Integrated Watershed Management Programme [IWMP] State Level Nodal Agency [S L N A] Meeting

Integrated Watershed Management Programme [IWMP] State Level Nodal Agency [S L N A] Meeting 23. 08. 2013 South Conference Hall, Secretariat Thiruvananthapuram at 2. 30 pm KV. Mohankumar, IAS CRD & CEO, SLNA Kerala

Agenda Item No. 1: Approval of the minutes of SLNA meeting held on 13/02/2013

Agenda Item No. 1: Approval of the minutes of SLNA meeting held on 13/02/2013 Copies of the minutes of the SLNA meeting held on 13 -02 -2013 have been forwarded to all members. No comments have been received. The minutes of the meeting is given in Annexure I. The same may be approved.

Agenda Item No. 2 ACTION TAKEN REPORT OF THE SLNA MEETIMG HELD ON 13/08/2013

Agenda Item No. 2 ACTION TAKEN REPORT OF THE SLNA MEETIMG HELD ON 13/08/2013 Res. No. 1: Posting of Midterm Evaluators Action taken: expression of interest invited from various institutions under Kerala Agricultural University & from National organisations viz; NBSS&LUP Banglore & CSWRTI, Ootty for empanelling as midterm evaluators. List of institutions from whom interest was received (7 institutions) initially was forwarded to Do. LR for empanelling as midterm evaluators Do. LR had approved the list. Regarding institutions under KAU we are discussing in this meeting as agenda item no-07

Res. No. 2: Hill area status of districts in Kerala Action taken: All districts

Res. No. 2: Hill area status of districts in Kerala Action taken: All districts in Kerala except Idukki and Wayanad are considered as Plain with a unit cost of Rs 12, 000/ha. we have already forwarded the list of districts/ taluks/ panchayats falling under Western Ghat region as approved by Planning Commission of India as documents for hill area status of districts in Kerala. The reply from Go. I is awaited.

Res. No. 3: Enhancing Financial achievement Action taken: The financial achievement is enhanced from

Res. No. 3: Enhancing Financial achievement Action taken: The financial achievement is enhanced from 2. 32 crores to 12. 7 crores (7. 86% to 43. 01%) Due to heavy monsoon there is slight delay in implementation of EPA activities A further increase of 80% is expected in 2 months

Res. No. 4: Approval of PPRs for Batch IV(2012 -13) Action taken: The PPR

Res. No. 4: Approval of PPRs for Batch IV(2012 -13) Action taken: The PPR for projects of Batch IV for an area of 73765 ha spread over 12 districts consisting of 93 micro watersheds was presented before the 31 ststeering committee meeting held on 22 -02 -2013 and got cleared. The projects cleared is as follows

Sr. District No Project Name Weigtage No. of Project Cost MWS Area per Ha*

Sr. District No Project Name Weigtage No. of Project Cost MWS Area per Ha* Project Central Cost Share (90%) State Share (10%) Name of PIA [Block Panchayath) 1 Trivandrum IWMP-III/2012 -13 59 5 7616 12000 9. 139 8. 225 0. 914 2 Kollam IWMP-III/2012 -13 59 2 2212 15000 3. 318 2. 986 0. 332 Vettikavala 3 Alapuzha IWMP-III/2012 -13 62 8 5421 12000 6. 505 5. 855 0. 651 Bharanikavu 4 Kottayam IWMP-III/2012 -13 65 8 5100 12000 6. 120 5. 508 0. 612 Pallom 5 Idukki IWMP-VII/2012 -13 78. 5 6 4465 15000 6. 698 6. 028 0. 670 Kattapana 6 Idukki IWMP-VIII/2012 -13 73. 5 5 4964 15000 7. 446 6. 701 0. 745 Azhutha 7 Idukki IWMP-IX/2012 -13 71. 0 4 5737 15000 8. 606 7. 745 0. 861 Thodupuzha 8 Ernakulam IWMP-III/2012 -13 65 8 5162 12000 6. 194 5. 575 0. 619 Parakadavu 9 Thrissur IWMP-IV/2012 -13 57 6 5998 15000 8. 997 8. 097 0. 900 Vellangalloor 10 Palakkad IWMP-VI/2012 -13 61 6 6165 15000 9. 248 8. 323 0. 925 Chittoor 11 Malappuram IWMP-V/2012 -13 66 3 1979 15000 2. 969 2. 672 0. 297 Wandoor 12 Malappuram IWMP-VI/2012 -13 66 9 5470 12000 6. 564 5. 908 0. 656 Vengara 13 Kozhikkode IWMP-III/2012 -13 53 7 5162 15000 7. 743 6. 969 14 Kannur IWMP-IV/2012 -13 66 13 5263 15000 7. 895 7. 105 0. 774 Kunnamangala m 0. 789 Iritty 15 Kasaragod IWMP-VI/2012 -13 70 4 3051 12000 3. 661 3. 295 0. 366 Kasaragod TOTAL 93 73765 101. 102 90. 991 10. 110 Pothencode

Res. No. 5: Approval of DPR Action taken In the last SLNA meeting 14

Res. No. 5: Approval of DPR Action taken In the last SLNA meeting 14 DPRs were approved. Chairman set a time line for submission of the remaining DPRs of Batch II as 31 -3 -2013 and Batch III as 30 -06 -2013. 11 DPRs of Batch II were submitted and scrutinized by Technical Scrutinizing Committee and returned for modification/correction. The Time line fixed for submission of DPR of Batch III projects by Do. LR is 31 -10 -2013. Hence we have given the time line for submission of DPR of Batch III projects as 31 -10 -2013.

Res. No. 6: Operational clarity for Batch III projects in Idukki District Action taken

Res. No. 6: Operational clarity for Batch III projects in Idukki District Action taken üThe PIAs of 5 projects of Idukki district under Batch III was SS &SC department üFor all the other projects in Kerala, Block Panchayaths are the PIAs. üBased on the demand of MLAs and MPs of Idukki district to change PIAs of projects of Idukki district as Block Panchayts, government had directed SLNA to submit remarks on the issue. üAccordingly the remarks were submitted üGovt. vide letter No. 3278/DD 1/2013/LSGD dated 26 -04 -2013 requested Do. LR to make necessary modification in the sanction order making Block panchayaths as PIA for the 5 projects in Idukki district. üThe reply is awaited.

Res. No. 7: Revision of SPSP Action taken: • There were some errors In

Res. No. 7: Revision of SPSP Action taken: • There were some errors In the SPSP prepared for IWMP in Kerala • Exclusion of potential areas like municipal areas, inclusion of already treated areas, under weightage for clusters etc. • Go. I had given direction to revise the SPSP. • In the last SLNA meeting it has been decided to revise the SPSP and entrust the responsibility with either KSLUB or SS&SC department. • The task was entrusted to KSLUB. They have agreed to undertake the work and have placed a proposal for an amount of Rs 3, 56, 400/ • This is included as Agenda item no 6

Res. No. 8: Approval of District wise breakup of the area to be treated

Res. No. 8: Approval of District wise breakup of the area to be treated for 2013 -14 Action taken PPR for the projects of 2013 -14 was prepared and included in the Agenda item no 4

Res. No. 9: Empanelling Mid Term Evaluators Action taken Already covered under resolution No.

Res. No. 9: Empanelling Mid Term Evaluators Action taken Already covered under resolution No. 10

Res. No. 10: Approval of Technical Support Organisations Action taken SLNA had already empanelled

Res. No. 10: Approval of Technical Support Organisations Action taken SLNA had already empanelled 20 TSOs for giving support to PIAs for preparation of DPR. This is quite insufficient for meeting the demands. Hence it has been decided to empanel more TSOs. The search committee had conducted the evaluation for empanelling more NGOs as TSO on 14 -08 -2013. The action is in progress.

Res. No. 11: Inter –Intra transfer of Funds Action taken: Do. LR had issued

Res. No. 11: Inter –Intra transfer of Funds Action taken: Do. LR had issued orders (Z-11011/20/2009 -PPC dated june 2012) For inter and intra transfer of funds From one project to another or from one batch to another for effective utilisation of funds already released for ongoing IWMP projects. As per the SLNA decision, Rs. 7. 75 crores was withdrawn from Batch I&III projects and re allotted to 20 projects of Batch III (phase II) & batch IV

Res. No. 12: NWDPRA XI Plan proposal for Rs 4. 71 crores under RKVY-

Res. No. 12: NWDPRA XI Plan proposal for Rs 4. 71 crores under RKVY- ratification in SLNA Action taken SLNA ratified, no further action

Res. No. 13: Extension of Pre- IWMP projects Action taken: • There are 28

Res. No. 13: Extension of Pre- IWMP projects Action taken: • There are 28 Pre- IWMP projects sanctioned by Do. LR for our state. • Do. LR had directed to close the pre-IWMP projects by 31 -122012. • The PIAs had requested to extend the time limit for closure at least by 6 months in order to complete the implementation. • We have requested Go. I for extension of projects. • But Go. I had given extension for only one project viz; Chadayamangalam, [III installment received during March 2013 only] • Do. LR has directed to send the closure proposal for all the other projects. • Details furnished in annexure XI.

Agenda Item No. 03: Review of Progress Report

Agenda Item No. 03: Review of Progress Report

Batch - I (2009 -10) IWMP - Physical Progress Report Area 1 Kasargode-IWMP-I 5411

Batch - I (2009 -10) IWMP - Physical Progress Report Area 1 Kasargode-IWMP-I 5411 Parappa 11 112 8 2 Kasargode-IWMP-II 4971 Parappa 13 22 7 3 Kasargode-IWMP-III 6356 Parappa 11 10 9 4 Palakkad-IWMP-I 5911 Thrithala 6 36 12 5 Palakkad-IWMP-II 6428 Alathur 7 52 6 6 Palakkad-IWMP-III 5221 Thrithala 7 165 8 7 Wayanad-IWMP-I 4403 Kalpetta 10 141 10 8 Wayanad-IWMP-II 3663 Kalpetta 7 234 11 9 Wayanad-IWMP-III 4598 Sulthan Bathery 7 211 11 10 Wayanad-IWMP-IV 5175 Kalpetta 4 235 12 Total 52137 83 1218 94 Entrusted CPCRI, Kasargode for Evaluation of prepratory phase can be done Name of Project No of Status of Name of No of EPA Status No of MWs SHGs Evaluati PIA Completed of DPR Formed on Approved by SLNA Sl No

Batch - II (2010 -11) IWMP - Physical Progress Report Sl No Name of

Batch - II (2010 -11) IWMP - Physical Progress Report Sl No Name of Project Area Name of PIA No of Micro Watersheds No of SHGs Formed No of EPA Completed Status of DPR 1 Champakulam C 5889 Champakulam 3 323 8 Approved by SLNA 2 Vyppin A 1 5897 Vypin 6 221 6 3 Elamdesam A 6 - 6708 Elamdesam 7 57 3 Approved by SLNA Not Submitted 4 Payyannur C 1 5369 Payyannur 15 172 57 Submitted 5 Neeleswar A 10 5133 Parappa 14 22 2 Not Submitted 6 Ithikkara A 4 4917 Ithikkara 7 242 12 Approved by SLNA 7 Erattupetta 1 5365 Erattpuetta 7 245 55 Submitted 8 Thuneri A 28 5712 Thuneri 11 185 35 Submitted 9 Wandoor B 1 4203 Areekode 8 225 25 Submitted 10 Areekode A 1 5263 Areekode 10 296 32 Submitted 11 Pattambi E 1 5245 Pattambi 3 178 8 Submitted 12 Pattambi E 2 4385 Pattambi 5 120 12 Submitted 13 Ranni B 6784 Ranni 5 174 8 14 Vamanapuram A 7492 Vamanapuram 6 405 14 15 Kodakkara A 1 5434 Kodakkara 7 224 12 Submitted Approved by SLNA Submitted 16 Wadakkanchery B 5 5927 Wadakkanchery 10 351 10 Submitted 124 3440 299 Total 89723 Status of Evaluation Entrusted CPCRI, Kayamkulam for Evaluation of prepratory phase can be done Entrusted CPCRI, Kasargode for Evaluation Entrusted CPCRI, Kayamkulam for Evaluation of prepratory phase can be done

Batch - III- Phase - I (2011 -12) IWMP - Physical Progress Report Name

Batch - III- Phase - I (2011 -12) IWMP - Physical Progress Report Name of PIA 5563 4631 5734 5897 5118 PIA not finalised 5 4 9 6 2 IWMP V/2011 -12 Karadukka 5700 Karadukka 15 8 7 IWMP II/2011 -12 Irikkur 5054 Irikkur 11 15 8 IWMP III/2011 -12 Iritty 4935 Iritty 11 83 9 IWMP II/2011 -12 Uzhavoor 5820 Uzhavoor 7 24 10 IWMP III/2011 -12 Areekode 4126 Areekode 8 21 11 IWMP IV/2011 -12 Kuttippuram 5582 Kuttippuram 8 15 12 IWMP II/2011 -12 Pathanapuram 6174 Pathanapuram 8 18 13 IWMP II/2011 -12 Mulanthuruthy 4359 Mulanthuruthy 8 11 14 IWMP II Chirayinkeezhu 6803 Chirayinkeezhu 8 31 15 IWMP II Chengannur Total 6819 82315 Chengannur 8 118 283 509 Sl No Name of Project Area 1 2 3 4 5 IWMP II/2011 -12 IWMP IV/2011 -12 IWMP VI/2011 -12 6 Status of DPR Due date for submission of DPR is 31 -10 -2013 No of SHGs Formed No of Micro Watersheds

Batch - IV (2012 -13) IWMP - Physical Progress Report No of Watershed Sl

Batch - IV (2012 -13) IWMP - Physical Progress Report No of Watershed Sl No Name of Project Area Name of PIA Micro Committee Watersheds Formed 1 IWMP II/2011 -12 Pulikeezhu 4838 Pulikeezhu 5 3 2 IWMP V/2011 -12 Chowannur 4887 Chowannur 8 3 IWMPII/2011 -12 Nenmara 4439 Nenmara 3 4 IWMP III/2011 -12 Balussery 5120 Balussery 7 7 5 IWMP V/2011 -12 Kalpatta 3347 Kalpatta 10 6 IWMP III/2012 -13 Pothenkode 7616 Pothenkode 5 7 IWMP III/2012 -13 Vettikavala 2212 Vettikavala 2 8 IWMP III/2012 -13 Bharanikkavu 5421 Bharanikkavu 8 9 IWMP III/2012 -13 Pallom 5100 Pallom 8 10 IWMP VII/2012 -13 Kattapana 4465 Kattapana 6 11 IWMP VIII 2012 -13 Azhutha 4964 Azhutha 5 12 IWMP IX/2012 -13 Thodupuzha 5737 Thodupuzha 4 13 IWMP III/2012 -13 Parakkadavu 5162 Parakkadavu 8 14 IWMP IV/2012 -13 Vellangallur 5998 Vellangallur 6 15 IWMP VI/201 -13 Chittur 6165 Chittur 6 16 IWMP V/2012 -13 Wandoor 1979 Wandoor 3 17 IWMP VI/2012 -13 Vengara 5470 Vengara 9 18 IWMP III/2012 -13 Kunnamangalam 5162 Kunnamangalam 7 19 IWMP IV/2012 -13 Iritty 5263 Iritty 13 20 IWMP VI/2012 -13 Kasargod 3051 Kasargod 4 Total 96396 127 10 No of SHGs Formed 23 465 488

Abstract of Programme Fund Position (Rs. In Lakhs) Central State Share Received Total Amount

Abstract of Programme Fund Position (Rs. In Lakhs) Central State Share Received Total Amount received Expenditure % of Expenditure Sl No Year 1 2009 -10 1407. 70 156. 41 1564. 11 623. 00 39. 80 2 2010 -11 679. 12 75. 45 754. 60 529. 70 70. 19 3 2011 -12 577. 04 57. 70 634. 74 118. 84 18. 72 4 2012 -13 0. 00 2663. 86 289. 56 2953. 45 1271. 54 43. 05 Total

Financial Performance of Batch - 1 (2009 -10) Projects in IWMP Sl No Name

Financial Performance of Batch - 1 (2009 -10) Projects in IWMP Sl No Name of Project Total Central Cost Area Name of PIA share (Rs. In (90%) Lakhs) Kasargode-IWMP 5411 -I Kasargode-IWMP 2 4971 -II Kasargode-IWMP 3 6356 -III 1 Parappa 811. 65 730. 49 81. 17 146. 10 16. 23 162. 33 37. 79 23. 28 Parappa 745. 65 671. 09 74. 57 134. 22 14. 91 149. 13 28. 88 19. 37 Parappa 953. 40 858. 06 95. 34 171. 61 19. 07 190. 68 38. 03 19. 94 Thrithala 886. 65 797. 99 88. 67 159. 60 17. 73 177. 33 130. 44 73. 56 6428 Alathur 964. 20 867. 78 96. 42 173. 56 19. 28 192. 84 85. 95 44. 57 5221 Thrithala 783. 15 704. 84 78. 32 140. 97 15. 66 156. 63 70. 72 45. 15 4403 Kalpetta 660. 45 594. 41 66. 05 118. 88 13. 21 132. 09 55. 74 42. 20 3663 Kalpetta 549. 45 494. 51 54. 95 98. 90 10. 99 109. 89 61. 79 56. 23 5175 Kalpetta 776. 25 698. 63 77. 63 139. 73 15. 53 155. 25 66. 37 42. 75 4598 Sulthan Bathery 689. 70 620. 73 68. 97 124. 15 13. 79 137. 94 47. 54 34. 46 7820. 55 7038. 50 782. 06 1407. 70 156. 41 1564. 11 623. 25 39. 85 4 Palakkad-IWMP-I 5911 Palakkad-IWMPII Palakkad-IWMP 6 III Wayanad-IWMP 7 I Wayanad-IWMP 8 II Wayanad-IWMP 9 IV Wayanad-IWMP 10 III 5 Total Central State Total Expenditu % of Share Amount re Expenditure Received (10%) Release (20 %) 52137

Financial Performance of Batch - II (2010 -11)Projects in IWMP Sl No Name of

Financial Performance of Batch - II (2010 -11)Projects in IWMP Sl No Name of Project Area 2 3 4 Champakulam C Vyppin A 1 Elamdesam A 6 Payyannur C 1 5 Neeleswar A 10 5133 6 7 8 9 10 11 12 13 4917 5365 5712 4203 5263 5245 4385 6784 1 Ithikkara A 4 Erattupetta 1 Thuneri A 28 Wandoor B 1 Areekode A 1 Pattambi E 2 Ranni B Vamanapuram 14 A 15 Kodakkara A 1 Wadakkancher 16 y B 5 Total 5889 5897 6708 5369 7492 5434 5927 89723 Total Cost Central Name of (Rs. In share PIA Lakhs) (90%) Champakul am Vypin Elamdesam Payyannur Neeleswara m Ithikkara Erattpietta Thuneri Areekode Pattambi Ranni Vamanapur am Kodakkara Wadakkanc hery Central State Share Receive (10%) Received d (6%) % of Total Expendit Release ure 706. 68 636. 01 70. 67 38. 16 4. 24 42. 40 36. 92 87. 07 884. 55 1006. 20 805. 35 796. 10 905. 58 724. 82 88. 46 100. 62 80. 54 47. 77 54. 33 43. 49 5. 31 6. 04 4. 83 53. 07 60. 37 48. 32 42. 59 3. 36 30. 87 80. 25 5. 57 63. 89 769. 95 692. 96 77. 00 41. 58 4. 62 46. 20 20. 62 44. 63 737. 55 643. 80 856. 80 630. 45 789. 45 786. 75 657. 75 814. 08 663. 80 579. 42 771. 12 567. 41 710. 51 708. 08 591. 98 732. 67 73. 76 64. 38 85. 68 63. 05 78. 95 78. 68 65. 78 81. 41 39. 83 34. 77 46. 27 34. 04 42. 63 42. 48 35. 52 43. 96 4. 43 3. 86 5. 14 3. 78 4. 74 4. 72 3. 95 4. 88 44. 25 38. 63 51. 41 37. 83 47. 37 47. 21 39. 47 48. 84 35. 04 28. 37 34. 84 31. 96 34. 3 34. 66 29 36. 7 79. 18 73. 44 67. 77 84. 49 72. 41 73. 42 73. 48 75. 14 1123. 80 1011. 42 112. 38 60. 69 6. 74 67. 43 56. 81 84. 25 652. 08 586. 87 65. 21 3. 91 39. 12 35. 71 91. 27 711. 24 640. 12 71. 12 38. 41 4. 27 42. 67 37. 9 88. 81 12576. 48 11318. 83 1257. 65 679. 13 75. 46 754. 59 529. 65 70. 19

Financial Performance of Batch - III (2011 -12)- PHASE - I Projects in IWMP

Financial Performance of Batch - III (2011 -12)- PHASE - I Projects in IWMP State Share (10%) Central State Share Received (6%) % of Total Expendit Remar Expen Release ure ks diture Name of Project Area 1 IWMP II/2011 -12 5563 834. 45 751. 005 83. 445 45. 06 5. 01 50. 07 0 0. 0 2 IWMP III/2011 -12 4631 694. 65 625. 185 69. 465 37. 51 4. 17 41. 68 0 0. 0 3 IWMP IV/2011 -12 5734 860. 1 774. 09 86. 01 46. 44 5. 16 51. 60 0 0. 0 4 IWMP V/2011 -12 5897 884. 55 796. 095 88. 455 47. 77 5. 31 53. 08 0 0. 0 5 IWMP VI/2011 -12 5118 767. 7 690. 93 76. 77 41. 46 4. 61 46. 07 0 0. 0 6 IWMP V/2011 -12 Karadukka 5700 Karadukka 684 615. 6 68. 4 36. 94 4. 10 41. 04 1. 17 2. 9 7 IWMP II/2011 -12 Irikkur 5054 Irikkur 606. 48 545. 832 60. 648 32. 75 3. 64 36. 39 11. 2 30. 8 8 IWMP III/2011 -12 Iritty 4935 Iritty 592. 2 532. 98 59. 22 31. 98 3. 55 35. 53 8. 27 23. 3 698. 4 628. 56 69. 84 37. 71 4. 19 41. 90 16. 4 39. 1 4126 Areekode 495. 12 445. 608 49. 512 26. 74 2. 97 29. 71 11. 23 37. 8 669. 84 602. 856 66. 984 36. 17 0. 74 36. 91 20. 89 56. 6 740. 88 666. 792 74. 088 40 4. 45 44. 45 20. 23 45. 5 523. 08 470. 772 52. 308 28. 25 0. 00 28. 25 13. 71 48. 5 816. 36 734. 724 81. 636 44. 08 4. 90 48. 98 6. 97 14. 2 818. 28 736. 452 81. 828 44. 19 4. 91 49. 10 8. 77 17. 9 577. 05 57. 70 634. 75 118. 84 18. 7 10 11 12 13 IWMP II/2011 -12 Uzhavoor IWMP III/2011 -12 Areekode IWMP IV/2011 -12 Kuttippuram IWMP II/2011 -12 Pathanapuram IWMP II/2011 -12 Mulanthuruthy PIA not finalised 5820 Uzhavoor 5582 6174 4359 14 IWMP II Chirayinkeezhu 6803 15 IWMP II Chengannur 6819 Total 82315 Kuttippura m Pathanapur am Mulanthur uthy Chirayinke ezhu Chengannu r 10686. 0 9617. 481 1068. 609 9 Expenditure incurred was for DPR preparation and Capacity Building activities. Central share (90%) Sl No 9 Name of PIA Total Cost (Rs. In Lakhs)

Financial Performance of Batch III (2011 -12) Phase II Projects in IWMP Name of

Financial Performance of Batch III (2011 -12) Phase II Projects in IWMP Name of Project Area Block Total Cost Central Share (90%) State Share (10 %) 1 st Instal ment received (6%) State Share Recei ved Total Released Expen diture IWMP II/2011 -12 4838 Pulikeezhu 580. 56 522. 504 58. 056 0 0 34. 80 0 2 IWMP V/2011 -12 4887 Chowannur 586. 44 527. 796 58. 644 0 0 35. 20 0 3 IWMP II/2011 -12 4439 Nenmara 532. 68 479. 412 53. 268 0 0 32. 00 0 4 IWMP III/2011 -12 5120 Balussery 614. 4 552. 96 61. 44 0 0 36. 90 0 5 IWMP V/2011 -12 3347 Kalpetta 502. 05 451. 845 50. 205 0 0 30. 10 0 2816. 13 2534. 52 281. 61 0 0 169. 00 0 TOTAL Remark s Fund Released to through Inter Intra Transfer from unspent balance in WCDC Idukki Sl. No

Fund Release to Batch - III & IV through Inter Intra Transfer Central State

Fund Release to Batch - III & IV through Inter Intra Transfer Central State Total Expe Share Amount nditu Received (10%) Received Release re (6%) Sl No Name of Project 1 IWMP III/2012 -13 Pothenkode 7616 Pothenkode 913. 9 822. 51 91. 39 0 0 54. 8 0 2 IWMP III/2012 -13 Vettikaval 2212 Vettikaval 331. 8 298. 62 33. 18 0 0 19. 9 0 650. 5 585. 45 65. 05 0 0 39 0 3 IWMP III/2012 -13 Bharanikkavu 5421 Bharanikkavu 4 IWMP III/2012 -13 Pallom 5100 Pallom 612 550. 8 61. 2 0 0 36. 7 0 5 IWMP VII/2012 -13 Kattapana 4465 Kattapana 669. 8 602. 82 66. 98 0 0 40. 2 0 6 IWMP VIII 2012 -13 Azhutha 4964 Azhutha 744. 6 670. 14 74. 46 0 0 44. 7 0 7 IWMP IX/2012 -13 Thodupuzha 5737 Thodupuzha 860. 6 774. 54 86. 06 0 0 51. 6 0 8 IWMP III/2012 -13 Parakadavu 5162 Parakadavu 619. 4 557. 46 61. 94 0 0 37. 2 0 9 IWMP IV/2012 -13 Vellangallur 5998 Vellangallur 899. 7 809. 73 89. 97 0 0 54 0 10 IWMP VI/2012 -13 Chittur 6165 Chittur 924. 8 832. 32 92. 48 0 0 55. 5 0 11 IWMP V/2012 -13 Wandoor 1979 Wandoor 296. 9 267. 21 29. 69 0 0 17. 8 0 12 IWMP VI/2012 -13 VENGARA 5470 Vengara 656. 4 590. 76 65. 64 0 0 39. 4 0 Kunnamangala 774. 3 m 696. 87 77. 43 0 0 46. 5 0 13 15 14 IWMP III/2012 -13 Kunnamangalam IWMP IV/2012 -13 Iritty IWMP VI/2012 -13 Kasargod Total 5162 5263 Iritty 789. 5 710. 55 78. 95 0 0 47. 4 0 3051 Kasargod 366. 1 329. 49 36. 61 0 0 22 0 0 0 606. 7 0 73765 10110. 3 9099. 27 1011. 03 Remarks Fund released through inter intra transfer method form unspent balance in WCDC Palakkad, Wyanad, Kasargode Total Central Cost Area Name of PIA share (Rs. In (90%) Lakhs)

Institutional Fund Released by Do. LR (Rs. In Lakhs) For SLNA For WCDCs Total

Institutional Fund Released by Do. LR (Rs. In Lakhs) For SLNA For WCDCs Total Central assistance released so far during 2009 -10 to 2012 -13 52. 92 23. 28 76. 2 Other miscellaneous (incl. Interest accrued) if any 40. 65 0 40. 65 Total funds available 93. 57 23. 28 116. 85 Total expenditure 52. 85 19. 07 71. 92 % of Expenditure 56. 48 81. 92 61. 55 Balance funds available 40. 72 4. 21 44. 93 Remarks Audit of In stitutional Grant for the period from 2009 -10 to 2012 -13 have been completed and audit statement forwarded to Do. LR. Proposal for releasing institutional grant has also been sent to Do. LR Particular

Agenda Item No. 4 : Preliminary Project Reports (PPR): Sanction for Watershed Development Projects

Agenda Item No. 4 : Preliminary Project Reports (PPR): Sanction for Watershed Development Projects of Batch V for the year 2013 -14 to be submitted to Go. I for approval v. Go. I has allotted physical targets for new projects for 2013 -14. v. As per the weightage criteria of SPSP the target of the state comes to 60124 ha. v. The SLNA meeting held on 13 -02 -2013 decided to follow the weightage criteria to prepare PPR for 60124 ha v. Details furnished in the next slide

As per weightage criteria , SLNA decided to prepare PPR for 60124 ha as

As per weightage criteria , SLNA decided to prepare PPR for 60124 ha as follows. District Area allocated 1 Thiruvananthapuram 5315 ha 2 Kollam 3657 ha 3 Pathanamthitta 5541 ha 4 Alappuzha 6490 ha 5 Kottayam 6089 ha 6 Idukki 2423 ha 7 Ernakulam 4473 ha 8 Thrissur 3610 ha 9 Palakkad 5226 ha 10 Malappuram 6291 ha 11 Kannur 5256 ha 12 Kasargod. 5753 ha Total 60124 ha

 • The preparation of Preliminary Project Report has been completed. • During the

• The preparation of Preliminary Project Report has been completed. • During the course of field verification for PPR preparation, several already treated areas, water bodies, roads, buildings etc were excluded. • As per the modifications made, the following is the revised area for 2013 -14

The revised area for 2013 -14 District Area allocated 1 Thiruvananthapuram 5426 ha 2

The revised area for 2013 -14 District Area allocated 1 Thiruvananthapuram 5426 ha 2 Kollam 3898 ha 3 Pathanamthitta 5500 ha 4 Alappuzha 6305 ha 5 Kottayam 6112 ha 6 Ernakulam 4428 ha 7 Thrissur 3427 ha 8 Palakkad 5084 ha 9 Malappuram 6235 ha 10 Kannur 4667 ha 11 Kasargod. 5239 ha Total 56321 ha KSLUB may present the PPRs

Agenda Item No. 05: Approval of Detailed Project Reports (DPRs) Submitted by WCDC and

Agenda Item No. 05: Approval of Detailed Project Reports (DPRs) Submitted by WCDC and Scrutinized by Technical Experts of SLNA. • There is a budget provision of 1% of the total project cost, for DPR preparation • SLNA has received 61 watershed development projects under IWMP in 4 batches viz. 2009 -10, 2010 -112011 -12 and 2012 -13. • Year wise details of projects approved by Go. I is as follows Year Number of districts Number of projects No. of micro watersheds Area in Ha. 2009 -10 3 10 94 52137 2010 -11 13 16 127 89722 2011 -12 9 15 115 82315 2012 -13 14 20 126 96396 61 462 320572 Total

The status of DPR of the above 61 projects is as follows Batch I

The status of DPR of the above 61 projects is as follows Batch I DPR status No of projects Submitted 10 10 Approved Remarks by SLNA 10 4 11 DPRs placed for II 16 15 III 15 1 Due date 31 -10 -2013 IV 20 Nil Due date 31 -12 -2013 approval

The following DPRs of Batch II may be approved subject to further modifications if

The following DPRs of Batch II may be approved subject to further modifications if any while scrutinizing by the technical committee. The list of DPRS furnished below: Sl No 1 2 3 District Pathanamthitta Kottayam Thrissur 4 Malappuram 5 Palakkad 6 7 8 Kozhikode Kannur Kasaragod Project Ranni Erattupetta Wadakkancharry Kodakara Areekode B 1 Wandoor B 1 Pattambi E 2 Thuneri Payyannur Parappa

Agenda Item No. 06 Revision of State Perspective and Strategic Plan (SPSP) Previous SLNA

Agenda Item No. 06 Revision of State Perspective and Strategic Plan (SPSP) Previous SLNA meeting decided to revise SPSP in order to: • Avoid overlapping/ duplication of already treated area, • For inclusion of certain potential areas which were excluded in the existing SPSP. KSLUB has placed a proposal for completing the work within 3 months for an amount of Rs 3, 56, 400/- as given in the next slide The expenditure in this regard can be met either from the funds provided under ‘Innovative Projects’ kept by SIRD or from the institutional non recurring grant provided for SLNA for setting up a GIS Lab in the SLDC.

Particulars Amount Generation of Thematic maps 1, 26, 000 and Ground Truth Verification -@Rs

Particulars Amount Generation of Thematic maps 1, 26, 000 and Ground Truth Verification -@Rs 9000*14 districts GIS works 36, 000 Data Entry 45, 000 Report and Map Preparation 50, 000 POL & Hire charges 50, 000 Miscellaneous 17, 000 Institutional overhead charge 10% 32, 400 Total 3, 56, 400 SLNA may take decisions on the following points also. 1. Whether the area included in the foreclosed projects of any watershed development programmes can be taken up under IWMP 2. Whether the area treated 10 years back, in any other watershed development schemes, can be included under IWMP

Agenda Item No. 07 Evaluation of Preparatory phase of Projects SLNA held on 13

Agenda Item No. 07 Evaluation of Preparatory phase of Projects SLNA held on 13 -02 -2013, suggested that only government organisations be considered for empanelling as midterm evaluators. We have addressed to all government agencies &institutions The response is very meagre i. e. Only 7 responded. Do. LR have empanelled the seven institutions. Kerala Agricultural University agreed to undertake evaluation provided the budget provision for evaluation (1% of the project cost) should be handed over directly from SLNA to the university account We have already engaged CPCRI, Kasargod and Kayamkulam for evaluation of 7 projects Evaluation of all the remaining projects may be entrusted to Kerala Agricultural University by execution of an Mo. U for evaluation of all projects under IWMP on a comprehensive project mode. SLNA may approve the above proposal.

Agenda Item No. 8: Overlapping of watershed programmes • Certain micro watersheds within the

Agenda Item No. 8: Overlapping of watershed programmes • Certain micro watersheds within the cluster of micro watersheds selected under IWMP is selected for implementation under other watershed development schemes like RIDF, WGDP etc. • This causes difficulty in implementation as well as duplication and overlapping. • To avoid this necessary instruction may be given to concerned agencies The SLNA may take a suitable decision.

Agenda Item No. 9 : Time line for III and IV Batch A time

Agenda Item No. 9 : Time line for III and IV Batch A time line for implementation of Batch III and IV is prepared Activity Time line Batch III Batch IV Appointing of WDT 31 -08 -2013 30 -09 -2013 Completion of DPR 31 -10 -2013 31 -12 -2013 Uploading of AAP in the website 15 -11 -2013 15 -01 -2014 Uploading of DPR in the website 30 -11 -2013 31 -01 -2014 Completion of EPA 31 -12 -2013 31 -03 -2014 Evaluation of Preparatory phase 31 -01 -2014 30 -04 -2014 The time line may be approved

Agenda Item no 10 Extension of GIS support to SLNA §As per the decision

Agenda Item no 10 Extension of GIS support to SLNA §As per the decision of SLNA meeting held on 16 -6 -2012, GIS support for SLNA was given by KSLUB. §As per the Mo. U signed the support was for a period of one year and it expires on 28 -11 -2013. §Hence decision may be taken to extend the GIS support for a further period of one more year.

Agenda Item No 11 Capacity Building Plan of SLNA Capacity Building has budget provision

Agenda Item No 11 Capacity Building Plan of SLNA Capacity Building has budget provision of 5% of project cost. A capacity building plan for the IWMP projects in Kerala is prepared (Annexure V) The same may be approved.

Agenda Item No 12 Entrusting of WDT/WCDC with the task of DPR Preperation. In

Agenda Item No 12 Entrusting of WDT/WCDC with the task of DPR Preperation. In the quarterly review meeting held at the Mo. RD in New Delhi on 2/08/2013 it has been suggested that in the event of all WCDC/WDT experts are positioned in Kerala, the state can impart adequate technical training to the experts and entrust them with the task of preparation of DPR as per the instructions already issued under para 51 of Common Guidelines. A decision may be taken to entrust WDT/WCDC with the task of DPR preparation from next batch onwards. A series of trainings can be organised with the technical support of SIRD, Kottarakkara, CWRDM, Kozhikode and IWDMK, Chadayamangalam etc. -Submitting this proposal for the resolution of this committee.

Agenda Item No 13 Institutional Grant As per G. O. (MS)No. 141/2010 dated. 3/7/2010

Agenda Item No 13 Institutional Grant As per G. O. (MS)No. 141/2010 dated. 3/7/2010 and G. O. (Rt)NO. 1000/2013/LSGD dated, 16/04/2013 Government have accorded sanction for the creation of 10 posts in SLNA and 42 post in WCDCS. 8 posts in SLNA and 33 posts in WCDCs are filled up. Action is being taken to fill up the remaining posts. Annual requirement for meeting the establishment expenditure of SLNA and WCDCs comes to Rs. 243. 50 lakh. DOLR has released only an amount of Rs. 76. 20 lakh as Intuitional Grant to our State. Proposals along with Audit statement and Utilization Certificate have already been submitted to DOLR for releasing 2 nd instalment of Institutional Grant. At present no funds are available in SLNA for releasing funds to WCDCs for paying the salary of their staff. Hence as a temporary measure, the interest in Programme Fund may be re appropriated for the above purpose and the same may be recouped as and when the funds is received from DOLR. Details of annual requirement are enclosed as Annexure VI. Sanction may be accorded for re appropriating the interest of programme fund for paying salary.

Best practices & some Initiatives under IWMP in Kerala

Best practices & some Initiatives under IWMP in Kerala

Social mapping and PRA exerciese at Chirayinkeezhu watershed, Thiruvanathapuram district - IWMP-II/2011 -12

Social mapping and PRA exerciese at Chirayinkeezhu watershed, Thiruvanathapuram district - IWMP-II/2011 -12

Baseline survey- Erattupettah watershed, Kottayam district- IWMP 1/2010 -11

Baseline survey- Erattupettah watershed, Kottayam district- IWMP 1/2010 -11

Drainage survey- Erattupettah watershed, Kottayam district- IWMP 1/2010 -11

Drainage survey- Erattupettah watershed, Kottayam district- IWMP 1/2010 -11

Transect walk Champakkulam, Alappuzha. IWMP 1/2010 -11 IWMP Payyannur, Kannur- IWMP 1/2010 -11

Transect walk Champakkulam, Alappuzha. IWMP 1/2010 -11 IWMP Payyannur, Kannur- IWMP 1/2010 -11

PRA Exercise IWMP Payyannur, Kannur- IWMP 1/2010 -11

PRA Exercise IWMP Payyannur, Kannur- IWMP 1/2010 -11

Mapping exercise PRA EXERCISE - ON 15. 05. 2012 - IWMP 1/2010 -11 Champakkulam-

Mapping exercise PRA EXERCISE - ON 15. 05. 2012 - IWMP 1/2010 -11 Champakkulam- IWMP 1/2010 -11 - Alappuzha Social mapping- ON 15. 05. 2012 - IWMP 1/2010 -11 IWMP Payyannur, Kannur- IWMP 1/2010 -11

PRA activities- Alathur- IWMP-II-A 1/2009 -10

PRA activities- Alathur- IWMP-II-A 1/2009 -10

Watershed gramasabha at Kizhakkanchery. Alathur Palakkad district- IWMP-II-A 1/2009 -10

Watershed gramasabha at Kizhakkanchery. Alathur Palakkad district- IWMP-II-A 1/2009 -10

Watershed gramasabha-Vypin -IWMP 1/2010 -11 Transect walk in Vypin IWMP 1/2010 -11

Watershed gramasabha-Vypin -IWMP 1/2010 -11 Transect walk in Vypin IWMP 1/2010 -11

Entry Point Activities

Entry Point Activities

Renovation of Pond at Koyipra paddy field (Phase I) at Payyannur, kannur district: IWMP

Renovation of Pond at Koyipra paddy field (Phase I) at Payyannur, kannur district: IWMP 1/2010 -11 Koyipra paddy field pond Before During and After the work Koyipra paddy field pond had been beneficial for 200 farmers, as it was providing adequate water for cultivation. Over the years, the pond was neglected and the side walls were fallen down as a result its depth and water storage capacity were reduced and due to shortage of water, the farmers were forced to stop cultivation at Koyipra field leaving it barren for several years.

Panappuzhachal Shutter type check dam In Payyannur, Kannhur district: IWMP 1/2010 -11 Panappuzhachal shutter

Panappuzhachal Shutter type check dam In Payyannur, Kannhur district: IWMP 1/2010 -11 Panappuzhachal shutter type check dam before, during and after the work Vellariyanam stream is flowing through the panappuzhachal watershed; plays a pivotal role as a water source. Severe water scarcity is observed in the area during summer and is considered as drought prone. Around 110 families are largely depend on this stream.

Panappuzhachal Stream bank stabilization with retaining wall In Payyannur, Kannhur district: IWMP 1/2010 -11

Panappuzhachal Stream bank stabilization with retaining wall In Payyannur, Kannhur district: IWMP 1/2010 -11 Panappuzhachal Stream bank stabilization Before, During and after the work Main problem faced by the people of vellariyanam is stream bank erosion. This bank erosion deviates the flow of water, leads to desiltation and overflow of a water to the paddy field.

Paravoor river protection work In Payyannur, Kannhur district: IWMP 1/2010 -11 River protection work.

Paravoor river protection work In Payyannur, Kannhur district: IWMP 1/2010 -11 River protection work. Before, During and after the work

IWMP 1/2010 -11 Ranni B Watershed, Pathanamthitta district: Percolation Pond at Seethakuzhy Before work

IWMP 1/2010 -11 Ranni B Watershed, Pathanamthitta district: Percolation Pond at Seethakuzhy Before work After completion of work Watershed Seethathodu Grama Panchayat Seethathodu Capacity (l) 1, 11, 000 Area Benefitted (ha) 20 No of Families Benefitted 60 Total Cost (Lakhs) 4, 69, 000

IWMP 1/2010 -11 Ranni B Watershed, Pathanamthitta district: Ferrocement Rainwater Harvesting Tank Before work

IWMP 1/2010 -11 Ranni B Watershed, Pathanamthitta district: Ferrocement Rainwater Harvesting Tank Before work After completion of work Watershed Grama Panchayat Capacity (l) Area Benefitted (ha) No of Persons Benefitted Total Cost (Lakhs) Kavummoolathodu Chittar 14, 178 20 1000 1, 20, 000

IWMP 1/2010 -11 Ranni B Watershed, Pathanamthitta district: Reinforced Cement Concrete Water Harvesting Tank

IWMP 1/2010 -11 Ranni B Watershed, Pathanamthitta district: Reinforced Cement Concrete Water Harvesting Tank for Harnessing the Water from a Natural Spring Before work After completion of work Watershed Grama Panchayat Capacity (l) No of Families Benefitted Total Cost (Lakhs) Mamoodu Ranni -Perunadu 10, 440 50+Sabirimala Pilgrims 1, 47, 231

IWMP 1/2010 -11 Ranni B Watershed, Pathanamthitta district: Retaining Wall for Soil Conservation at

IWMP 1/2010 -11 Ranni B Watershed, Pathanamthitta district: Retaining Wall for Soil Conservation at Panniyar Colony Before work After completion of work Watershed Grama Panchayat Area Benefitted (ha) No of Families Benefitted Total Cost (Lakhs) Kavummoolathodu Chittar 2 40 1, 76, 200

IWMP 1/2010 -11 Ranni B Watershed, Pathanamthitta district: Stream Side Protection for Soil Conservation

IWMP 1/2010 -11 Ranni B Watershed, Pathanamthitta district: Stream Side Protection for Soil Conservation at Seethathodu Before work After completion of work Watershed Grama Panchayat Area Benefitted (ha) No of Families Benefitted Total Cost (Lakhs) Seethathodu 22. 8 80 2, 14, 500

IWMP 1/2010 -11 Ranni B Watershed, Pathanamthitta district: Stream Side Protection for Soil Conservation

IWMP 1/2010 -11 Ranni B Watershed, Pathanamthitta district: Stream Side Protection for Soil Conservation at Puthenpurayilpadi Onkkam Road side Before work After completion of work Watershed Grama Panchayat Area Benefitted (ha) No of Families Benefitted Total Cost (Lakhs) Madathumoozhy Ranni-Perunadu 29 60 2, 62, 490

EPA at Vamanapuram block of Thiruvananthapuram district. IWMP 1/2010 -11 Vegetable cultivation of Old

EPA at Vamanapuram block of Thiruvananthapuram district. IWMP 1/2010 -11 Vegetable cultivation of Old age care home at Nellanad Grama Panchayath

EPA at Vamanapuram block of Thiruvananthapuram district. IWMP 1/2010 -11 Crop demonstration at the

EPA at Vamanapuram block of Thiruvananthapuram district. IWMP 1/2010 -11 Crop demonstration at the office compound of Vamanapuram block- PIA

EPA at Vamanapuram block of Thiruvananthapuram district. IWMP 1/2010 -11 Vegetable cultivation at Pre

EPA at Vamanapuram block of Thiruvananthapuram district. IWMP 1/2010 -11 Vegetable cultivation at Pre metric hostel of Vamanapuram block- PIA

EPA at Vamanapuram block of Thiruvananthapuram district. IWMP 1/2010 -11 Installation of solar panels

EPA at Vamanapuram block of Thiruvananthapuram district. IWMP 1/2010 -11 Installation of solar panels at the Block Panchayath office- PIA- through KELTRON. The entire block office is now self sufficient in electricity from this installation. This innovation has created public interest and many house holds in the vicinity are coming forward for solar panel installation

EPA at Vamanapuram block of Thiruvananthapuram district. IWMP 1/2010 -11 Installation of rain water

EPA at Vamanapuram block of Thiruvananthapuram district. IWMP 1/2010 -11 Installation of rain water harvesting system and well re-charge at the Block Panchayath office. The water level of the well has increased significantly. This innovation has created public interest and many house holds in the vicinity are coming forward for installation of rain water harvesting systems

EPA at Vamanapuram block of Thiruvananthapuram district. IWMP 1/2010 -11 Installation of rain water

EPA at Vamanapuram block of Thiruvananthapuram district. IWMP 1/2010 -11 Installation of rain water harvesting system and well re-charge at the campus of Pirappancode high school within the Vamanapuram watershed

EPA activity at Vypin Watershed, Eranakulam district- IWMP 1/2010 -11 De-silting of Bender canal

EPA activity at Vypin Watershed, Eranakulam district- IWMP 1/2010 -11 De-silting of Bender canal Before de-silting During de-silting After de-silting

EPA activity at Vypin Watershed, Eranakulam district- IWMP 1/2010 -11 Construction of outer bund

EPA activity at Vypin Watershed, Eranakulam district- IWMP 1/2010 -11 Construction of outer bund & installation of pumping facility at Thundipuram paddy cultivating area (padasekharam) Before construction of bund During construction of bund & pump house After completion of bund

EPA of Erumapetty Grama Panchayathvadakkanchery block of Thrissur district- IWMP 2/2010 -11 Chathan Kulam

EPA of Erumapetty Grama Panchayathvadakkanchery block of Thrissur district- IWMP 2/2010 -11 Chathan Kulam Before Renovation (Side Wall Repair and Installation of Shutter) (5 th April 2013) Work Ongoing in Chathankulam (18 th April 2013) Inaugral Function after Renovation (June 7 2013)

EPAof Varavoor Grama Panchayath- vadakkanchery block of Thrissur district- IWMP 2/2010 -11 Puthankulam before

EPAof Varavoor Grama Panchayath- vadakkanchery block of Thrissur district- IWMP 2/2010 -11 Puthankulam before Renovation (20/02/2013) Puthankulam (Work in Progress) (04/03/2013) After Work Completion (26/04/2013)

Entry Point Activities at Mundathicode Grama Panchayath (Construction of VCB)vadakkanchery block of Thrissur district-

Entry Point Activities at Mundathicode Grama Panchayath (Construction of VCB)vadakkanchery block of Thrissur district- IWMP 2/2010 -11 Before Work (02/04/2013) After Work completion (25/06/2013) Work in Progress (02/05/2013)

Entry Point Activities at Mundathicode Grama Panchayath Distribution of paddy seeds - vadakkanchery block

Entry Point Activities at Mundathicode Grama Panchayath Distribution of paddy seeds - vadakkanchery block of Thrissur district. IWMP 2/2010 -11 Paddy Seeds distribution (August 2012) Before Harvesting Ready for Harvesting

Construction of water harvesting tank and rennovation of public well EPA at Vypin watershed,

Construction of water harvesting tank and rennovation of public well EPA at Vypin watershed, Eranakulam district- IWMP 1/2010 -11 Before the work After completion of work During work

EPA Well recharge - Vadakkanchery block of Thrissur district- IWMP 2/2010 -11 Work in

EPA Well recharge - Vadakkanchery block of Thrissur district- IWMP 2/2010 -11 Work in Progress (06/05/2013) Well Recharge after Completion (08/07/2013)

Protection work of existing watershed near Anchampoyk pump house in Chirakkara GP. Ithikkara, Kollam

Protection work of existing watershed near Anchampoyk pump house in Chirakkara GP. Ithikkara, Kollam district- IWMP 1/2010 -11 The work was the construction of retaining wall around a natural stream through a pipe so that the people can use the water for drinking and also for bathing purposes. Drainage is also constructed for the outflow of waste water.

Construction of side wall for Chalakkara colony thodu in ward XII of Nedumpana GP.

Construction of side wall for Chalakkara colony thodu in ward XII of Nedumpana GP. Ithikkara, Kollam district- IWMP 1/2010 -11 The work was the construction of retaining wall for chalakkara colony thodu for a distance of 25. 00 m on both sides of the thodu. In addition to the specified works in estimate, an existing slab is also protected. It is a useful work and the thodu looks clean and neat now, free from waste and silt. Also the flow of water is maintained

Construction of side wall for Kallamkodi poyka vadakkath in Chirakkara GP. Ithikkara, Kollam district-

Construction of side wall for Kallamkodi poyka vadakkath in Chirakkara GP. Ithikkara, Kollam district- IWMP 1/2010 -11 The work has been completed in all respect. The payment is also done for the above said work. The work was the construction of SIDE wall for Kallamkodi poyka for a distance of 86. 00 m on both sides of the thodu. The thodu ends at the lagoon. Now the pure water flows uninterrupted.

Construction of check dam across Odamthode Watershed in Alathur Palakkad district- IWMP-II-A 1/2009 -10

Construction of check dam across Odamthode Watershed in Alathur Palakkad district- IWMP-II-A 1/2009 -10 During work Before start of work

Alathur Palakkad district- IWMP-II-A 1/2009 -10 • Before Coconut basin Mangalamdam watershed 11 -03

Alathur Palakkad district- IWMP-II-A 1/2009 -10 • Before Coconut basin Mangalamdam watershed 11 -03 -2012 • After coconut basin in Mangalamdam watershed 15 -01 -2013

Soil and water conservation: Stone bund built at Vattapparathodu - Alathur Palakkad district- IWMP-IIA

Soil and water conservation: Stone bund built at Vattapparathodu - Alathur Palakkad district- IWMP-IIA 1/2009 -10

Palambra Thode rennovation: Kodakara in Thrissur District- IWMP 1/2010 -11

Palambra Thode rennovation: Kodakara in Thrissur District- IWMP 1/2010 -11

PRA Exercisevadakkanchery block of Thrissur district- IWMP 2/2010 -11

PRA Exercisevadakkanchery block of Thrissur district- IWMP 2/2010 -11

THUNERI block of Kozhikode district IWMP 1/2010 -11 Before and after Gully plugging

THUNERI block of Kozhikode district IWMP 1/2010 -11 Before and after Gully plugging

Training and Capacity Building

Training and Capacity Building

Capacity building activites at Chambakkulam, Alappuzha district- IWMP 1/2010 -11 For SHG members 17.

Capacity building activites at Chambakkulam, Alappuzha district- IWMP 1/2010 -11 For SHG members 17. 07. 2013 For WC- 18. 06. 2013 For user group 18. 04. 2013

CAPACITY BUILDING IN CONNECTION WITH IWMP Chirayinkeezh. Thiruvananthapuram district- IWMP-II/2011 -12 PANCHAYAT LEVEL- 20

CAPACITY BUILDING IN CONNECTION WITH IWMP Chirayinkeezh. Thiruvananthapuram district- IWMP-II/2011 -12 PANCHAYAT LEVEL- 20 -25/04/2013 SHG’s LEVEL- 7 & 8 Feb, 2013

CAPACITY BUILDING TRAINING IMPARTED TO KUDUMBASREE, SHG MEMBERS, MGNREGA WORKERS, WC MEMBERS ON 26.

CAPACITY BUILDING TRAINING IMPARTED TO KUDUMBASREE, SHG MEMBERS, MGNREGA WORKERS, WC MEMBERS ON 26. 04. 2013 – 04. 05. 2013 - VYPIN ERANAKULAM-IWMP 1/2010 -11

Capacity building programme for Thippilikkayam Cocunut basin user group formation – IWMP Alathur, Palakkad

Capacity building programme for Thippilikkayam Cocunut basin user group formation – IWMP Alathur, Palakkad district- IWMP-II-A 1/2009 -10

Capacity building for WC- – IWMP Alathur, Palakkad district- IWMP-II-A 1/2009 -10

Capacity building for WC- – IWMP Alathur, Palakkad district- IWMP-II-A 1/2009 -10

IWMP Alathur, Palakkad district- IWMP-II-A 1/2009 -10 • Capacity building for watershed committees of

IWMP Alathur, Palakkad district- IWMP-II-A 1/2009 -10 • Capacity building for watershed committees of IWMP Alathur by PIA, on Ragam Theatre Mangalamdam • Capacity building in IWMP Alathur by PIA, on Kizhakkencherry Gramapanchayath

Inspections • A number of Central, State, District and PIA level officials and People

Inspections • A number of Central, State, District and PIA level officials and People Representatives inspected and commended various stages during their inspections. We can explore the possibility of put forth the inspection scene of VIPs.

Visit of Secretary Do. LR Champakkulam, Alappuzha- IWMP 1/2010 -11

Visit of Secretary Do. LR Champakkulam, Alappuzha- IWMP 1/2010 -11

Visit of Secretary Do. LR at vamanapuram, Trivandrum district- IWMP 1/2010 -11

Visit of Secretary Do. LR at vamanapuram, Trivandrum district- IWMP 1/2010 -11

IEC initiatives. The State has initiated some model programs under IEC and general awareness

IEC initiatives. The State has initiated some model programs under IEC and general awareness programs which are unique are highlighted. • • • World Environment Day celebrations. World Earth Day celebrations. Street plays. Annual Reports. Social mobilization.

State level Inaugural Function on 10/5/2012 at Paravoor watershed- IWMP-1/2010 -11 Entry Point Activites

State level Inaugural Function on 10/5/2012 at Paravoor watershed- IWMP-1/2010 -11 Entry Point Activites inauguration at Vamanapuram watershed, Trivandrum district- IWMP 1/2010 -11

World Environment day celebration by Vamanapuram watershed, Thiruvananthapuram district- • Planted 100 fruit yielding

World Environment day celebration by Vamanapuram watershed, Thiruvananthapuram district- • Planted 100 fruit yielding trees in various school campuses • Model vegetable gardens in schools raising 250 vegetable grow bags • Distributed 2000 tree saplings to students and public

IWMP SHILPASHALA ON 30/05/13 AT CHIRAYINKEESZH Watershed, Thiruvananthapuram district: IWMP-II/2011 -12

IWMP SHILPASHALA ON 30/05/13 AT CHIRAYINKEESZH Watershed, Thiruvananthapuram district: IWMP-II/2011 -12

AS A PART OF IWMP, ENVIRONMENTAL DAY WAS CELEBRATED ON 5 TH JUNE 2013

AS A PART OF IWMP, ENVIRONMENTAL DAY WAS CELEBRATED ON 5 TH JUNE 2013 AT ALL SCHOOLS IN THE WATERSHED AREA OF CHIRAYINKEEZH BLOCK PANCHAYATH- IWMP-II/2011 -12 GOVT HSS AYILAM (MUDHAKAL PANCHAYAT) S C V B HS CHIRAYINKEEZH GOVT HSS KIZHUVILAM GOVT HSS ELAMBA

World environment day Exhibition organised by WCDC Kannur Exhibition organised by WCDC Eranakulam

World environment day Exhibition organised by WCDC Kannur Exhibition organised by WCDC Eranakulam

Planting trees at Payyanur block panchayath & Paravoor watershed on June 5 th Environment

Planting trees at Payyanur block panchayath & Paravoor watershed on June 5 th Environment day IWMP Payyannur- Kannur district- IWMP 1/2010 -11

June 5 th Environment day IWMP Payyannur- Kannur district- IWMP 1/2010 -11 Cotton bag

June 5 th Environment day IWMP Payyannur- Kannur district- IWMP 1/2010 -11 Cotton bag distribution School level environment day awareness programme

Water day celebrations- IWMP Payyannur- Kannur district- IWMP 1/2010 -11 Oath taking ceremony

Water day celebrations- IWMP Payyannur- Kannur district- IWMP 1/2010 -11 Oath taking ceremony

Water Day celebrations IWMP- Sulthan Bathery IWMPIV-H 5/2009 -10

Water Day celebrations IWMP- Sulthan Bathery IWMPIV-H 5/2009 -10

IEC activities at- – IWMP Alathur, Palakkad district- IWMP-IIA 1/2009 -10 Tradefair at Palakkad

IEC activities at- – IWMP Alathur, Palakkad district- IWMP-IIA 1/2009 -10 Tradefair at Palakkad Stall by Alathur IWMP 26. 8. 2012(1) Tradefair at Palakkad Stall by Alathur IWMP 26. 8. 2012(2) Pathravartha as a part of IEC

IEC activities at- – IWMP Alathur, Palakkad district- IWMP-IIA 1/2009 -10 Environment day Rally

IEC activities at- – IWMP Alathur, Palakkad district- IWMP-IIA 1/2009 -10 Environment day Rally celebration 2012 June 4 th Environment week celebration 2013 at St. Mary’s Public School Mangalamdam June 3 rd Environment week celebration 2013 at CAUP SCHOOL MAMPAD June 5 th Environment week celebration 2013 at Lourde matha Higher secondary School

IEC activities at- – IWMP Alathur, Palakkad district- IWMP-IIA 1/2009 -10 • June 6

IEC activities at- – IWMP Alathur, Palakkad district- IWMP-IIA 1/2009 -10 • June 6 th Environment week celebration 2013 at CVM Higher Secondary School Vandazhy • June 7 th Environment week celebration 2013 at GHSS Kizhakkanchery

Environment day celebrations. Vengara watershed Malappuram district- IWMPVI/2012 -13

Environment day celebrations. Vengara watershed Malappuram district- IWMPVI/2012 -13

Magic show on “Pollution free Vypin” conducted by renowned magician Ezhupunna Gopinath at various

Magic show on “Pollution free Vypin” conducted by renowned magician Ezhupunna Gopinath at various locations of Vypin watershed (IWMP 1/2010 -11), Eranakulam on 22. 05. 2013

Success Stories

Success Stories

Vamanapuram of Trivandrum (IWMP 1/2010 -11) and Pallom of Kottayam (IWMP-III/2012 -13) IWMP projects

Vamanapuram of Trivandrum (IWMP 1/2010 -11) and Pallom of Kottayam (IWMP-III/2012 -13) IWMP projects launched exclusive websites and all data made available on line Vamanapuram: http: //www. kslubiwmp. com/vmprm/index. php Pallom: http: //www. kslubiwmp. com/Pallom/index. php

Construction of check dam across Odamthode Watershed in Alathur, Palakkad district- IWMP-II-A 1/2009 -10

Construction of check dam across Odamthode Watershed in Alathur, Palakkad district- IWMP-II-A 1/2009 -10 Odamthodu in kizhakkenchery panchayath has 173 families. People depend on agriculture for their daily living. The main water source in this area is odamthodu. The two sides of this watershed are rounded with forest land. It is above 885 feet above from sea level. Total area of Odamthode watershed is 614 ha but treatable area is 481 ha • There are 614 ha in Odamthodu watershed out of which 481 ha is selected as treatable area, for EPA work the estimated amount is 1500000. The EPA work in this region is a shuttered check dam across Odamthodu. The check dam construction is beneficial for the people in this region as it will reduce the water storage. • As this is a hilly area, the water that they get during rainy season flow away and it cause severe water shortage during summer. There is not enough water for agricultural purpose and it is badly affecting agricultural production. Due to the construction of check dam across Odamthodu, the people in the region came together and supported the work and are benefited in their agricultural works and for daily use of Water. Outcomes • Sufficient water for daily use • Enhancement to production of agriculture • Reduction of water scarcity • Brought Unity among the People of Odamthodu •

Palambra Thode: Kodakara in Thrissur District. IWMP 1/2010 -11 Palambra Thode is a rivulet

Palambra Thode: Kodakara in Thrissur District. IWMP 1/2010 -11 Palambra Thode is a rivulet in Varantharappilly Panchayath of Allencherry Padam_ Kallanthodu Microwatershed (17 K 28 b) having an area of 2483. 11 hec. This rivulet was completely in a shattered condition and used to submerge the locale during the monsoon. The VCB was too old to deliver any benefit to 52 acres of land of the populace. Then IWMP was appeared as a panacea. • The renovation of Plambra Thode was selected as an Entry Point Activity of Kodakara PIA earmarking Rs. 7 lakhs. A user group was immediately formed to start the work. The work was inaugurated on 08 -03 -2013 by Sri. Sivaraman, Block Panchayath President of Kodakara to complete it on 15 -05 -2013. Two sides of the stream was packed with rubbles spanning 80 meters and well plastered over it. A VCB having length of 8 meters were also built. The direct beneficiaries of this programme are the people living around this stream. OUTCOMES • (1)The water runs thorough this stream in the summer can be preserved to reduce the intensity of water scarcity to a greater extend • (2) Re-energise the paddy and other Agri. cultivation • (3) Checking the flow of water during monsoon to reduce the intensity of deluge. • As far as IWMP is concerned it is one of the better Advertisement/ Publicity of this Programme as the work is well executed and eye catching. In addition to this, it is a good example of great will and collective manpower of a user group that can be replicated in other programmes. •

Palambra Thode: Kodakara in Thrissur District. IWMP 1/2010 -11

Palambra Thode: Kodakara in Thrissur District. IWMP 1/2010 -11

Renovation of pond at Koyipra paddy field of Kannilamthodu watershed- IWMP Payyannur- Kannur district-

Renovation of pond at Koyipra paddy field of Kannilamthodu watershed- IWMP Payyannur- Kannur district- IWMP 1/2010 -11 • The user group proposed renovation of pond at Koyipra paddy field. This pond had been beneficial for 200 farmers, as it was providing adequate water for cultivation. Over the years, the pond was neglected and the side walls were fallen down as a result its depth and water storage capacity were reduced the farmers were forced to stop cultivation for several years. The activities involved are in two phases 1) In Entry Point Activity (EPA), Extra deepening of pond by 2. 1 m and retaining wall construction using laterite boulders. 2) In NRM-Retaining wall, Pitching on sloped surface of the pond also steps for conveyance and protection wall allaround

OUTCOME…. . • We could increase storage capacity of pond by 473 cum through

OUTCOME…. . • We could increase storage capacity of pond by 473 cum through this work. • Paddy cultivation and Horticulture will increase • A soil mining company has been stopped from mining the land due to the construction of pond. So, the area has been saved from land degradation, decreasing water table leading to topographic disorder, habitat destruction, destruction of agricultural land etc. All these factors could have led to ecological imbalance of the area. • User group is planning for Aqua cultivation after completion of the work • As a result of the work, almost all the families of the watershed participate in all the IEC & capacity building programmes conducted by the PIA.

Before the work During the work After the work

Before the work During the work After the work

Kochukayal Pipe Culvert -Alappuzha District is IWMP-I/2010 -11 at Champakulam • A pipe culvert

Kochukayal Pipe Culvert -Alappuzha District is IWMP-I/2010 -11 at Champakulam • A pipe culvert of 10 meter length and 3 meter width (Kochukayal Pipe Culvert) was constructed under entry point activity of IWMP • One side of the structure is paddy field and the other side is water logged area • This construction helps to regulate water flow in 65 acres of paddy field and the other side fresh water pisciculture is possible in an area of 4 acres and it is taken in the annual plan 2013 -14 in convergence with MGNREGS and Fisheries department. The project cost is Rs. 2, 20, 000/-. This work is done by the user group of Naduthuruthu. • It also provides a footway for 100 families and childrens of nearby Anganvadi where boat service is the only connectivity to other places. • The major problem faced by the people in the area is difficulty of material conveyance. The earth for the work was brought from Kottayam district, 40 Kms away by lorry, then carried to material transportation boat with the help of skilled labour. The poured earth again transported to the worksite by trolly. For the poor people who are living in the area, unable to bear huge conveyance charge. Hence the work taken through EPA was whole-heartedly welcomed by the natives.

Kochukayal Pipe Culvert -Alappuzha District is IWMP-I/2010 -11 at Champakulam

Kochukayal Pipe Culvert -Alappuzha District is IWMP-I/2010 -11 at Champakulam

Well Recharging in Wadakanchery Block Panchayath- of Thrissur district- IWMP 2/2010 -11 • Mandan

Well Recharging in Wadakanchery Block Panchayath- of Thrissur district- IWMP 2/2010 -11 • Mandan Parambu Colony situated in Kadangode gramapanchayath is a very dry hilly area. The main water sources are wells. Since January onwards the wells begin to dry. The residents of the colony have no other source for drinking water. The colony is a habitat of “Nayadees”, a very backward class. • Under the Entry Point Activity of IWMP, Wadakanchery recharged wells of Mandamparambu Colony situated in Kunnetheri. Mathra Thodu Watershed. Under the said program 19 private wells and 1 public well have been recharged with the cooperation of a government aided agency, “Mazhapolima”. Their main program is to promote Water Conservation through Point Recharge. • Through this activity the Block Panchayath could solve the Water Scarcity of the Mandamparambu Colony to some extent. Though a small achievement but it occurred to be a big boon to the people there.

A recharged well in Wadakanchery Block Panchayathof Thrissur district- IWMP 2/2010 -11

A recharged well in Wadakanchery Block Panchayathof Thrissur district- IWMP 2/2010 -11

Kochukayal Pipe Culvert at Champakkulam, Alappuzha. IWMP 1/2010 -11 • Kochukayal Pipe Culvert is

Kochukayal Pipe Culvert at Champakkulam, Alappuzha. IWMP 1/2010 -11 • Kochukayal Pipe Culvert is constructed at Naduthuruthu, lan Island where Boat service is the only connectivity to the other places. One hundred families lived there. • The Pipe Culvert regulates water intake in Kannittakayal Paddy field. That helps agriculture in 65 acre. It also provide footway to the villagers. Kochukayal pond situated near the Pipe Culvert. It facilitate Kochukayal pond renovation and fresh water fish culture that includes in the 2012 -2013 plan, convergence with NREGS and Fisheries. • This work was started on 19. 04. 2013 and completed on 04. 06. 2013. The Prioject cost is Rs. 2, 20, 000/-. • After inauguration of the culvert, a training programme was conducted to the user group members for maintaining Asset.