Installation Accelerator Systems Installation Planning Schedules Install org

  • Slides: 31
Download presentation
Installation – Accelerator Systems • Installation Planning & Schedules – Install org chart &

Installation – Accelerator Systems • Installation Planning & Schedules – Install org chart & planning – 2007 Installations – BTH -> FEH “ 2008” Installation October 29 -31, 2007 FAC Review – Accelerator Installation 1 Richard M. Boyce boyce@slac. stanford. edu

* October 29 -31, 2007 FAC Review – Accelerator Installation 2 Denotes IMT member

* October 29 -31, 2007 FAC Review – Accelerator Installation 2 Denotes IMT member Richard M. Boyce boyce@slac. stanford. edu

Installation Planning • 2007 SLAC Shutdown –SLAC downtime – September, October, November 2007 •

Installation Planning • 2007 SLAC Shutdown –SLAC downtime – September, October, November 2007 • 2007 Installation Planning – Installation through BC 2 & all cable plant; including cables through the BSY into the BTH West – Using SLAC Schedule process for SLAC resource loading • 2008 Installation Planning – LCLS installations begin at Early Occupancy dates defined by TCCo & LCLS – 2008 Installation schedule developed to begin detailed planning & integration process – refined by the rebaseline • Early Co-Occupancy dates being defined • Will follow on 2007 Installation learning curve and use P 3 for detailed install schedule (shift work, multiple calendars, etc) • Schedule shows Metrology work starting as early as December 2007 October 29 -31, 2007 FAC Review – Accelerator Installation 3 Richard M. Boyce boyce@slac. stanford. edu

2007 Installation Schedule LCLS 2007 Installation schedule includes: Facilities Work Sector 21 – 30

2007 Installation Schedule LCLS 2007 Installation schedule includes: Facilities Work Sector 21 – 30 electrical BTH West MEP & LCW Cable Plant Sector 24 – 30 I&C and DC cables for BC 2 BSY Work Cables from B 005, B 106, B 136 into BTH West BPM S 21 to BSY Mechanical/Vacuum Sector 24 – 29 removal and installations of BC 2 & L 3 Controls BCS; BC 2 Magnet controls; Vacuum System; BC 2 Timing System; BC 2 MPS; BC 2 Networks; BC 2 Motion Control System October 29 -31, 2007 FAC Review – Accelerator Installation 4 Richard M. Boyce boyce@slac. stanford. edu

2007 Installation Schedule (cont) LCLS 2007 Installation schedule, as of 10/19/07, contains 550 task

2007 Installation Schedule (cont) LCLS 2007 Installation schedule, as of 10/19/07, contains 550 task lines Shift work and multiple crews being used for Mech/Vac; shift work in schedule for Cable Plant work during PPS no access periods Critical Path As of 10/19/07, CP runs through BC 2 Removal of hardware - Cable plant and component install – cable terminations – cable testing; complete 11/23/07 Magnet testing & checkouts need to interleave and follow cable completion through end of downtime Further testing may need ROD periods October 29 -31, 2007 FAC Review – Accelerator Installation 5 Richard M. Boyce boyce@slac. stanford. edu

2007 Installation Schedule (cont) LCLS 2007 Installation schedule 6/22/07 BSY Work (for example) Cable

2007 Installation Schedule (cont) LCLS 2007 Installation schedule 6/22/07 BSY Work (for example) Cable Plant from B 005, B 106, B 136 into BTH West Requires Downtime (obviously) to install cables, therefore needed in 2007 down. Magnet loads not installed until ~March 2008, but need to checkout & commission before next downtime Cable plant (Controls) install needs to be coordinated with BTH West MEP (LCLS CF) October 29 -31, 2007 FAC Review – Accelerator Installation 6 Richard M. Boyce boyce@slac. stanford. edu

BSY Work – B 005 to BTH West Cable run from B 005 through

BSY Work – B 005 to BTH West Cable run from B 005 through the BSY, into BTH West via ~12 small penetrations B 005 October 29 -31, 2007 FAC Review – Accelerator Installation 7 Richard M. Boyce boyce@slac. stanford. edu

2007 LCLS Installation Schedule 0 of 4 Started integrating schedules in July October 29

2007 LCLS Installation Schedule 0 of 4 Started integrating schedules in July October 29 -31, 2007 FAC Review – Accelerator Installation 8 Richard M. Boyce boyce@slac. stanford. edu

2007 LCLS Installation Schedule 1 of 4 Status as of 10/19/07 Completed items removed

2007 LCLS Installation Schedule 1 of 4 Status as of 10/19/07 Completed items removed October 29 -31, 2007 FAC Review – Accelerator Installation 9 Richard M. Boyce boyce@slac. stanford. edu

2007 LCLS Installation Schedule 2 of 4 October 29 -31, 2007 FAC Review –

2007 LCLS Installation Schedule 2 of 4 October 29 -31, 2007 FAC Review – Accelerator Installation 10 Richard M. Boyce boyce@slac. stanford. edu

2007 LCLS Installation Schedule 3 of 4 October 29 -31, 2007 FAC Review –

2007 LCLS Installation Schedule 3 of 4 October 29 -31, 2007 FAC Review – Accelerator Installation 11 Richard M. Boyce boyce@slac. stanford. edu

2007 LCLS Installation Schedule 4 of 4 Several Controls Systems schedules included: PPS, BCS,

2007 LCLS Installation Schedule 4 of 4 Several Controls Systems schedules included: PPS, BCS, Magnet, Vacuum, MPS, etc. October 29 -31, 2007 FAC Review – Accelerator Installation 12 Richard M. Boyce boyce@slac. stanford. edu

2007 Installation Schedule (cont) Installation checks & balances RSWCF for linac & cable way

2007 Installation Schedule (cont) Installation checks & balances RSWCF for linac & cable way penetrations ES&H review of Statement Of Work’s (SOWs) Subcontractor installations Appropriate training Work authorization forms (WAF) AD & LCLS forms Radiation Work Permit (RWP) Electrical safety for cable plant install & connection to PS PO lockdown procedure being used October 29 -31, 2007 FAC Review – Accelerator Installation 13 Richard M. Boyce boyce@slac. stanford. edu

Shutdown Planning & Installation Schedule • Installation Planning & Schedules – BTH -> FEH

Shutdown Planning & Installation Schedule • Installation Planning & Schedules – BTH -> FEH 2008 Installation October 29 -31, 2007 FAC Review – Accelerator Installation 14 Richard M. Boyce boyce@slac. stanford. edu

2008 Installation Planning • 2008 Installation Planning – LCLS installations begin at Early Occupancy

2008 Installation Planning • 2008 Installation Planning – LCLS installations begin at Early Occupancy dates defined by TCCo • BTH, Undulator Hall & Service Buildings available as early as December 5, 2007; NEH 12/21/07; X-ray tunnel 1/8/08; FEH 3/24/08; SB 2. 3 late December • TCCo has priority over co-occupied space until B. O. – BTH-NEH B. O. 3/21/08; X-ray tunnel – FEH B. O. 6/23/08 – NEH elevator not available until ~March 2008, will limit early equipment installation • Subcontract SOWs are being prepared • Need to ensure this work does not impact the 2007 installation effort, but stay on schedule (cable plant already slipped into February 2008) October 29 -31, 2007 FAC Review – Accelerator Installation 15 Richard M. Boyce boyce@slac. stanford. edu

2008 LCLS Installation Schedule 1 of 7 2008 Schedule 2007 Downtime • Co-Occupancy dates

2008 LCLS Installation Schedule 1 of 7 2008 Schedule 2007 Downtime • Co-Occupancy dates defined • Major subcontracts used for installations • First activity is Metrology network installation LTU components connect to cables installed through BSY in 2007 downtime October 29 -31, 2007 FAC Review – Accelerator Installation 16 Richard M. Boyce boyce@slac. stanford. edu

LTU Hardware contained inside BTH West and BTH Entry areas are East & West

LTU Hardware contained inside BTH West and BTH Entry areas are East & West mazes, and openings at headhouse Will plan access areas to limit interferences with Undulator and LTU installation phases West Maze entry point Headhouse entry East Maze – Undulator entry point SB 2. 1 SB 2. 2 BTH West tunnel October 29 -31, 2007 FAC Review – Accelerator Installation SB 2. 3 17 Undulator Hall Richard M. Boyce boyce@slac. stanford. edu

2008 LCLS Installation Schedule 2 of 7 LTU components installed in BTH Undulator girder

2008 LCLS Installation Schedule 2 of 7 LTU components installed in BTH Undulator girder installation October 29 -31, 2007 FAC Review – Accelerator Installation 18 Richard M. Boyce boyce@slac. stanford. edu

LCLS UNDULATOR SYSTEM 33 rf Beam Position Monitors 33 Beam Finder Wires Wire Position

LCLS UNDULATOR SYSTEM 33 rf Beam Position Monitors 33 Beam Finder Wires Wire Position Monitor Hydro static level system 33 Undulators 33 Quadrupoles/Correctors EM air-cooled 10 Long breaks 22 Short Breaks Supports with movers 5 DOF plus horizontal slider Vacuum System interconnects October 29 -31, 2007 FAC Review – Accelerator Installation 19 Richard M. Boyce boyce@slac. stanford. edu

Egress space between aisle and back of undulators (cleared with Fire Marshal) October 29

Egress space between aisle and back of undulators (cleared with Fire Marshal) October 29 -31, 2007 FAC Review – Accelerator Installation Undulator Elevation 20 Richard M. Boyce boyce@slac. stanford. edu

~430’ long Integration also means knowing what the facility looks like prior to installing

~430’ long Integration also means knowing what the facility looks like prior to installing equipment October 29 -31, 2007 FAC Review – Accelerator Installation 21 Richard M. Boyce boyce@slac. stanford. edu

Undulator Hall SB 2. 3 SB 3. 1 Beam dump/Fee area October 29 -31,

Undulator Hall SB 2. 3 SB 3. 1 Beam dump/Fee area October 29 -31, 2007 FAC Review – Accelerator Installation 22 Richard M. Boyce boyce@slac. stanford. edu

2008 LCLS Installation Schedule 3 of 7 E- Dump components installed FEE installation October

2008 LCLS Installation Schedule 3 of 7 E- Dump components installed FEE installation October 29 -31, 2007 FAC Review – Accelerator Installation 23 Richard M. Boyce boyce@slac. stanford. edu

LCLS 2008 Installation schedule FEE systems are well along in the planning stages October

LCLS 2008 Installation schedule FEE systems are well along in the planning stages October 29 -31, 2007 FAC Review – Accelerator Installation 24 Richard M. Boyce boyce@slac. stanford. edu

2008 LCLS Installation Schedule 4 of 7 NEH Installations; most of which are delayed

2008 LCLS Installation Schedule 4 of 7 NEH Installations; most of which are delayed into FY 09 October 29 -31, 2007 FAC Review – Accelerator Installation 25 Richard M. Boyce boyce@slac. stanford. edu

LCLS 2008 Installation schedule NEH overview NEH Hutches October 29 -31, 2007 FAC Review

LCLS 2008 Installation schedule NEH overview NEH Hutches October 29 -31, 2007 FAC Review – Accelerator Installation 26 Richard M. Boyce boyce@slac. stanford. edu

2008 LCLS Installation Schedule 5 of 7 X-Ray tunnel and FEH installation delayed until

2008 LCLS Installation Schedule 5 of 7 X-Ray tunnel and FEH installation delayed until FY 2009 October 29 -31, 2007 FAC Review – Accelerator Installation 27 Richard M. Boyce boyce@slac. stanford. edu

2008 LCLS Installation Schedule 6 of 7 LTU ready – 8/11/08 Und ready –

2008 LCLS Installation Schedule 6 of 7 LTU ready – 8/11/08 Und ready – 10/15/08 FEE ready – 4/30/09 October 29 -31, 2007 FAC Review – Accelerator Installation 28 Richard M. Boyce boyce@slac. stanford. edu

2008 LCLS Installation Schedule 7 of 7 2008 Downtime Systems ready for first electron

2008 LCLS Installation Schedule 7 of 7 2008 Downtime Systems ready for first electron beam into LTU & dump by 10/22/08 Commissioning activities leading to CD-4 2009 Downtime October 29 -31, 2007 FAC Review – Accelerator Installation 29 Richard M. Boyce boyce@slac. stanford. edu

Summary • 2008 Installation Planning – Early occupancy of Conventional Facilities will begin the

Summary • 2008 Installation Planning – Early occupancy of Conventional Facilities will begin the installation process for technical systems • Working to understand definition of early occupancy for each area – Does not require Linac/PEPII down for LCLS installations • BTH West installation puts some limits on beam operation to other areas like ESA – Need to coordinate several subcontracts (~3 -4? ) to install mechanical systems and cable plant simultaneously – Detailed Installation planning in process by coordinators October 29 -31, 2007 FAC Review – Accelerator Installation 30 Richard M. Boyce boyce@slac. stanford. edu

End of Presentation October 29 -31, 2007 FAC Review – Accelerator Installation 31 Richard

End of Presentation October 29 -31, 2007 FAC Review – Accelerator Installation 31 Richard M. Boyce boyce@slac. stanford. edu