Installation Review March ‘ 03 u Installation step 4. (3 days) temporary support It’s

Installation Review March ‘ 03 u Installation step 4. (3 days) temporary support It’s made of 2 halves; the upper one is brought into position through rotation about axis “A” (to avoid risks for the beam pipe) n It has 4 flaps (“B”) at ± 45º for fixation of beam-pipe and SPD supports prior to transfer their load to ITS n u Align (survey) temporary support to the beam pipe F. Tosello, L. Simonetti – INFN Torino A B A

u. Fix support for beam pipe Installation Review and FMD (“ 3 rd cone”)

u. Fix support for beam pipe Installation Review and FMD (“ 3 rd cone”) to March ‘ 03 temporary support Installation step 5. (4 days) n The 3 rd cone is made of two halves containing the FMDs n lifting tools allow for slow and accurate positioning of 3 rd cone n Spoke structure reduces material in front of FMDs and allows for visual inspection u. Test FMDs n FMDs have pigtails up to the outer edge of the 3 rd cone u. Remove 3 rd cone lifting tools Lifting tool Dummy 3 rd cone F. Tosello, L. Simonetti – INFN Torino FMD – Si 1

Installation Review March ‘ 03 Installation step 6. (2 days) u Mount and adjust

Installation Review March ‘ 03 Installation step 6. (2 days) u Mount and adjust 1 st support to the beam pipe n n Responsibility AT/VAC Survey u Mount and adjust monitoring system of bellow movements n n Responsibility ALICE Non-touching capacitive sensors are proposed Lifting tool F. Tosello, L. Simonetti – INFN Torino

Installation Review March ‘ 03 u Remove Installation step 7. (8 days) Temporary support

Installation Review March ‘ 03 u Remove Installation step 7. (8 days) Temporary support section 2 of beam pipe support SPD services (Resp. AT/VAC) u Install the two SPD halfcylinders (Resp. ALICE) 3 rd cone Section 2 SPD cone Two half cylinder/cones n Specific installation tools are being designed n SPD services (cables, fibres & capillaries) are pre-assembled in the cones n Fix the two, coupled, SPD half-cylinders to temp. support, above the 3 rd cone, using a 2 nd series of bolts & precision plugs n ¨SPD fixed in cantilever mode to temp. support, SPD pigtails on RB 24 side. L. Simonetti unconnected F. Tosello, – INFN Torino 4

u Slide Installation Review March ‘ 03 Installation step 8. (7 days) outer ITS

u Slide Installation Review March ‘ 03 Installation step 8. (7 days) outer ITS onto SPDs (Responsibility ALICE) n Transfer load of SPD and 3 rd cone (beam pipe) from temporary support to ITS n Connect SDD and SSD on RB 26 side n Final fixation of SPD pigtails on RB 24 Temp. Support side to ITS cone u Mount and adjust 2 nd support to the beam pipe (resp. AT/VAC) n Survey u Outer ITS, SPD & beam pipe are now an integral unit SPD SDD SSD F. Tosello, L. Simonetti – INFN Torino TPC/C 4