Interferometer Sensing and Control (ISC) Cost and Schedule Breakout Presentation NSF Review of Advanced LIGO Project Richard Abbott CIT April 5, 2006 LIGO-G 060210 -B-M
ISC Description & Deliverables l At a Total Cost of $8. 04 M, the ISC system provides the hardware and software for: » Sensing and controlling interferometer length – – – – – Radio Frequency (RF) detectors 4. 1 ($272 k) RF Readout Chain 4. 2 ($184 k) RF Signal Source 4. 3. 4 ($162 k) ISC Signal Conditioning Electronics 4. 3. 2 ($335 k) Real-time Processing & Networking 4. 3. 1 ($479 k) ISC Analog-to-digital Converters (ADCs) 4. 3. 3 ($661 k) Real-time Software 4. 4 ($433 k) Diagnostic and Supervisory Software 4. 5 ($319 k) Seismic Platform Interferometer 4. 9 ($580 k) » Optical Alignment systems – Alignment Sensing & Control (ASC) detectors ($515 k) – ASC RF Demodulation 4. 3. 5 ($200 k) – Video Monitoring System 4. 6. 2 ($403 k) April 5, 2006 LIGO-G 060210 -B-M 2
ISC Description & Deliverables (cont. ) » Readout signals used to search for gravity waves – DC Readout detectors ($144 k) – ISC Sensing Tables 4. 6. 3 ($1. 336 M) – Output Mode Cleaner 4. 7. 1 ($306 k) » Reconfiguring parts of the vacuum envelope ($743 k) – Vacuum Detection Infrastructure 4. 8 ($743 k) » Fabrication Testing and Validation 4. 7 ($497 k) » ISC Management 1 ($472 k) l In Process Spares included in deliverable costing April 5, 2006 LIGO-G 060210 -B-M 3
ISC Work Breakdown Structure (WBS Dictionary Available at http: //www. ligo. caltech. edu/~advligo/isc_current_wbs. pdf) April 5, 2006 LIGO-G 060210 -B-M 4
ISC Cost by WBS April 5, 2006 LIGO-G 060210 -B-M 5
ISC Schedule Highlights April 5, 2006 LIGO-G 060210 -B-M 6
ISC Staffing Profile April 5, 2006 LIGO-G 060210 -B-M 7
ISC Major Milestones April 5, 2006 LIGO-G 060210 -B-M 8
Subsystem Cost Estimating Basis l Cost estimating reliant on extrapolation from initial LIGO experiences due to custom nature of electronics » Wherever possible, representative quotes taken from industry – – PCB manufacturing facilities (PCB Express) Circuit board stuffing (Screaming Circuits) Huntington Vacuum etc. for standard vacuum parts Accuglass Vacuum connections l Estimates for LIGO designed electronics based on repackaging of existing designs wherever applicable l Travel » Estimated based on LIGO 1 experience and extrapolated to Advanced LIGO complexity April 5, 2006 LIGO-G 060210 -B-M 9
ISC Risks and Concerns l Staffing availability » Schedule assumes personnel familiar with LIGO designs » Possible mitigation in improved standards for documentation and written processes » Training of personnel to expand their roles » Use of outside testing facilities l Quality Control » Historically, this is a point of weakness » Efforts to mitigate include – Better test procedures – Use of unbiased outside testing facilities – Better peer review process April 5, 2006 LIGO-G 060210 -B-M 10
Safety Practices l Laser Safety » Laser safety practices will be in accordance with standing approved LIGO laser safety practices l Electrical Safety » Systems with hazardous electrical voltages such as photodiode bias supplies will be designed and used in accordance with approved LIGO electrical standards and procedures April 5, 2006 LIGO-G 060210 -B-M 11