Integration and Integration Facility Schedule and Manpower Update

  • Slides: 9
Download presentation
Integration and Integration Facility Schedule and Manpower Update William Miller University of Minnesota August

Integration and Integration Facility Schedule and Manpower Update William Miller University of Minnesota August 8 th, 2018

Schedule Adjustments-Pre BO We have not talked about the potential schedule the Integration and

Schedule Adjustments-Pre BO We have not talked about the potential schedule the Integration and Testing facility since the collaboration meeting but we have made some basic time scales of how long it takes to be ready. • ITF BO-July 2020: Installation of infrastructure & equipment – 9 mon. • ITF Startup-April 2021: Begin start-up of ITF equipment – 6 mon. • ITF Operations-October 2021: Begin Operations 15 mon. before Cavern BO • CUC startup-December 2021: Begin shipping underground 2 May 14, 2018

Status of ITF Building Requirements Has there been any progress on building layout and

Status of ITF Building Requirements Has there been any progress on building layout and ITF requirements. An installation schedule to facility infrastructure and equipment, is 9 months enough? We should discuss this at a working group meeting again since we stated that we needed to complete these requirements by ~Oct 2018. • Building layout • APA integration clean room size • Cold Box design and requirements, installation time needed • Storage area • Equipment requirements • Other work areas Need to compete a detailed requirements document A draft has been started 3 May 14, 2018

Draft Layout ITF 4 May 14, 2018

Draft Layout ITF 4 May 14, 2018

Estimated ITF Timeline Milestone Dates: • Final Requirements for ITF • Final Design of

Estimated ITF Timeline Milestone Dates: • Final Requirements for ITF • Final Design of ITF • Beneficial Occupancy of ITF • Complete ITF Infrastructure • ITF Startup • ITF Operations 5 May 14, 2018 October 2018 June 2019 July 2020 April 2021 April-September 2021 October 2021 - ~2025

Manpower estimates Status • I have almost completed the merge of my original top

Manpower estimates Status • I have almost completed the merge of my original top down estimate with Jim’s bottom’s up and I have included manpower estimates from APA, CE and PE consortium. • I have made estimates of the ramp up for the commissioning/infrastructure phase of the ITF of the consortium but nothing for the design phase. 6 May 14, 2018

Manpower for ITF: Pre-Operations 7 May 14, 2018

Manpower for ITF: Pre-Operations 7 May 14, 2018

Manpower summary 8 May 14, 2018

Manpower summary 8 May 14, 2018

Total FTEs at the ITF 60 Total FTE ITF 50 40 30 Some of

Total FTEs at the ITF 60 Total FTE ITF 50 40 30 Some of the trained IT Facility staff will help during commissioning then move underground 20 10 0 1 2 3 4 5 6 7 8 910111213141516171819202122232425262728293031323334353637383940414243444546474849505152535455565758596061626364656667686970717273747576 Total IT Facility Crew 9 May 14, 2018 Total IT Facility Consortia Total IT Facility