IPS Support Group Eighth meeting Council of Ministers 30 January 2009 12: 00 – 13: 30
Outline of the presentation • IPS progress and activities in 2008 • IPS processes and outputs for 2009
2008 IPS General overview • 2008 was the first year that the IPS Calendar was timely implemented in its entire cycle
2008 IPS General overview • 8 Strategic Planning Committees organized during the period Jan. Dec • 2008 IPS calendar finalization and approval (DSDC, MEI, Mo. F)-Jan • Macroeconomic and Fiscal Framework 2009 -2011 approval -Jan • 2008 Ministry Integrated Plans preparation and finalization, including the MTBP Annual Report of Results Jan-March • Policy Priority Note preparation (reflected in MTBP ceilings) Feb • MTBP 2009 -2011, and budget for 2009 approved by Co. M - Oct
2008 IPS General overview • NSDI 2007 -2013 approved on 12. 03. 2008 • 37 sectorial and crosscutting strategies – 24 sector and crosscutting strategies are approved with Co. M decision; – 5 are in the process of being approved; – 8 in the preparation process. • NSDI Progress Report 2006 -2007: – consulted in two roundtables: civil society and donor comunity ; (November) – sent for comments to parliamentary committees – finalized in December 2008.
IPS progress and activities in 2008 External Assistance • • • 2008 Survey on monitoring Paris Declaration – Jan-July EAOD approved, finalised and published - April 2 Go. A - Donors roundtables – May, Nov Database update and analysis of EA – July - Nov High-Level Forum in Accra participation – Sep Sector Working Groups revitalization and enhancement of Go. A leadership.
SWG meetings in 2008 SWG No. meetings Justice and Home Affaires 17 plus one Plenary Meeting Energy 0 Agriculture and Rural Development 2 Transport 0 Environment 2 Spatial Planning 0 Gender 2 Economy 0 Health 2 Public Finance and Social Insurance 0 Decentralization and Regional Development 1 Social protection and inclusion 0 Water 1 Employment 0 VET 1 Education 0 Anticorruption 0 Statistics 0 Tourism, Youth and Culture 0 Election and Civil Registry 0
SWG meetings for 2008 Problems and difficulties encountered • Some SWG have not met during the year • Donors and LM not totally involved in the process (feedbacks, minutes, materials, analysis, project proposals, commitments) • Difficulties when 2 LM are involved • Donors request individual meetings with LMs; there are cases when DSDC is not informed • SWG performance measurement (targets, products, indicators) – should be focused on results; need to apply Paris Indicators to the sector level and use them to monitor progress in each sector
External Assistance Updating Donor Database - Problems and difficulties encountered during 2008 • Partial reporting from some donors (most data lacking the actual disbursement rates or provisions for the next year/s) • Some donors did not report and some others reported very late • Reporting format some times not compatible to the DSDC required data.
IPS processes and outputs for 2009 NSDI • 2009 Ministry Integrated Plan – 2008 Annual Report – 2009 Ministry Monitoring Plan • Policy Priorities Notes – Setting out priority policies and projects for MTBP 2010 -2012 • MTBP 2010 -2012 preparation process – Assessment of priorities: Programme Policy Review (PPR) – Assessment of priorities: Program Expenditure and Investment Planning (PEIP) – Assessment of priorities: Annual Budget • 2008 NSDI Annual Progress Report • Sector and Crosscutting Strategy Monitoring • MDGs Review
IPS processes and outputs for 2009 MEDIUM-TERM BUDGET PROGRAMME • Public Expenditure Management Calendar approved – in Dec 08 • Macroeconomic assessment and forecast – 2009 -2012 macroeconomic assessment and forecast - beginning of the year • Economic and financial updates – updates on the country’s economic and fiscal performance - quarterly • Preparation of 2010 -2012 MTBP and 2010 State Budget • New procedures on Public Investment Management fully implemented and integrated in MTPB procedures
IPS processes and outputs for 2009 European Integration • SAA implementation: – Assess implementation of the NPI-SAA – Reflect SAA implementation priorities in MTBP and budget process – Monitor the NPI-SAA Set up EU-Albania joint structures upon SAA entry into force • IPA – – Review of the MIPD Finalise IPA 2009 programming Programme IPA 2010 Decentralisation • Initiation of “acquis” translation process into Albanian – Certification of translated acts – Translation of acts reflecting the priorities of NPI-SAA – Translation standardisation
IPS processes and outputs for 2009 External Assistance • Monitoring External Assistance – Update data on Donor Projects - Feb – Produce the Annual Progress Report on EA- March – Establish new EA management procedures - Jan-Apr • Donor Coordination Activities – – – Further improve functioning of SWG - Jan-Dec SWG calendar preparation – Jan Calendar of Donor programming missions and cooperation agreements - Feb Regional Donor Coordination Conference - 2 -3 April Government-Donor Roundtables - May , Nov • Monitoring the Implementation of Paris Declaration – Harmonisation Action Plan - A joint document between Go. A-Donor to identify areas for progress toward meeting 2010 targets of Paris Declaration
IPS awareness and communication q Publications § Government-Donor Dialogue joint newsletter is qualitatively improved and giving more focus to IPS issues and activities § IPS Communication strategy in process q DSDC website under procurement q Press releases published regularly in Co. M website 1/28/2009 14
Key Challenges 2009 • Operationalise the functioning of IPS Coordination Group • Improve overall inclusion of EI agenda in IPS coordination • Improve overall monitoring framework – Considerable delays in NSDI TA for DSDC • Better reflection of External Assistance projects in the budget and treasury systems • Considerable delays in IPSIS – EAMIS establishment • Overall aim for 2009: shifting from process to quality
- Southeast asian ministers of education
- Closing prayer for class
- Building intercultural competence for ministers
- Anagram of eighth
- Psychology eighth edition david g myers
- Eighth planet from the sun
- Nearest quarter inch
- David g myers psychology 8th edition
- The fifth, sixth, seventh, and eighth amendments protect *
- 8th commandment catholic
- What is the eighth wonder
- Reverse three-quarter crown
- Eighth amendment excessive bail
- Eighth letter of the alphabet
- Eighth amendment excessive bail
- Eighth amendment excessive bail