Initial Tracking Tests of DHC Tower Kurt Francis, Donna Kubik - Northern Illinois University Update - 09/24/2003 1
Current Status • Very primitive tracking software • Using Visual Basic • PMT #1 (Bottom) is given priority because PMT#1 generates the Dynode 12 signal - used to generate trigger • Layers 1 and 2 are connected to PMT#1 • Treats layers as pairs • Simple logic – For every column ; if either 1 or 2 cells from one column in layers 1 & 2 are hits then start track - counts layers hit – Every column of layer pairs 3 and 4 - count layers hit 2
Summary • With 10 QDC counts from Pedestal as the threshold only 4% of the events have tracks that pass through all four layers. • All of them are straight through a column • The percentage of 3 layer tracks is a strong function of the threshold 5
Next Steps • Still want to do more tests with Light Yield and S. P. E. • Try to use dynode-12 signal from second PMT to create 4 -way coincidence trigger or to replace one of the Paddles • Improved tracking software • Test different arrays with available PMTs 6