pedrosa 01 -Nov-2019

Master schedule Note: Critical path for the ISTs in the PS is in the

Master schedule Note: Critical path for the ISTs in the PS is in the PS SWY F. Pedrosa 01 -Nov-2019

Main shutdown works – from February 2020 F. Pedrosa 01 -Nov-2019

Main shutdown works – from February 2020 F. Pedrosa 01 -Nov-2019

Access constraints – Main focus on the PS SWY Note: For the PS ring

Access constraints – Main focus on the PS SWY Note: For the PS ring we will need 3 / 4 days middle of June to test the auxiliary magnets in the ring and to perform an HV test after the covers installation F. Pedrosa 01 -Nov-2019

BE-BI F. Pedrosa 01 -Nov-2019

BE-BI F. Pedrosa 01 -Nov-2019

BE-RF • Before finalizing the draft planning for RF at least one additional meeting

BE-RF • Before finalizing the draft planning for RF at least one additional meeting is needed to discuss the last version of the ISTs received last week (meeting scheduled to next Monday morning) F. Pedrosa 01 -Nov-2019

EN-STI F. Pedrosa 01 -Nov-2019

EN-STI F. Pedrosa 01 -Nov-2019

TE-ABT • TE-ABT validated already most of these tests schedule F. Pedrosa 01 -Nov-2019

TE-ABT • TE-ABT validated already most of these tests schedule F. Pedrosa 01 -Nov-2019

TE-EPC • POPS part is already validated by TE-EPC • Some additional details are

TE-EPC • POPS part is already validated by TE-EPC • Some additional details are needed from EPC regarding some tests, which could affect some ISTs from other systems – Y. Gaillard is working on collecting this additional information F. Pedrosa 01 -Nov-2019

TE-MSC • Most of these tests and associated works (covers removal or covers installation)

TE-MSC • Most of these tests and associated works (covers removal or covers installation) have been checked with TEMSC – validation should come in the coming days F. Pedrosa 01 -Nov-2019

ISTs F. Pedrosa 01 -Nov-2019

ISTs F. Pedrosa 01 -Nov-2019

ISTs + Activities F. Pedrosa 01 -Nov-2019

ISTs + Activities F. Pedrosa 01 -Nov-2019

DSO tests Note: Even if the DSO tests are not an IST, they have

DSO tests Note: Even if the DSO tests are not an IST, they have been included in the ISTs planning with the same structure + same level of details, and will be sent for validation to the BE DSO (like all the other tests to the respective responsible) F. Pedrosa 01 -Nov-2019

Conclusions • The ISTs planning for the PS SWY part is in the critical

Conclusions • The ISTs planning for the PS SWY part is in the critical path and schedule is tight, but preparation is already in a very good level of detail • The ISTs planning for the PS Ring has some margin and could use part of the Hardware Commissioning period if needed (proposed by the OP colleagues) • Some discussions are still needed with BE-RF • Some information is still missing from TE-EPC, but they are working on it • The F 61 commissioning planning is still not detailed enough and discussions are ongoing with the project to see if some agreements done in the past could be reversed to gain some margin • The BTP commissioning on the PS side is still not detailed in the ISTs PS planning • DSO tests included in the ISTs planning • Information on links and dependencies is most of the times unavailable, so there is a high risk of not being able to perform the test within the allocated slot due to the unavailability of such information F. Pedrosa 01 -Nov-2019