Injector / Linac Installation Status Manager-Kathleen Ratcliffe Project Schedule/Integration-R. M. Boyce Construction Interface-J. Turner

Injector / Linac Installation Status Manager-Kathleen Ratcliffe Project Schedule/Integration-R. M. Boyce Construction Interface-J. Turner Major Partner-Mechanical Fabrication Department Installation Underway! Lehman Review 24 -26 October 2006 C. E. Rago 1

2006 Installation Sector 21 Sector 20 Laser BC 1 Out Bunch Compressor 1 X-Band

2006 Installation Sector 21 Sector 20 Laser BC 1 Out Bunch Compressor 1 X-Band Compressor L 1 Insertion/SAB Vault Wall Lehman Review 24 -26 October 2006 C. E. Rago 2

Linac Status Downtime Installation 10/~20 Weeks of Linac Access Prep Complete / Installation Underway

Linac Status Downtime Installation 10/~20 Weeks of Linac Access Prep Complete / Installation Underway Installation Considerations: Linac Housing / Return to A-Line Operation January 07 Vacuum Envelope & All Safety Systems Injection Vault / Laser Schedule and Controls SLAC Resources / MFD and Others Hardware Ready System Schedule / Commissioning Good Design, Teamwork, Control Lehman Review 24 -26 October 2006 C. E. Rago 3

2006 Installation Sector 21 Sector 20 Laser BC 1 Out Bunch Compressor 1 X-Band

2006 Installation Sector 21 Sector 20 Laser BC 1 Out Bunch Compressor 1 X-Band Compressor L 1 Insertion/SAB Vault Wall Lehman Review 24 -26 October 2006 C. E. Rago 4

BC 1 Out Future EO/BL BL 11/12 Lehman Review 24 -26 October 2006 C.

BC 1 Out Future EO/BL BL 11/12 Lehman Review 24 -26 October 2006 C. E. Rago TD 11 (Stopper) Wire Scanner / PMT 5

Bunch Compressor 1 4 Dipoles BC 1 Diagnostics 2 Tweeker Quads Lehman Review 24

Bunch Compressor 1 4 Dipoles BC 1 Diagnostics 2 Tweeker Quads Lehman Review 24 -26 October 2006 C. E. Rago 6 Chambers & Supports

Bunch Compressor 1 Sub-Assembly Lehman Review 24 -26 October 2006 C. E. Rago 7

Bunch Compressor 1 Sub-Assembly Lehman Review 24 -26 October 2006 C. E. Rago 7

BC 1 Vac Chamber & Magnets Lehman Review 24 -26 October 2006 C. E.

BC 1 Vac Chamber & Magnets Lehman Review 24 -26 October 2006 C. E. Rago 8

X-Band Compressor WC 293 Removable 60 cm X-Band Lehman Review 24 -26 October 2006

X-Band Compressor WC 293 Removable 60 cm X-Band Lehman Review 24 -26 October 2006 C. E. Rago 9

The X-band accelerator section Klystron, modulator being power tested prior to installation. Lehman Review

The X-band accelerator section Klystron, modulator being power tested prior to installation. Lehman Review 24 -26 October 2006 C. E. Rago 10

LX Installed Lehman Review 24 -26 October 2006 C. E. Rago 11

LX Installed Lehman Review 24 -26 October 2006 C. E. Rago 11

WC 293 Installation Lehman Review 24 -26 October 2006 C. E. Rago 12

WC 293 Installation Lehman Review 24 -26 October 2006 C. E. Rago 12

WC 293 Installed Lehman Review 24 -26 October 2006 C. E. Rago 13

WC 293 Installed Lehman Review 24 -26 October 2006 C. E. Rago 13

L 1 2 ea 9 ½ Ft DLWG Lehman Review 24 -26 October 2006

L 1 2 ea 9 ½ Ft DLWG Lehman Review 24 -26 October 2006 C. E. Rago 14

L 1 Installed Lehman Review 24 -26 October 2006 C. E. Rago 15

L 1 Installed Lehman Review 24 -26 October 2006 C. E. Rago 15

L 1 Quad Installed Lehman Review 24 -26 October 2006 C. E. Rago 16

L 1 Quad Installed Lehman Review 24 -26 October 2006 C. E. Rago 16

Insertion / SAB BX 02 Dipole SDMP / Stopper SAB Dipole OTRS 1 /

Insertion / SAB BX 02 Dipole SDMP / Stopper SAB Dipole OTRS 1 / ANL Lehman Review 24 -26 October 2006 C. E. Rago 17

2006 Installation Sector 21 Sector 20 Laser BC 1 Out Bunch Compressor 1 X-Band

2006 Installation Sector 21 Sector 20 Laser BC 1 Out Bunch Compressor 1 X-Band Compressor L 1 Insertion/SAB Vault Wall Lehman Review 24 -26 October 2006 C. E. Rago 18

The Injector Vault Cable plant, vault ready for beamline components. Lehman Review 24 -26

The Injector Vault Cable plant, vault ready for beamline components. Lehman Review 24 -26 October 2006 C. E. Rago 19

Wall 3 Wire Scanners BX 01 Dipole BBS Radiation Stopper Lehman Review 24 -26

Wall 3 Wire Scanners BX 01 Dipole BBS Radiation Stopper Lehman Review 24 -26 October 2006 C. E. Rago 20

Wall – Quad & Wire Scanner Lehman Review 24 -26 October 2006 C. E.

Wall – Quad & Wire Scanner Lehman Review 24 -26 October 2006 C. E. Rago 21

Heater Phase 1 Heater Table Lehman Review 24 -26 October 2006 C. E. Rago

Heater Phase 1 Heater Table Lehman Review 24 -26 October 2006 C. E. Rago 22

L 0 A / L 0 B L 0 A Lehman Review 24 -26

L 0 A / L 0 B L 0 A Lehman Review 24 -26 October 2006 C. E. Rago L 0 B 23

L 0 A on the MMF CMM Lehman Review 24 -26 October 2006 C.

L 0 A on the MMF CMM Lehman Review 24 -26 October 2006 C. E. Rago 24

Laser Table Gun / GTL Gun SAB Dipole Lehman Review 24 -26 October 2006

Laser Table Gun / GTL Gun SAB Dipole Lehman Review 24 -26 October 2006 C. E. Rago 25

Laser table Gun-to-Linac area To L 0 a Spectrometer GTL table Gun Lehman Review

Laser table Gun-to-Linac area To L 0 a Spectrometer GTL table Gun Lehman Review 24 -26 October 2006 C. E. Rago 26

The LCLS photocathode electron gun Lehman Review 24 -26 October 2006 C. E. Rago

The LCLS photocathode electron gun Lehman Review 24 -26 October 2006 C. E. Rago 27

Linac Housing Installation Status Wall / L 1 / X-Band Installation Underway Field staging

Linac Housing Installation Status Wall / L 1 / X-Band Installation Underway Field staging started. Final components moving from Storage to Field. Lehman Review 24 -26 October 2006 C. E. Rago 28

Linac Housing Installation Issues Fabrication Issues Feedthroughs / 9 & 10 Scale Leaks (~3/23

Linac Housing Installation Issues Fabrication Issues Feedthroughs / 9 & 10 Scale Leaks (~3/23 BPMs Held / Now welding) BC 1 Diagnostics / Late for January Install (No effect on commissioning schedule!) Late components: BLM 11 (BLM 12 will be installed to support commissioning) Toroids (Vendor failure / quantity to support commissioning) SAB/Insertion Vac Chambers. (Fabrication HELP from LBNL) Spool Pieces (Fabricated to support commissioning) These issues require scheduled downtime/s in January : March Lehman Review 24 -26 October 2006 C. E. Rago 29

LCLS Injection LCLS Insertion region Linac beam Vac Chambers late for January Linac integrity

LCLS Injection LCLS Insertion region Linac beam Vac Chambers late for January Linac integrity needed for ESA program in Jan. Lehman Review 24 -26 October 2006 C. E. Rago 30

Injector Installation Status Injector Installation / Second priority to Linac. Injector vault: Floor and

Injector Installation Status Injector Installation / Second priority to Linac. Injector vault: Floor and cable plant installed Injector beamline: Accelerator structures, L 0 a ready, L 0 b / Ready S-Band WG / Last pieces in final bake. Gun in hot test at Klystron Mfg / Looks Good! Second gun assembly is in pre-braze cold-test. Vault Supports & Tables waiting contract start. GTL supports & table highest priority Lehman Review 24 -26 October 2006 C. E. Rago 31

Injector Installation Issues Water system under pressure to make schedule! Integrated Design Multiple contracts

Injector Installation Issues Water system under pressure to make schedule! Integrated Design Multiple contracts have been let! Much traction since last Lehman review! GTL System at highest fabrication priority! Improve on 2/8/07 RFI projection. Lehman Review 24 -26 October 2006 C. E. Rago 32

Some Good Stuff Good Design and Solid Documentation. Active Data Base Interconnect Control Component

Some Good Stuff Good Design and Solid Documentation. Active Data Base Interconnect Control Component Histories Non-Compliance Effective Teamwork MFD/MD/KLY/AD Downstream Linac under design! Lehman Review 24 -26 October 2006 C. E. Rago 33