Injection and Beam Dump B Goddard V Mertens
Injection and Beam Dump B. Goddard, V. Mertens, M. Barnes, E. Carlier, F. Castronuovo, L. Ducimetiere, E. Gallet, V. Kain, M. Lamont, J. Uythoven + many, many others • Brief overview of system components and dependencies • Breakdown of tests foreseen in preparation for beam • Equipment “folder”: tests results, handling of non conformities, performance below specs, machine as commissioned vs. machine as specified • Piquet/Experts availability 3 rd March 2008 Extended LTC
Part the 1 st injection systems 3 rd March 2008 Extended LTC
Injection systems: schematic view (LSS 8 R) 3 rd March 2008 Extended LTC
Injection sub-systems • Main injection sub-systems – – – – • Injection septa MSI Injection kickers MKI Kicker state control and surveillance Injection protection devices TCDI, TCDIM, TDI, TCDD(M), TCLIA/B, TCLIM Beam instrumentation BTVs, BPMs, BLMs, FBCTs Vacuum system Injection quality checks IQC Links to other systems – – – – BIS, via the injection BICs and the main LHC BICs Injection pre-pulse from RF in point 4 LBDS for abort gap keeper and arming inhibit LHC control system and timing SLP for beam energy Vacuum for MKI interlocking and conditioning TL BCT and special LHC ring BPMs for kicker ↔ beam synchronisation Major part of transfer lines not included here (… but also being followed up). 3 rd March 2008 Extended LTC
Injection systems: IST and HWC (I) • Individual System Tests and HWC : making sub-systems work – Septa MSI • Fully commissioned (electrical tests, polarity, water flow, interlocks, heat run … done) • Vacuum chambers baked out • IR 2: DCCT still to be re-configured (modification of compensation coil) – Kickers MKI • • Major part of commissioning finished – all remotely controllable HV tested to beyond nominal voltage Links to external systems being commissioned piecewise, still to test BIS, RF pre-pulses, IR 8: Re-bake MKI interconnects (w 14? ) to gain in vacuum ( HV performance), followed by short HV test • Inter-tank valves to be (re-)opened as needed for beam operation (not prematurely !) – Beam instrumentation: basically “all commissioned – waiting for beam”, except • BTV: some devices to be finished/recalibrated after bake-out of adjacent equipment • BLM: situation around MSI to be checked (mixture TL / ring or add a few more …) – EMC tests between equipment (kickers, p. converters, cryo, …) scheduled for w 12 -13 3 rd March 2008 Extended LTC
Injection systems: IST/HWC results HV pulse testing/conditioning of MKI in LSS 2 L, with inter-tank valves open (28 th Feb 08) voltage pulse counter vacuum pulse form 3 rd March 2008 Extended LTC pulse length
Injection systems: IST and HWC (II) – Transfer line protection devices TCDI/M • • All in place Some cables to shield against cross-talk from power cables, Some screws/springs to replace ex-vacuum, TCDIH 87904 to re-align (vacuum intervention w 14) – LHC injection Protection devices TDI, TCDD(M), TCLIA/B, TCLIM • IR 2 TDI in place (to bake out), IR 8 TDI to replace against new model (w 14 with adjacent TCTVB), close vacuum, bake-out, NEG activation. • TDI electronics/controls/mechanisms – still to finish in-situ part of commissioning • IR 8 TCDDM in place, IR 2 TCDD to install (w 13 with TCTVB), close vacuum, bake-out, NEG • All TCLIB/TCLIM in place – Vacuum • Rings: under vacuum, bake-out / NEG activation done (with exception of short areas around TCTVB, TDI/TCDD) • End of transfer lines: tested and under vacuum – Organisation: responsibility and coordination • HWC responsible for coordinating IST/HWC carried out by equipment groups: planning, access, safety, impact of cooldowns, EMC tests, … • Strong support from LTI project – providing lubricant in interfaces (as it were) 3 rd March 2008 Extended LTC
Injection systems: dry runs • Dry runs : running injections as a system from CCC – Commissioning system links and interdependencies, SW tools, … – Possible to already be “fully-connected” to all external systems – First dry-run test (2 days) carried out in December 2007 • Checked B 1 and B 2 systems in “mostly-stand-alone” mode (no BIS connection, no SLP, no connection to LBDS, no RF prepulse, some timing issues to address) – Further 2 -day tests planned with increasing scope and complexity: • W 15: B 1 and B 2 systems connected to SLP, RF and timing, … • W 19: links to LBDS, BIS, testing inject and dump modes, … • W 23: Full set of injection scenarios – Organisation, responsibility and coordination • Much preparation and mobilisation for HW, controls and SW • OP responsible for dry runs: schedule, test, tools, coordinate • BT/LTI providing strong support… 3 rd March 2008 Extended LTC
Injection systems: machine check-out • Machine check-out : run injections as embedded systems from CCC – Will be “fully-connected” to all external systems (in particular RF, SLP, timing, BIS, LBDS) – Re-check all injection scenarios with all interconnects in place • • Checks of all equipment, SW, sequencing, timing, interconnection, … Will need beam permit from BIS loop, to allow injection kickers to pulse – Organisational issues: responsibility and coordination • • OP responsible for machine check-out, with support from equipment groups and LTI project BT will provide system commissioning team (scheduled or on call as required) + MKI and controls piquet 3 rd March 2008 Extended LTC
Injection systems: known issues • Follow-up of “non-conformities” – Known tight spots – need more formal documentation • Aperture limits at Q 5 (tilted), MKI, D 2, TDI (informal note JBJ) • Injection line chamber size/position where passing Q 6 (informal note JMJ) • MSI alignment and aperture (EDMS 488061) – MKI high-frequency ripple • Net effect on beam being calculated, including action of transverse damper (BG, WH) • Kicker “soft-start” before injection – To mitigate effects of de-conditioning after pause (in parallel with turnaround) – Additions being prepared now (sequencer, modifications of interlocks, …) • Documentation / data bases – Scope of formal change management system to be defined (if any …) – Layout database to be worked on with DB people – finish off some details – Aperture model to be completed and re-checked – TL models ready for DB • Completion of installations – TCLIA in LSS 2 R/LSS 8 L in shutdown 2008/09 (“phase II” collimator) – 2 nd passive absorber upstream of MSI for ultimate beam (to be decided, funded, designed SD 2008/09 ? ) 3 rd March 2008 Extended LTC
Part the 2 nd beam dump system 3 rd March 2008 Extended LTC
Dump kicker installations around P 6 (B 2) UD 62 UP 62 TD 62 RA/UA 63 dilution kicker generators, cables and magnets UJ 62 UJ 63 RA 63 UA 63 RA 67 UJ 68 TD 68 UD 68 RA/UA 67 extraction kicker generators, cables and magnets 3 rd March 2008 UP 68 2008 Extended LTC
Beam dump subsystems • Main LBDS subsystems – – – Extraction kickers MKD Extraction septa MSD Dilution kickers MKBH, V Beam dump block TDE Triggering and synchronisation unit TSU Beam energy tracking system BETS Kicker state control and surveillance Passive protection devices TCDS, TCDQ, TCSG, TCDQM Vacuum system Beam instrumentation BTVs, BPMs, BLMs, FBCTs, BSRA Post-operational checking systems IPOC, XPOC • Links to other systems – – – – BIS loop monitoring and user permit DCCT current from 8 Power convertors (4 RBs, 2 Q 4 s, 2 MSDs) Revolution frequency from RF in point 4 Direct BLM and access system inputs to TSU Synch BPMs for kicker timing Injection system for abort gap keeper and arming inhibit LHC controls system and timing 3 rd March 2008 Extended LTC
Beam dump HW interdependencies Direct BLM Access IPOC / XPOC system checks User Permits (interlocks) from BIS clients 3 rd March 2008 Extended LTC
Beam dump system: IST and HWC • Individual System Tests and HWC : making subsystems work – MSD septa : powering tests finished – MKD/MKB kickers : testing for past 6 months • Now changing to running in remote (fully so after w 11) • All magnets and generators tested to 7 Te. V • Final parts being deployed and tested now (TSUs, links to BICs) – Beam dump blocks TDE : still to leak-test and put under N 2 – Ring beam pipes : under vacuum, baked and NEG activated – Extracted beam lines TD 62 and TD 68 : tested – need final alignment – MKB vacuum remains a concern – Protection devices : TCDQ IST/HWC finishing, TCSG still to do – Beam instrumentation : a few BLMs to move, direct BLM VME electronics missing –most ISTs/HWC completed and basically ready – Presently (w 9 -10) making EMC tests between equipment systems – Organisation: responsibility and coordination • HWC responsible for coordinating IST/HWC carried out by equipment groups: planning, access, safety, impact of 5 -6 and 6 -7 cooldowns, EMC tests, … • Presently a very long-standing and efficient collaboration between all concerned (groups, HWC, LBDS, OP) 3 rd March 2008 Extended LTC
Beam dump system: reliability run • Reliability run and kicker burn-in – Designed to validate some key safety assumptions (SIL calculations) – Ideally “Fully-connected” to all external systems • Will be possible only very late (RF, BIS, access, DCCTs, …) machine checkout • Not compatible with requirement to run system for ~4 months for statistics – Since December 2007 configured and running B 1 MKDs in “stand alone” mode, interleaved with ISTs/HWC • Internal function generator (BETS simulator) for energy ramp • Internal dump trigger • IPOC and XPOC operational for data acquisition and analysis – From 10 th March, configure B 1 & B 2 systems in “semi-connected” mode • • BETS simulator ramp triggered by timing system Local beam permit loop connected to LBDS Dumps triggered by timing events via the BIS Access system “beam dump” signal strapped – to be redone for final DSO tests Direct BLM input masked on TSU boards – redone when BLM cards available IPOC/XPOC operational, logging, … Run by sequencer from CCC (arming, state control, timing tables, …) – Organisation: responsibility and coordination • LBDS project responsible for reliability run: tests, tools, analysis, coordinating with HWC, OP, LSA, … 3 rd March 2008 Extended LTC
Current [A] Dumps Reliability run results (12/07 2/08) Distribution of beam dump energies (9’ 376 dumps as of 29/02/08) Time [ms] Stability/reproducibility of MKD. B 1 kick strength at 7 Te. V Kick strength variation [%] Energy [Ge. V] Stability/reproducibility of MKD. B 1 kick strength at 450 Ge. V ± 1% variation ± 0. 4% variation Specification ± 0. 4% Date 3 rd March 2008 Extended LTC Date
Rise time [ms] Rise time of all 15 MKD at 7 Te. V Rise time of all 15 MKD at 450 Ge. V Specification 2. 7 ms Date Rise time [ms] Reliability run results (12/07 2/08) Stability/reproducibility of MKD. B 1 average rise time at 7 Te. V Stability/reproducibility of MKD. B 1 average rise time at 450 Ge. V 22 ns Date 3 rd March 2008 Extended LTC Date
Reliability run results (12/07 2/08) • Stability and reproducibility – Generator kick strength less stable than expected at 450 Ge. V (measured ± 0. 4% at 7 Te. V, ± 1% at 450 Ge. V). Possible thermal effect being investigated – Rise time looks OK – rise time averaged over all 15 MKDs is < 2. 72 ms, and for any individual MKD in the range 2. 6 - 2. 8 ms (c. f. specified 2. 7 ms). We have a small 50 ns margin which we will need to eat into… – Short-term hysteresis effects on kick waveform measurement transformer? Now deploying 2 nd pick-up type and investigating • Burn-in and fault statistics (on 30 generators 60 switches) – – – Switches most important elements being tested Calculations predicted 6 broken for 4 months operation of both systems Presently operated B 1 for about 3 months with ~50 % duty cycle Total of ~10’ 000 beam dumps to date (300’ 000 switch operations) 2 switches broken (pulsing) in July 07 trigger transformer contacts (systematic problem – now should not re-occur) – 1 switch broken (under voltage at 7 Te. V) on 27/02/08. First real switch failure (note that detection worked failed safe synch dump) 3 rd March 2008 Extended LTC
Beam dump system: dry runs • Dry runs : running LBDS as a system from CCC – Commissioning system links and interdependencies, SW tools, … – Ideally would be “Fully-connected” to all external systems, but not possible until final machine checkout phase – First dry-run test (2 days) carried out in w 7 • Checked beam 1 system in “very-semi-connected” mode • Testing and deploying tools needed for operation, and for reliability run from CCC – Further 2 -day tests planned with increasing scope and complexity: • W 11: B 1 system connected to BIS, RF, LASS and driven via sequencer • W 15: B 1 and B 2 systems together, with protection devices • W 19: links to injection systems, inject and dump modes, … – Organisation: responsibility and coordination • Much preparation and mobilisation for HW, controls, SW • OP responsible for dry runs: schedule, test, tools, coordinate • BT providing strong support… 3 rd March 2008 Extended LTC
Beam dump system: machine checkout • Machine checkout : run LBDS as embedded system from CCC – Will be “Fully-connected” to all external systems – in particular magnet DCCTs, RF and BIS – Will need a series of energy ramps (5 -10) • Check kicker energy tracking with RB circuits • Synchronisation with RF revolution frequency • Assume can be done parasitically – i. e. some ramps are made before beam… – Will need time with the BIS loops closed (1 -2 days) • Check signal transmission and detection, arming sequences • Assume this can be done as part of final beam interlock system commissioning – Organisation: responsibility and coordination • OP responsible for machine checkout: support from equipment groups and LBDS project • BT group will provide system commissioning team (scheduled or on call as required), plus equipment piquets for kicker HW and controls 3 rd March 2008 Extended LTC
Beam dump system: known issues • Follow-up of known non-conformities (some correctable…) – Known changes w. r. t. original specification • • • BI and protection element tilt sign errors (ICC report from TS/SU) Horizontal offset of MKBs and BCTs (EDMS 849665) MKD second beam chamber offset (EDMS 859393) Non-standard TD line chamber sizes for Q 4/Q 5 integration (EDMS 671966) Absence of RF shielding transitions in a few locations (EDMS? ) MSD and TCDS alignment and aperture (EDMS 631718) • Kicker performance still being qualified in reliability run – MKD magnet kick strength variations (under investigation), rise time tight – Number of switch failures to date looks OK • Change management system needed for dump kicker system – Magnets/chambers/generators/switches/delays/lookup-tables/… – To be worked out with layout DB people • Completion of installations/correction of NCs planned – – Installation of staged MKB kickers for LHC phase II (08/09 shutdown) Final TDE N 2 handling system (08/09 shutdown? ) Vacuum transitions – when sectors opened, or SD before high intensity operation Tilt errors - when sectors opened 3 rd March 2008 Extended LTC
Part the 3 rd common comments 3 rd March 2008 Extended LTC
Documentation • Required documentation should be easily available for injection and dump systems, as relevant: – – – • MKD 7 Te. V 30. 12 k V 30. 3 k. V Installation drawings and layouts ~complete Equipment drawings and parameters ~complete Optics files and aperture models partial Alignment information ~complete Expected bunch positions on BPMs and BTVs ~complete MKD/B lookup tables to formalise XPOC references and tolerances needed Kicker calibration, test and reliability run data partial Equipment config. (generators, switches, magnets, …) to formalise Arming and state descriptions partial Interlock references (protection devices, interlock BI, …) partial Non-conformity documents partial No single repository (layout DBs, CDD, EDMS, LSA, Geode, …) 3 rd March 2008 Extended LTC
Snapshot of commissioning status Injection Beam dump 3 rd March 2008 Extended LTC
Coordination aspects • Clear separation of commissioning phases would be nice (as on paper) – Too idealistic – In reality the boundaries are very blurred: overlap of last installations, bug fixes, IST, HWC, dry runs, … – Additional constraints from equipment tests, cool-down, … – Coordination is a long-standing, efficient collaboration between all concerned (groups, HWC, LTI/LBDS projects, ABP, OP, …) • Organisation of commissioning teams and support – BT, OP and other groups’ experts already heavily involved and will form backbone of system commissioning teams: will be available on scheduled and unscheduled basis until beam commissioning is finished – BT piquet service will be in place for all LHC kickers (magnets, generators and controls) for machine checkout and beyond 3 rd March 2008 Extended LTC
Conclusion • Injection systems and beam dump system are progressing well through the commissioning phases – – – Seriously blurred boundaries but under control All components tested to full strength with no major problems Connections to other systems are being brought on-line Operation from the CCC has started Strong system commissioning teams are being forged A lot left to do, but (barring disaster) systems will be ready for first beam 3 rd March 2008 Extended LTC
- Slides: 27