ISOLDE HIE ISOLDE Status and Plans Richard Catherall

  • Slides: 46
Download presentation
ISOLDE & HIE ISOLDE Status and Plans Richard Catherall EN-STI ISOLDE Technical Coordinator IEFC

ISOLDE & HIE ISOLDE Status and Plans Richard Catherall EN-STI ISOLDE Technical Coordinator IEFC Workshop 7 th – 9 th March 2012

Outline • Status and plans for 2012 experiments • Shifts and schedule • RILIS

Outline • Status and plans for 2012 experiments • Shifts and schedule • RILIS and REX operation • New experiments for post accelerated beams 2012 • HIE-ISOLDE status and plans • Reports and recommendations from the IAP • Cavity design and tests • Civil engineering and installation work LS 1 • Foreseen activities for LS 1 • Target area activities • Modifications in the experimental hall • Other plans

Injector schedule 2012 35 weeks of physics (vs 29 in 2010, 2011) Guaranteed protons

Injector schedule 2012 35 weeks of physics (vs 29 in 2010, 2011) Guaranteed protons (46% requested): (Possible increase at next research board) Protons for ISOLDE restart in spring 2014

ISOLDE schedule 2012 Status today: 9 IS experiments and 2 LOIs CLOSED this month

ISOLDE schedule 2012 Status today: 9 IS experiments and 2 LOIs CLOSED this month 79 IS experiments and 9 LOIs OPEN (711 + 30 requested shifts) + 14 IS experiments and 5 LOIs SUBMITTED to this INTC (193 + 17 requested shifts) 1059 remaining shifts for proposals and LOIs 904 + 47 (LOIs) shifts requested so far (66 more might be still requested) Reasonable number of shifts that can be scheduled in 2012: 590

RILIS operation Ion beams of 15 elements were produced 5 Laser ON time in

RILIS operation Ion beams of 15 elements were produced 5 Laser ON time in 2011: Ø 2756 h – Total Ø 2527 h – On-line • > 50 % of the Total running time of ISOLDE facility 197 (250) shifts in 2011 ~ 250 (300) planned for 2012 Beam Sm Ga Mg At Pb Dy Nd Pr Ag Tl Cd Mn Ni Yb Zn Planned 80 104 256 160 184 64 136 - 112 208 288 120 272 - 376 Real 89 101 146 269 221 35 110 4 92 231 242 390 348 73 407

REX Operation • Delivered shifts for experiments and LOIs in 2011: – REX –

REX Operation • Delivered shifts for experiments and LOIs in 2011: – REX – 147 shifts (160 shifts scheduled) • Similar plans for 2012: ~200 shifts to be scheduled – Enable 2 ms RF pulse length on all amplifiers for slow extraction tests to be done in 2012 – A few “difficult” light beams will require testing and further tuning

Rare decays of 6 He with an optical chamber incoming 6 He ions New

Rare decays of 6 He with an optical chamber incoming 6 He ions New experimental setups using postaccelerated beams gas at atmospheric pressure d ionization electrons a HV electrodes e gating electrode charge amplification zone GEM foils light REX Recording system Trigger CCD PMT

New experimental setups using postaccelerated beams Scattering chamber for studies of nuclosynthesis (rapid proton-capture)

New experimental setups using postaccelerated beams Scattering chamber for studies of nuclosynthesis (rapid proton-capture) Nuclear structure of very light nuclei with an active target p ΔE-E Ec. m.

Offline experiment: Measure 44 Ti(a, p) reaction at supernova energy Ejected 44 Ti becomes

Offline experiment: Measure 44 Ti(a, p) reaction at supernova energy Ejected 44 Ti becomes gamma emitter => Sensitive diagnostic of explosion mechanism Core collapse supernovae Material: Extraction and acceleration: Source of 44 Ti: PSI Exotic radionuclides from accelerator waste for science and technology ~1018 atoms available Experiment:

Outline • Status and plans for 2012 experiments • Shifts and schedule • RILIS

Outline • Status and plans for 2012 experiments • Shifts and schedule • RILIS and REX operation • New experiments for post accelerated beams 2012 • HIE-ISOLDE status and plans • Reports and recommendations from the IAP • Cavity design and tests • Civil engineering and installation work LS 1 • Foreseen activities for LS 1 • Target area activities • Modifications in the experimental hall • Other plans

Highlights from the IAP report: Cryomodule Design • The top loading design is a

Highlights from the IAP report: Cryomodule Design • The top loading design is a good choice with examples in ISAC-II, LNL, MSU and ANL. • For the cryogenic safety the IAP has the impression that the numbers presented for the burst disk size to mitigate overpressure in the case of a venting accident are over conservative • Concerns about the use of MLI => consider nickel plating of thermal shield and electro-polishing large surfaces (mirror-like) helium reservoir • The cryomodule assembly sequence should be optimized to give adequate access to the cavities in case they have to be rinsed in the future • The capability to helium condition the cavities by adding a leak system to the cryomodule should be analyzed at the cavity testing stage • A 1400 W cryogenic plant should have sufficient margin.

Highlights from the IAP report RF Cavities • Work on the cavity has made

Highlights from the IAP report RF Cavities • Work on the cavity has made good progress and is on the right path although many cold tests are still necessary to get things settled • It is almost certain that the very stringent specification on the inner conductor beam port is too tight by probably a factor of ten at least. It is suggested that cavity development should proceed with this as a fact while beam simulations are done in parallel to confirm. • It is noted that one of the RF performance curves reaches the high field value 6 MV/m and has a very low Q-slope for a sputtered cavity but a Qo which is a factor of ten from the goal. – evaluate influence of tuner plate

Highlights from the IAP report: General • Possible concerns are related to realities of

Highlights from the IAP report: General • Possible concerns are related to realities of funding which may cause complicated procurement strategies • Synergies between ESS and HIE-ISOLDE should be explored with regard to the training of people • The goal of having the 5. 5 Me. V/u linac commissioned in 2014 is tight but still possible => risk analysis by Sep. 2012 • Diagnostics look well thought out and conceptually well advanced for this stage of the project. • Compare safety protocols with other operating facilities • A finalization of the experimental layout is required • The IAP suggests that attention must be given on the production of xrays • The IAP strongly support the addition of the storage ring to the ISOLDE infrastructure

RF Measurements @ 4. 5 K (2011) 1 E+10 Q 1 Mag Dec 2010

RF Measurements @ 4. 5 K (2011) 1 E+10 Q 1 Mag Dec 2010 -1 st (150ºC) Q 1 Mag Feb 2011 -2 nd (150ºC) Q 1 Diode Jul 2011 (150ºC) Q 2 Mag Sept 2011 (150ºC) Q 1 Mag Nov 2011 (370 ºC) Q 2 Diode Dec 2011 ( 470ºC) HIE-ISOLDE specification Quality Factor 1 E+09 1 E+08 1 E+07 1 E+06 0 1 2 3 4 Eacc(MV/m) 5 6 7

RF Measurements (2012) 1 E+09 Quality factor ~ 35 W @ 6 MV/m 1

RF Measurements (2012) 1 E+09 Quality factor ~ 35 W @ 6 MV/m 1 E+08 Q 2_6 January 2012 ~ 70 W @ 6 MV/m Q 1_9 cal 1 Q 1_9 cal 2 1 E+07 0 1 2 3 4 Eacc (MV/m) 5 6 7 8

Outlook for 2012 Ø Completion of Civil Engineering Works by Q 3 2012 Ø

Outlook for 2012 Ø Completion of Civil Engineering Works by Q 3 2012 Ø Installation of Main Services (EL, CV, Transport) Ø Launch procurement of Cryogenic Plant (FC Mar. 2012) Ø Launch procurement of first batch of 5 (+5 option) high-beta cavities + ancillaries by Q 1 2012. Ø Review Cryomodule Design (26 -27 Apr. 2012) and launch procurement of CM 1 by Q 2 2012. Ø Review HEBT Layout (25 Apr. 2012) and launch procurement Ø Validate LLRF system and tuner plate design

Hie-Isolde Planning A simplified presentation of the different stages: 2011 Q 2 Q 3

Hie-Isolde Planning A simplified presentation of the different stages: 2011 Q 2 Q 3 2012 Q 4 Q 1 Q 2 Q 3 2013 Q 4 Q 1 Q 2 Q 3 2014 Q 1 Q 2 Q 3 2015 Q 4 Q 1 Q 2 Q 3 2016 Q 4 Q 1 Q 2 Q 3 Q 4 Beam Transfer Lines Civil Cryo Main services Ventilation Demi water Electrical syst. s CM 1&2 CM 5&6 CM 3&4 5. 5 Me. V/u 10 Me. V/u Timeline: sd CM 1&2 LS 1 -What issdthe impact on operations? Dec 2012 shutdown 18 - Isolde & REX Ops sd sd Apr 2014 (Isolde normal operations) Cryo Mod 1 & 2 install (REX perturbations)

Civil Engineering New SAS January 2012

Civil Engineering New SAS January 2012

Main Services Electrical systems, Cooling & Ventilation Start installation main services July 2012

Main Services Electrical systems, Cooling & Ventilation Start installation main services July 2012

Electrical systems: July 2012 – June 2013

Electrical systems: July 2012 – June 2013

Cooling & Ventilation: July 2012 – June 2013

Cooling & Ventilation: July 2012 – June 2013

Cryogenics Compressors: July 2013 – December 2013 Cold Box: Jan 2014 – June 2014

Cryogenics Compressors: July 2013 – December 2013 Cold Box: Jan 2014 – June 2014 23

Tunnel and Cryo Line Cutting walls & install tunnel: Sep 2013 LS 1 Cryo

Tunnel and Cryo Line Cutting walls & install tunnel: Sep 2013 LS 1 Cryo Cold Line: January 2014 – June 2014

Hie-Isolde SC Linac: 5. 5 Me. V/u by the autumn of 2014 First 10

Hie-Isolde SC Linac: 5. 5 Me. V/u by the autumn of 2014 First 10 Me. V/u by March 2016 Bunched beam by 2017 ?

Outline • Status and plans for 2012 experiments • Shifts and schedule • RILIS

Outline • Status and plans for 2012 experiments • Shifts and schedule • RILIS and REX operation • New experiments for post accelerated beams 2012 • HIE-ISOLDE status and plans • Reports and recommendations from the IAP • Cavity design and tests • Civil engineering and installation work LS 1 • Foreseen activities for LS 1 • Target area activities • Modifications in the experimental hall • Other plans

LS 1 Activities for ISOLDE • Robot replacement • Hot Cell Installation • Medicis

LS 1 Activities for ISOLDE • Robot replacement • Hot Cell Installation • Medicis • Target storage area • Miniball move • ISOLTRAP platform • RFQ Cooler alignment • HIE-ISOLDE • PAD-MAD installation – Building 115 move/installation – Building 507 (light building) Target Area Experimental Area

Target Area: Robot replacement • The current ISOLDE robots: – are coming to the

Target Area: Robot replacement • The current ISOLDE robots: – are coming to the end of their lifetime. • No compatible spare parts – Are prone to faults – Have no back-up redundancy – Are limited in flexibility • No further programming possible • Part of the long term improvements in operation is to replace the existing robots.

Target Area: Replacement robot • New robot system based on “known” system. Installation in

Target Area: Replacement robot • New robot system based on “known” system. Installation in target area – Q 4 2013

Target Area: ISOLDE Hot Cell • For the dismantling and oxidation of used ISOLDE

Target Area: ISOLDE Hot Cell • For the dismantling and oxidation of used ISOLDE targets • Pre-conditioning prior to shipment to PSI for waste treatment Location of new Hot Cell Building 179 with target area Installation scheduled for long shutdown 2013

Target Area: Medicis Medical Isotopes Collected from ISOLDE • At present 1. 4 Ge.

Target Area: Medicis Medical Isotopes Collected from ISOLDE • At present 1. 4 Ge. V, 2μA p. May have 2 Ge. V, 4 -8μA protons in 2018, of which 90% can be recuperated at the dump position. • Samples can be transferred to Class A labs via a pneumatic transport system • "Presentation at ICTR-PHE 2012 conference“ by Thierry STORA

Target Area: Medicis • - Ta(p, X)149 Tb is one of the most efficient

Target Area: Medicis • - Ta(p, X)149 Tb is one of the most efficient production method. G. Beyer et al. , Radiochim. Acta 90, 247 (2002) • Can use CERN specific technologies for isotope production (i. e. nano-structured target, patent WO 2010/034364, CERN) • Large variety of isotopes accessible

Exp. Hall: MINIBALL Move Miniball Exp. station Actar / Helios Miniball Beam diagnostics •

Exp. Hall: MINIBALL Move Miniball Exp. station Actar / Helios Miniball Beam diagnostics • Beam transfer line – – • MINIBALL move – • 1 straight section with 2 branches Oct 2013 – Sept 2014 Oct 2013 – April 2014 Planning to be discussed in upcoming MINIBALL Collaboration meeting in 2 weeks

Exp Hall: ISOLTRAP • Mass measurement experiment situated in the middle of the ISOLDE

Exp Hall: ISOLTRAP • Mass measurement experiment situated in the middle of the ISOLDE hall • Platform made of wood – Inacceptable for a Class C type laboratory • Plans to re-furbish the platform – Replace wooden platform with an aluminium platform

Exp Hall: RFQ Cooler • RFQ Cooler Alignment check • Laser at limit of

Exp Hall: RFQ Cooler • RFQ Cooler Alignment check • Laser at limit of transmission for optical cooling experiments • External alignment checks done at the end of 2011 – But to no avail • Internal alignment checks need to be done

PAD & MAD Installation

PAD & MAD Installation

PAD & MAD Installation • Integration currently under discussion • Limited space in hall

PAD & MAD Installation • Integration currently under discussion • Limited space in hall (especially near HRS entrance) • Integration in target area – Conflict with hot cell operations – Access difficulties for large equipment (eg. FE’s, BTY magnets)

Buildings 115 & 507 Present situation (ground floor Jura side): Control room 38

Buildings 115 & 507 Present situation (ground floor Jura side): Control room 38

Solid State Lab 115 1. Increasing the surface of the Solid State Lab in

Solid State Lab 115 1. Increasing the surface of the Solid State Lab in B. 115: Control room 39

Replace building 507 2. Replacing the existing building 507 by a new building -

Replace building 507 2. Replacing the existing building 507 by a new building - Ground floor (only accessible from within the surveyed area): Control room 40

Replace building 507 2. Replacing the existing building 507 by a new building -

Replace building 507 2. Replacing the existing building 507 by a new building - First floor (accessible from outside the surveyed area): Control room 41

Building status • Building 115 (extended solid state laboratory) – Plans completed – Costs

Building status • Building 115 (extended solid state laboratory) – Plans completed – Costs • 407 k. CHF (to be secured) – Make building 275 available for other users – Implies all handling of radioactive sources to within the confines of the ISOLDE perimeter • Building 507 (light building) – Under discussion – HIE-ISOLDE data acquisition rooms outside hall – Visitor’s room – access to visitors will be denied in future when the hall will be defined as a controlled area. – A new version being considered based on partly metallic structure and partly “portacabin” type modules

Target Storage Area 2 new Kuka linear Robots In Isolde Target Area (2013) Handling

Target Storage Area 2 new Kuka linear Robots In Isolde Target Area (2013) Handling with 1 remote controlled vehicle Deliver the new target to the exchange point for the Kuka robots Remove hot target and place on the shelf (during shut down) Move the 3 years decayed target from shelf to hot cell Move waste containers (with “standard” trans-pallet) New hot Cell (2013) New Target S. Marzari To PSI

Isolde LS 1 Planning 2012 Q 1 Q 2 Q 3 2013 Q 4

Isolde LS 1 Planning 2012 Q 1 Q 2 Q 3 2013 Q 4 Q 1 Q 2 2014 Q 3 Q 4 Q 1 Q 2 Q 3 Q 4 Robots Hot Cell Medicis Target area Target storage? PAD/MAD? ISOLTRAP RFQ Cooler Miniball move HIE-ISOLDE installation ISOLDE operation Building 507? 44 Building 115 Exp. hall

Summary • Operations 2012 – A busy year ahead with a little more planned

Summary • Operations 2012 – A busy year ahead with a little more planned due to the extended operation time. – The shift backlog clearly indicates the growing demand for physics at ISOLDE • HIE-ISOLDE – Moving out of the R&D phase and into the procurement phase. – Important milestones to attain in 2012 to maintain the current schedule • ISOLDE LS 1 planning – A few tasks remain to be confirmed – A clear overlap of activities in the target area in Q 4 2013 – A potential conflict between HIE-ISOLDE installation and ISOLDE operation in April 2014.

Thank you for your attention Acknowledgements • • • GS/SE EN/MEF BE/ABP BE/OP PH/SME

Thank you for your attention Acknowledgements • • • GS/SE EN/MEF BE/ABP BE/OP PH/SME EN/HDO BE/RF EN/CV EN/EL TE/CRG EN/STI • GS/DI • TE/MSC • EN/HE : DANIEL PARCHET, ELISEO PEREZ-DUENAS : STEPHANE MARIDOR : FREDRIK WENANDER : DIDIER VOULOT, ERWIN SIESLING : MAGDA KOWALSKA, SUZANNE KREIM : YACINE KADI : MATTEO PASINI, MATTHEW FRASER : PAUL PEPINSTER, BENOIT LACARELLE : RENE NECCA : NICOLAS DELRUELLE, JOS METSELAAR : THIERRY STORA, ANA-PAULA BERNARDES, VALETINE FEDOSSEEV, BRUCE MARSH, STEFANO MARZARI : CYRILLE BEDEL : JEAN-PHILIPE TOCK, YANN LECLERCQ, LLOYD WILLIAMS, ARNAUD BOUZOUD : BRUNO FERAL, JEAN LOUIS GRENARD, KEITH KERSHAW