Indian Institutions and Fermilab Collaboration Cryomodule Test SystemCMTS
Indian Institutions and Fermilab Collaboration Cryomodule Test System(CMTS) (Section # 8. 2) Sub-Project Coordinators V. K. Mishra, DAE Mike White, FNAL 2 nd Review Meeting on the Joint Project Document for R&D Phase of IIFC during July 11 -12, 2016 at BARC, Mumbai
Outline • Scope of work • Status - Technical - Schedule • Issues Requiring Management Attention - Technical - Schedule • Summary 2 nd Review Meeting on the Joint Project Document for R&D Phase of IIFC during July 11 -12, 2016 at BARC, Mumbai 2
Scope of work Cryomodule Test System(CMTS) (Section # 8. 2) S. No. Major Milestone Qty Delivery Date Remarks 1 1. 3 GHz CMTS Feed Cap 1 Done Delivered 2 1. 3 GHz CMTS End Cap 1 Done Delivered 3 1. 3 GHz CMTS Feed Box 1 31 Mar 2016 4 1. 3 GHz CMTS Cryo-distribution 1 31 Mar 2016 5 Development of CMTF Design document for 650 MHz Cryomodule 31 Dec 2016 6 Review of CMTF Design 31 Mar 2017 7 Fabrication of CMTF Cryostat 1 31 Mar 2018 8 Development of CMTF Controls (*) 1 31 Mar 2018 9 Integration of CMTF System without cryostat 1 31 July 2018 10 Delivery of Integrated CMTF System to Fermilab 1 31 Dec 2018 #12 Subject to supply of FRS and TRS by Fermilab for 650 MHz CMTF by 31 Oct 2015. 2 nd Review Meeting on the Joint Project Document for R&D Phase of IIFC during July 11 -12, 2016 at BARC, Mumbai 3
Background • Fermilab has shared drawings of the 1. 3 GHz CMTS which it purchased from an industry with BARC. –In last two years we have been jointly working and developed the Feedcap, and Endcap for the cryogenic distribution system for a 1. 3 GHz cryomodule test stand 2 nd Review Meeting on the Joint Project Document for R&D Phase of IIFC during July 11 -12, 2016 at BARC, Mumbai 4
Scope of work Milestones 1 & 2: 1. 3 GHz CMTS Feed Cap & End Cap Milestone Major Milestone Qty Delivery Date Remarks 1 1. 3 GHz CMTS Feed Cap 1 Done Delivered 2 1. 3 GHz CMTS End Cap 1 Done Delivered 2 nd Review Meeting on the Joint Project Document for R&D Phase of IIFC during July 11 -12, 2016 at BARC, Mumbai 5
Technical Status: DAE Feed Cap Design End Cap Design 2 nd Review Meeting on the Joint Project Document for R&D Phase of IIFC during July 11 -12, 2016 at BARC, Mumbai
Technical Status: DAE Feedcap/Endcap Delivered to FNAL June 2015 2 nd Review Meeting on the Joint Project Document for R&D Phase of IIFC during July 11 -12, 2016 at BARC, Mumbai
Technical Status: FNAL Commissioning run of distribution system including Feedcap completed March 2016 2 nd Review Meeting on the Joint Project Document for R&D Phase of IIFC during July 11 -12, 2016 at BARC, Mumbai
Milestone 3: 1. 3 GHz CMTS Feed Box Milestone Major Milestone 3 1. 3 GHz CMTS Feed Box Qty 1 Delivery date Remarks 31 Mar 2016 2 nd Review Meeting on the Joint Project Document for R&D Phase of IIFC during July 11 -12, 2016 at BARC, Mumbai 9
Cryomodule Test System(CMTS) Design is Complete. 2 nd Review Meeting on the Joint Project Document for R&D Phase of IIFC during July 11 -12, 2016 at BARC, Mumbai 10
Cryomodule Test System(CMTS) Status: Assembly is under progress. Vacuum Shell-Top Vacuum Shell-Bottom JT-HX Subassembly Thermal Shield Support Subassembly Cryo-lines Subassembly Temp. 2 nd Review Meeting on the Joint Project Document for R&D Phase of IIFC during July 11 -12, 2016 at BARC, Mumbai Sensor Subassy. 11
Cryomodule Test System(CMTS) Status & Schedule: • Procurement of various components has been delayed, but all the purchase orders have been placed and procurement will be completed by 31/10/2016 • FNAL will deliver temperature sensors by 31/07/2016 • DAE will deliver completed feedbox by 31 Mar 2017 2 nd Review Meeting on the Joint Project Document for R&D Phase of IIFC during July 11 -12, 2016 at BARC, Mumbai 12
Cryomodule Test System(CMTF) Milestone Major Milestone Qty Delivery Date 5 Development of CMTF Design document for 650 MHz Cryomodule 31 Dec 2016 6 Review of CMTF Design 31 Mar 2017 7 Fabrication of CMTF Cryostat 1 31 Mar 2018 8 Development of CMTF Controls 1 31 Mar 2018 9 Integration of CMTF System without cryostat 1 31 July 2018 Remarks #12 10 Delivery of Integrated CMTF System to 1 31 Dec 2018 Fermilab #12 Subject to supply of FRS and TRS by Fermilab for 650 MHz CMTF by 31 Oct 2015. Status • No progress as FRS and TRS are yet to be provided by FNAL. Schedule: • FNAL will provide FRS and TRS by DD/MM/YYYY. Integration of CMTF system will be completed 38 months after receipt of these documents. 2 nd Review Meeting on the Joint Project Document for R&D Phase of IIFC during July 11 -12, 2016 at BARC, Mumbai 13
Summary CMTS for 1. 3 GHz Cryomodule • Feedcap/Endcap (Milestones 1 & 2) delivered successfully. Feedcap fully commissioned. Endcap to be tested with first LCLSII cryomodule in summer of 2016 • Procurement of all remaining items for Feedbox (Milestone 3) will be completed by 31/10/2016 • FNAL will deliver Feedbox temperature sensors by 31/07/2016. • Feedbox fabrication underway and will be delivered by DAE by 31/03/2017 2 nd Review Meeting on the Joint Project Document for R&D Phase of IIFC during July 11 -12, 2016 at BARC, Mumbai 14
Summary CMTF for 650 MHz Cryomodule • Design of the HB 650 CM Cryogenic pipes are in the final stage. Design specification of the 650 MHz CMTF Interface Box will start soon. • FNAL will provide FRS and TRS for CMTF for 650 MHz Cryomodule by DD/MM/YYYY • Delivery of integrated 650 MHz CMTF system will be completed 38 months after finalization of FRS and TRS. 2 nd Review Meeting on the Joint Project Document for R&D Phase of IIFC during July 11 -12, 2016 at BARC, Mumbai 15
Thank you 2 nd Review Meeting on the Joint Project Document for R&D Phase of IIFC during July 11 -12, 2016 at BARC, Mumbai 16