Introduction South Halls Renovation and New Construction The
- Slides: 5
Introduction South Halls Renovation and New Construction The Pennsylvania State University Park, PA Penn State Architectural Engineering Senior Capstone Project Quaid Spearing | Construction Option Advisor: Dr. Anumba April 15, 2014
Project Overview Analysis 1: Modular Bathrooms Background Information Planning & Procurement Design Evaluation Results Analysis 2: SIPS Background Information Approach Results Analysis 4: Phase Resequencing Background Information Process Results Final Recommendation Acknowledgements Project Team • • Size: 71, 002 GSF Stories: Four plus Basement Function: Residential & Assembly Construction Dates: 05/13 – 12/13 Total Project Cost: $94. 1 M Phase Project Cost: $15. 2 M Delivery Method: Design-Build Quaid Spearing| Construction Option South Halls Renovation | Penn State University
Project Overview Analysis 1: Modular Bathrooms Background Information Planning & Procurement Design Evaluation Results Analysis 2: SIPS Background Information Approach Results Analysis 4: Phase Resequencing Background Information Process Results Final Recommendation Acknowledgements Analysis 1: Modular Bathrooms Design Evaluation Proposed New Bathroom Layout Quaid Spearing| Construction Option South Halls Renovation | Penn State University Original Bathroom Layout • Reduced number of layouts from 10 down to 6 ▫ Increase benefits of modularization by optimizing layout Potential Solution
Analysis 1: Modular Bathrooms Background Information Planning & Procurement Design Evaluation Results Analysis 2: SIPS Background Information Approach Results Analysis 4: Phase Resequencing Background Information Process Results Final Recommendation Acknowledgements Approach Analysis 2: SIPS Project Overview SIPS Methodology Crew Size Adjustments • • • Student Room SIPS 2013 June Parallel production of dorm wings 5 Day work weeks; Saturday serves as catchup day Float built into Activities 23 & 24 Quaid Spearing| Construction Option South Halls Renovation | Penn State University Area Zone 1 Zone 2 Zone 3 Zone 4 6/3 1 Zone 5 Zone 6 Zone 7 Zone 8 Zone 9 1 6/10 2 1 July 6/17 3 2 1 1 2 3 4 5 August September October November 6/24 4 3 2 1 7/1 5 4 3 2 7/8 6 5 4 3 7/15 7 6 5 4 7/22 8 7 6 5 7/29 9 8 7 6 8/5 10 9 8 7 8/12 11 10 9 8 8/19 12 11 10 9 8/26 13 12 11 10 9/2 14 13 12 11 9/9 15 14 13 12 9/16 16 15 14 13 9/23 17 16 15 14 9/30 18 17 16 15 10/7 19 18 17 16 10/14 20 19 18 17 10/21 21 20 19 18 10/28 22 21 20 19 11/4 23 22 21 20 11/11 24 23 22 21 4 3 2 1 5 4 3 2 1 6 5 4 3 2 7 6 5 4 3 8 7 6 5 4 9 8 7 6 5 10 9 8 7 6 11 10 9 8 7 12 11 10 9 8 13 12 11 10 9 14 13 12 11 10 15 14 13 12 11 16 15 14 13 12 17 16 15 14 13 18 17 16 15 14 19 18 17 16 15 20 19 18 17 16 21 20 19 18 17 22 21 20 19 18 23 22 21 20 19 24 23 22 21 20 Layout and Top Track Perim. Bedroom Framing/Insulation Ductwork MEP Coring Elec. Rough In & Tele-Data 6 7 8 9 10 Perim. Bedroom Piping Door Frames & Clg/Bulkhead Framing Sprinkler Rough In Plumbing Rough In Hang GWB 11 12 13 14 15 Finish GWB Windows Prime & Paint Lights & Final Tele-Data Install Flooring 16 17 18 19 20 FCU & Mech Trim Out Doors & Hardware Adjust Sprinkler Heads Elec/Tele/Fire Alarm Trim Out Suite/Lobby Case & Window Treat 21 22 23 24 Final Paint Carpet Final Clean & Punchlist Owner FF&E December 11/18 11/25 12/2 24 23 24 24 23 22 21 24 23 22 24 23 12/9 24 12/16 12/23 12/30
Project Overview Analysis 1: Modular Bathrooms Background Information Planning & Procurement Design Evaluation Results • No additional costs incurred Analysis 2: SIPS Background Information Approach Results Analysis 4: Phase Resequencing Background Information Process Results Final Recommendation Acknowledgements Results Analysis 2: SIPS Cost Analysis • Manhours remained the same • No perceivable cost savings due to schedule reduction Quaid Spearing| Construction Option South Halls Renovation | Penn State University Schedule Analysis Constructability • Decreased by 10 working days • Increased Collaboration • Allows owner to begin FF&E sooner • Material Delays • Timely Deliveries • Subcontractor Buy-in • Other Construction Activities • Enclosure • Bathrooms