Injectors LHC report K Foraz on behalf of
Injectors & LHC report K. Foraz on behalf of OSS members 31/01/14 LSC - EN-MEF-OSS 1
AD &LEIR • AD – BHN 06: • Should be back in AD on February 17 th (delay with vacuum chamber delivery – @ CERN now) – KFI tanks reinstallation • KFI 56 & KFI 55: one leak found on 1 st kicker – being solved no delay – Demineralized water will be back on Feb. 10 th – Vacuum maintenance in progress • LEIR – Access system test on February 17 th – Additional racks for transverse damper will be installed soon Courtesy B. Lefort & A. Bouvard 31/01/14 LSC - EN-MEF-OSS 2
PS • In Progress – Consolidation of the 7 PS main magnets completed – Dummy septum in SS 15 on beam line including alignment completed – Installation of fire doors progressing quickly – CV Consolidation in progress - Commissioning started. New chimney installed. Training for exploitation started. – Magnets maintenance started in TT 2 beam line – Flexible hoses replacement progressing well – Septum 16 External Shielding in progress – General equipment maintenance: Beam Instrumentation, Beam Stoppers… – Power House renovation b 355 on going and will be finished for the middle of Feb. 31/01/14 LSC - EN-MEF-OSS 3
PS start-up & POPS • Plan for POS & MPS – – – “ 7 th to 16 th April : test with POPS on PS magnets 16 th to 18 th April: test with MPS on PS magnets 22 nd April to 10 th May: run with PS machine (due to EN/CV maintenance of cooling station) 11 th May to 19 th May: no run due to installation of magnet covers 20 th May restart with POPS – We plan to make measurements on Test magnets during the next week. We presently restarted POPS and are making first pulses. ” Courtesy J. P. Burnet – Transparent to schedule May 20 th CV maint. 31/01/14 LSC - EN-MEF-OSS 4
PSB • • Completed. - Installation of 4 new SMV power converters in the BCER. - Installation of the Finement cavity (LIU project) - Installation of the BLM cables. In progress – Installation of the beam dump cooling system and BTY access stairs – Civil engineering works to create a new cable trench to service the beam injector line (LIU project). – Commissioning of the BT. KFA 10/20 hydraulic & control circuits. – Cabling of the beam dump instrumentation & remote monitoring system. – Installation of the newly designed Pick ups (Type UES). – Cooling circuit upgrades to the main bending and quadrupole magnets. – Renovation of the PR 134 crane. – • New PR 137 Renovation PR 134 SMV power converters Finement cavities CV consolidation and maintenance of CV, kickers, Septa, vacuum beam instrumentation, Magnet and Beam stopper, cabling campaign. Forecast – Installation of the LIU BLM ionisation chambers. – Installation of the BTY line vacuum chambers. – Preparations for the identification of the PSB obsolete cables. – Installation of the modified BTM line SEM-GRID’s – Installation of the renovated BTY. UES 152 pickup. 31/01/14 LSC - EN-MEF-OSS LIU BLM’s Magnet cooling upgrade 5
SPS • BA 1: – Irradiated cabling campaign is on-going • • • TT 10: Work continuing on schedule. The re-installation phase of the work is going for ALARA approval next week. – Reinstallation of beam line has begun. • • • BA 2: The area has been cleaned. The magnets have already been installed. (see photo) – EN/EL have started the cable campaign in BA 2 - This work will continue until April 2014. – TE/ABT are in the process of replacing Septas in BA 2 • • BE-BI accidently opened the wrong flange and vented the vacuum on the Septa. ABT are currently looking into what impact this had on the Septa. (see presentation by B. Goddard) Other works: – We are getting ready to re-install 16 magnets into BA 5 that were removed at the beginning of LS 1 for vacuum chamber coating. 31/01/14 LSC - EN-MEF-OSS 6
Injectors progress curves 31/01/14 LSC - EN-MEF-OSS 7
LHC - P 1 • R 2 E – Pt 1: – Done • QPS commissioning – UJ 14 – In progress • • • Current heaters commissioning Collimation commissioning WCC orientation (IT. 1 R) – • During pressure test on Monday, demineralized water was sprayed on electrical boxes and power converters doors… to be followed LSS 1: – Vacuum work finished in, B 1 R 1, B 4 R 1, B 1 L 1, B 4 L 1, in progress in A 1 R 1 – Consolidation of inner triplets in progress – TAS issue • While pumping vacuum sub-sector A 1 R 1 , the TAS moved longitudinaly by 15 mm (reversible situation) • The bellow is temporary blocked in order to prevent TAS movement • A Z stopper will be installed before June 31/01/14 CMS TAS Z stopper LSC - EN-MEF-OSS Courtesy S. Evrard 8
LHC – P 1 1 st & 2 nd TCTP at CERN , since Jan. 22 nd • • “Preliminary reception done (mechanical part). We have implemented a specific reception procedure for these two first collimators to thoroughly test them at CERN on vacuum compatibility with the minimum effect on the installation date (week 10). This implies the installation of the RF-contact fingers in presence of the manufacturer. This step has been successfully achieved, also the reception test on the torque. The two units (with the TCSP spare) are now in the vacuum lab for a full qualification cycle with bake out. The results will be available in week 7. The next 4 units will arrive first week of March, with the vacuum qualification on the manufacturers site. The sequence is then 4 / month. ” Courtesy O. Aberle 31/01/14 LSC - EN-MEF-OSS 9
LHC – P 1 P 2 • Arc 12 : – In progress • SMACC – – Insulation boxes installation (74% 90%)* Diodes installation (34% 66%)* Weld M (34%) Leak test M (7%) • DFBAB and C consolidation – 1 R: M line closed – MLI and screen being reinstalled – 2 L: M 3 lines issue being solved • QRL compensator leak test done • RF Ball test today *: 29 Jan@8 h • Point 2 – – – • Cryogenic maintenance in progress UW maintenance just started in progress UPS installation in progress LSS 2 – – – Upgrade of beam vacuum valves : A 1 L 2, A 1 R 2 finished Mechanical vacuum work • Finished : I 5 L 2, D 4 L 2 MKI. D 5 L 2 aligned 31/01/14 LSC - EN-MEF-OSS 10
LHC - P 2 P 3 • Arc 23 – In progress • During water circuit filling, a valve broke in 8 R 2 Mid term action – List valves position – If in front of an open IC – protect valve • SMACC – – BB desoldering (97% 99%)* BB Soldering (92% 97%)* Shunt installation (86% 97%)* DFBA » D : shunt installation finished (end =wk 12) » E: shunt installation in progress (end =wk 13) • QRL compensator in progress • LSS 3 – Survey and alignment of intermediate components finished – Reinforcement of UJ 33 cable tray finished – Vacuum activities in progress • Sub-sectors opening (B 5 R&L 3) • Upgrade of beam vacuum valves (A 7 L&R 3) – Re-installation of WCC starting next week 31/01/14 LSC - EN-MEF-OSS *: 29 Jan@8 h 11
LHC - P 3 P 4 • Arc 34 – In progress • DFBA consolidation – DFBAF – Lyra consolidation in progress (end = wk 15) – DFBAG – opening in progress (end = wk 20) • SMACC: – – Cut M (81% 97%)* BB desoldering (64% 94%)* BB soldering (31% 72%)* Shunt (27% 59%)* *: 29 Jan@8 h 31/01/14 LSC - EN-MEF-OSS 12
LHC – P 4 P 5 • LSS 4 & P 4 – In progress • • New cooling tower installation SU and UW maintenance Cryogenic maintenance RF maintenance Alignment of Q 5, Q 6, MU New cabling campaign (control) Vacuum in A 6 R 4 – ACS module installation in progress • Arc 45 – In progress • M opening (23% 70%)* • BB desoldering (27%)* • DFBA • H : re-started (End = wk 22) • I : in stand –by (end = wk 23) – Helium spill test next week » All signals are green 31/01/14 *: 29 Jan@8 h LSC - EN-MEF-OSS 13
LHC – P 5 • LSS 5: – No access this week – all works in stand-by: • Vacuum activities: A 1 R 5, A 1 L 5, B 1 R 5 • R 2 E – P 5 Helium storage for helium spill test – In progress No access this week – all works in stand-by • Cabling in progress – BT cabling – Control cabling in progress RR 53 1 st Iron block 31/01/14 • RR 53 shielding installation LSC - EN-MEF-OSS WCC installation – strong men 14 !!
LHC – P 5 P 6 • Arc 56 – Finished • Leak tests – 13 validated – but 3 sub-sectors opened for dipole diodes (only pumping will be needed) – In progress • DFBAJ: finished • DFBAK. 6 L – Surface repair in progress- shuffling back today – ahead of schedule thanks to MME (End = wk. 19) • Non Conformities on diodes being solved 31/01/14 LSC - EN-MEF-OSS 15
LHC – P 6 • LSS 6 & P 6 – Forecast • • • New cables for BI (BPM) and CV (Eletta changes) pulled Short circuit test preparation in progress (SCT in wk 9) MKB-MKD tests resumed Cryogenic maintenance Vacuum : IP 6 NEG activation done New TCSP. 4 R 6 installed IP 6 – NEG activation 31/01/14 LSC - EN-MEF-OSS 16
LHC – P 6 P 7 • Arc 67 • Safety valves installed and purge done • ELQA in progress ELQA in sector 67 31/01/14 LSC - EN-MEF-OSS 17
P 7 • LSS 7 – Cabling campaign in progress in 7 L – Vacuum: • NEG activation done (A 5 L 7) Ventilation support – Consolidation of warm magnets in progress – P 7 enclosure • • • 31/01/14 2 nd door installation in progress Work on UW tapping in progress R 2 E – P 7: – Cabling campaign in progress LSC - EN-MEF-OSS 18 2 nd door installation
LHC - P 7 P 8 • Arc 78 – SMACC consolidation in progress • M leak test 90% 98% • Closure 66% 85% * • QRL compensator – New leak on QRL vacuum sub-sector (H) – being repaired • DFBA consolidation in progress – DFBAN. 7 R – finished. – DFBAO. 8 L (end = wk 21) » Surface consolidation in progress • Dipole diodes measurement – 3 outliers • UPS being replaced *: 29 Jan@8 h 31/01/14 LSC - EN-MEF-OSS 19
LHC - P 8 • LSS 8 &P 8 – Cable campaign ongoing (right and left sides ) – WCC rinsing in progress – Upgrade of beam vacuum valves in progress (A 78, A 1 L 8, A 1 R 8, MKI areas, A 7 R 8) – BTVST being installed WCC. 8 R 31/01/14 LSC - EN-MEF-OSS 20
LHC – arc 81 • Arc 81 - SMACC - DFBAP. 8 R (ends next week. ) final works in progress - DFBAA. 1 L splice consolidation (ends next week. ) final works in progress - SMACC - Shunt installation completed Diodes installation (97% 100%) * M welding (74% 99%) * M leak tests (56% 78%) * Closure started (30%) - Dipole diode measurement done - OK - Cryogenics consolidation and maintenance - QRL consolidation of the compensator header D in progress - Beam pipe pumping finished *: 16 Jan@8 h 31/01/14 LSC - EN-MEF-OSS 21
Overall progress 31/01/14 LSC - EN-MEF-OSS 22
LHC New version of schedule • A new version is under approval – Taking into account the updated detailed schedule of arcs, LSS and services – Please insert your comments before mid February 31/01/14 LSC - EN-MEF-OSS 23
Version 3. 1 • A new feature included in excel file « Show-Hide » – Please click enable editing 31/01/14 LSC - EN-MEF-OSS 24
From version 3. 0 • Schematic view of baseline schedule V. 3. 0 31/01/14 LSC - EN-MEF-OSS 25
From version 3. 0 to 3. 1 • Schematic view of version 3. 1, now includes – – 31/01/14 DFBA repairs at P 6 and P 8 CSCM in sectors 67 and 81 a margin of 2 weeks after flushing for N. C. solving The sector test from P 2 to P 3 LSC - EN-MEF-OSS 26
Version 3. 1 under approval • Your comments are needed – Please forward the information to your colleagues – Some discussions are, for instance, in progress • with cryo maintenance, in order to optimize resources across all facilities • W. r. t diodes issue – A new version will be issued 2 nd part of February 31/01/14 LSC - EN-MEF-OSS 27
- Slides: 27