Hydro power plants Hydro power plants Inlet gate

  • Slides: 73
Download presentation
Hydro power plants

Hydro power plants

Hydro power plants Inlet gate Air inlet Surge shaft Penstock Tunnel Sand trap Trash

Hydro power plants Inlet gate Air inlet Surge shaft Penstock Tunnel Sand trap Trash rack Self closing valve Tail water Main valve Turbine Draft tube gate

The principle the water conduits of a traditional high head power plant

The principle the water conduits of a traditional high head power plant

Ulla- Førre Original figur ved Statkraft Vestlandsverkene

Ulla- Førre Original figur ved Statkraft Vestlandsverkene

Arrangement of a small hydropower plant

Arrangement of a small hydropower plant

Ligga Power Plant, Norrbotten, Sweden H = 39 m Q = 513 m 3/s

Ligga Power Plant, Norrbotten, Sweden H = 39 m Q = 513 m 3/s P = 182 MW Drunner=7, 5 m

Borcha Power Plant, Turkey H = 87, 5 m P = 150 MW Drunner=5,

Borcha Power Plant, Turkey H = 87, 5 m P = 150 MW Drunner=5, 5 m

Water intake • • Dam Coarse trash rack Intake gate Sediment settling basement

Water intake • • Dam Coarse trash rack Intake gate Sediment settling basement

Dams • Rockfill dams • Pilar og platedammer • Hvelvdammer

Dams • Rockfill dams • Pilar og platedammer • Hvelvdammer

Rock-fill dams 1. 2. 3. 4. Core Filter zone Transition zone Supporting shell Moraine,

Rock-fill dams 1. 2. 3. 4. Core Filter zone Transition zone Supporting shell Moraine, crushed soft rock, concrete, asphalt Sandy gravel Fine blasted rock Blasted rock

Slab concrete dam

Slab concrete dam

Arc dam

Arc dam

Gates in Hydro Power Plants

Gates in Hydro Power Plants

Types of Gates • Radial Gates • Wheel Gates • Slide Gates • Flap

Types of Gates • Radial Gates • Wheel Gates • Slide Gates • Flap Gates • Rubber Gates

Radial Gates at Älvkarleby, Sweden

Radial Gates at Älvkarleby, Sweden

Radial Gate The forces acting on the arc will be transferred to the bearing

Radial Gate The forces acting on the arc will be transferred to the bearing

Slide Gate Jhimruk Power Plant, Nepal

Slide Gate Jhimruk Power Plant, Nepal

Flap Gate

Flap Gate

Rubber gate Flow disturbance Reinforced rubber Open position Reinforced rubber Closed position Bracket Air

Rubber gate Flow disturbance Reinforced rubber Open position Reinforced rubber Closed position Bracket Air inlet

Circular gate End cover Ribs Hinge Manhole Pipe Ladder Bolt Fastening element Seal Frame

Circular gate End cover Ribs Hinge Manhole Pipe Ladder Bolt Fastening element Seal Frame

Circular gate Jhimruk Power Plant, Nepal

Circular gate Jhimruk Power Plant, Nepal

Trash Racks Panauti Power Plant, Nepal

Trash Racks Panauti Power Plant, Nepal

Theun Hinboun Power Plant Laos

Theun Hinboun Power Plant Laos

Gravfoss Power Plant Norway Trash Rack size: Width: 12 meter Height: 13 meter Stainless

Gravfoss Power Plant Norway Trash Rack size: Width: 12 meter Height: 13 meter Stainless Steel

Comp. Rack Trash Rack delivered by VA-Tech

Comp. Rack Trash Rack delivered by VA-Tech

Cleaning the trash rack

Cleaning the trash rack

Pipes • Materials • Calculation of the change of length due to the change

Pipes • Materials • Calculation of the change of length due to the change of the temperature • Calculation of the head loss • Calculation of maximum pressure – Static pressure – Water hammer • Calculation of the pipe thickness • Calculation of the economical correct diameter • Calculation of the forces acting on the anchors

Materials • Steel • Polyethylene, PE • Glass-fibre reinforced Unsaturated Polyesterplastic , GUP •

Materials • Steel • Polyethylene, PE • Glass-fibre reinforced Unsaturated Polyesterplastic , GUP • Wood • Concrete

Materials Material Steel, St. 37 Max. Stresses [MPa] 150 Steel, St. 42 190 Steel,

Materials Material Steel, St. 37 Max. Stresses [MPa] 150 Steel, St. 42 190 Steel, St. 52 206 PE Max. Diameter Max. Pressure [m] ~ 1, 0 160 2, 4 320 Max. p = 160 m. Max. D: 1, 4 m. Wood ~5 80 Concrete ~5 ~ 400 GUP 5

Steel pipes in penstock Nore Power Plant, Norway

Steel pipes in penstock Nore Power Plant, Norway

GUP-Pipe Raubergfossen Power Plant, Norway

GUP-Pipe Raubergfossen Power Plant, Norway

Wood Pipes Breivikbotn Power Plant, Norway Øvre Porsa Power Plant, Norway

Wood Pipes Breivikbotn Power Plant, Norway Øvre Porsa Power Plant, Norway

Calculation of the change of length due to the change of the temperature Where:

Calculation of the change of length due to the change of the temperature Where: DL = a = DT = Change of length [m] Length [m] Coefficient of thermal expansion [m/o. C m] Change of temperature [o. C]

Calculation of the head loss Where: hf = L = D = c =

Calculation of the head loss Where: hf = L = D = c = g = Head loss Friction factor Length of pipe Diameter of the pipe Water velocity Gravity [m] [-] [m] [m/s 2]

Example Calculation of the head loss Power Plant data: H = 100 m Head

Example Calculation of the head loss Power Plant data: H = 100 m Head Q = 10 m 3/s Flow Rate L = 1000 m Length of pipe D = 2, 0 m Diameter of the pipe The pipe material is steel Where: c = 3, 2 m/s Water velocity n = 1, 308· 10 -6 m 2/s Kinetic viscosity Re = 4, 9 · 106 Reynolds number

Where: Re = 4, 9 · 106 Reynolds number e = 0, 045 mm

Where: Re = 4, 9 · 106 Reynolds number e = 0, 045 mm Roughness D = 2, 0 m Diameter of the pipe e/D = 2, 25 · 10 -5 Relative roughness f = 0, 013 Friction factor The pipe material is steel 0, 013

Example Calculation of the head loss Power Plant data: H = 100 m Head

Example Calculation of the head loss Power Plant data: H = 100 m Head Q = 10 m 3/s Flow Rate L = 1000 m Length of pipe D = 2, 0 m Diameter of the pipe The pipe material is steel Where: f = 0, 013 c = 3, 2 m/s g = 9, 82 m/s 2 Friction factor Water velocity Gravity

Calculation of maximum pressure Static head, Hgr (Gross Head) Water hammer, Dhwh Deflection between

Calculation of maximum pressure Static head, Hgr (Gross Head) Water hammer, Dhwh Deflection between pipe supports Friction in the axial direction Hgr • •

Maximum pressure rise due to the Water Hammer Jowkowsky Dhwh a cmax g =

Maximum pressure rise due to the Water Hammer Jowkowsky Dhwh a cmax g = = Pressure rise due to water hammer Speed of sound in the penstock maximum velocity gravity c [m. WC] [m/s] [m/s 2]

Example Jowkowsky a = 1000 [m/s] cmax = 10 [m/s] g = 9, 81

Example Jowkowsky a = 1000 [m/s] cmax = 10 [m/s] g = 9, 81 [m/s 2] c=10 m/s

Maximum pressure rise due to the Water Hammer Where: Dhwh a cmax g L

Maximum pressure rise due to the Water Hammer Where: Dhwh a cmax g L TC = = = Pressure rise due to water hammer Speed of sound in the penstock maximum velocity gravity Length Time to close the main valve or guide vanes C L [m. WC] [m/s] [m/s 2] [m] [s]

Example L TC cmax g = = 300 10 10 9, 81 [m] [s]

Example L TC cmax g = = 300 10 10 9, 81 [m] [s] [m/s 2] C=10 L m/s

Calculation of the pipe thickness • Based on: – Material properties – Pressure from:

Calculation of the pipe thickness • Based on: – Material properties – Pressure from: • Water hammer • Static head Where: L = Length of the pipe Di p st t Cs r Hgr Dhwh = Inner diameter of the pipe = Pressure inside the pipe = Stresses in the pipe material = Thickness of the pipe = Coefficient of safety = Density of the water = Gross Head = Pressure rise due to water hammer [m] [Pa] [m] [-] [kg/m 3] [m] st st p ri t

Example Calculation of the pipe thickness • Based on: – Material properties – Pressure

Example Calculation of the pipe thickness • Based on: – Material properties – Pressure from: • Water hammer • Static head st Where: L = 0, 001 m Length of the pipe Di st r Cs Hgr Dhwh = = = Inner diameter of the pipe Stresses in the pipe material Density of the water t Coefficient of safety Gross Head Pressure rise due to water hammer 2, 0 m 206 MPa 1000 kg/m 3 1, 2 100 m 61 m st p ri

Cost [$] Calculation of the economical correct diameter of the pipe s, K t

Cost [$] Calculation of the economical correct diameter of the pipe s, K t s o tot lc a t To osts Installation c Costs for h ydraulic lo Diameter [m] , Kt sses, K f

Example Calculation of the economical correct diameter of the pipe Hydraulic Losses Power Plant

Example Calculation of the economical correct diameter of the pipe Hydraulic Losses Power Plant data: H = 100 m Q = 10 m 3/s plant = 85 % L = 1000 m Where: PLoss = r = g = Q = hf = L = r = C 2 = Head Flow Rate Plant efficiency Length of pipe Loss of power due to the head loss Density of the water [kg/m 3] gravity [m/s 2] Flow rate [m 3/s] Head loss [m] Friction factor [-] Length of pipe [m] Radius of the pipe [m] Calculation coefficient [W]

Example Calculation of the economical correct diameter of the pipe Cost of the Hydraulic

Example Calculation of the economical correct diameter of the pipe Cost of the Hydraulic Losses per year Where: Kf = PLoss = T = k. Whprice = r = C 2 = Cost for the hydraulic losses[€] Loss of power due to the head loss Energy production time [h/year] Energy price [€/k. Wh] Radius of the pipe [m] Calculation coefficient [W]

Example Calculation of the economical correct diameter of the pipe Present value of the

Example Calculation of the economical correct diameter of the pipe Present value of the Hydraulic Losses per year Where: Kf = T = k. Whprice = r = C 2 = Cost for the hydraulic losses[€] Energy production time [h/year] Energy price [€/k. Wh] Radius of the pipe [m] Calculation coefficient Present value for 20 year of operation: Where: Kf pv n I = Present value of the hydraulic losses = Lifetime, (Number of year ) [-] = Interest rate [-] [€]

Example Calculation of the economical correct diameter of the pipe Cost for the Pipe

Example Calculation of the economical correct diameter of the pipe Cost for the Pipe Material Where: m = rm = V = r = L = p = s = C 1 = Kt = Mass of the pipe Density of the material Volume of material Radius of pipe Length of pipe Pressure in the pipe Maximum stress Calculation coefficient Installation costs Cost for the material [kg] [kg/m 3] [m] [MPa] [€] [€/kg] NB: This is a simplification because no other component then the pipe is calculated

Example Calculation of the economical correct diameter of the pipe • Installation Costs: –

Example Calculation of the economical correct diameter of the pipe • Installation Costs: – Pipes – Maintenance – Interests – Etc.

Example Calculation of the economical correct diameter of the pipe Where: Kf = Kt

Example Calculation of the economical correct diameter of the pipe Where: Kf = Kt = T = k. Whprice = r = C 1 = C 2 = M = n = I = Cost for the hydraulic losses Installation costs [€] Energy production time [h/year] Energy price [€/k. Wh] Radius of the pipe [m] Calculation coefficient Cost for the material [€/kg] Lifetime, (Number of year ) [-] Interest rate [-] [€]

Example Calculation of the economical correct diameter of the pipe

Example Calculation of the economical correct diameter of the pipe

Calculation of the forces acting on the anchors

Calculation of the forces acting on the anchors

Calculation of the forces acting on the anchors F 5 F 1 F F

Calculation of the forces acting on the anchors F 5 F 1 F F 2 F 3 F 4 F 1 = Force due to the water pressure [N] F 2 = Force due to the water pressure [N] F 3 = Friction force due to the pillars upstream the anchor F 4 = Friction force due to the expansion joint upstream the anchor F 5 = Friction force due to the expansion joint downstream the anchor [N] [N]

Calculation of the forces acting on the anchors F R G

Calculation of the forces acting on the anchors F R G

Valves

Valves

Principle drawings of valves Open position Closed position Spherical valve Hollow-jet valve Gate valve

Principle drawings of valves Open position Closed position Spherical valve Hollow-jet valve Gate valve Butterfly valve

Spherical valve

Spherical valve

Bypass system

Bypass system

Butterfly valve

Butterfly valve

Butterfly valve

Butterfly valve

Butterfly valve disk types

Butterfly valve disk types

Hollow-jet Valve

Hollow-jet Valve

Pelton turbines • Large heads (from 100 meter to 1800 meter) • Relatively small

Pelton turbines • Large heads (from 100 meter to 1800 meter) • Relatively small flow rate • Maximum of 6 nozzles • Good efficiency over a vide range

Jostedal, Norway *Q = 28, 5 m 3/s *H = 1130 m *P =

Jostedal, Norway *Q = 28, 5 m 3/s *H = 1130 m *P = 288 MW Kværner

Francis turbines • Heads between 15 and 700 meter • Medium Flow Rates •

Francis turbines • Heads between 15 and 700 meter • Medium Flow Rates • Good efficiency =0. 96 for modern machines

SVARTISEN P = 350 MW H = 543 m Q* = 71, 5 m

SVARTISEN P = 350 MW H = 543 m Q* = 71, 5 m 3/S D 0 = 4, 86 m D 1 = 4, 31 m D 2 = 2, 35 m B 0 = 0, 28 m n = 333 rpm

Kaplan turbines • Low head (from 70 meter and down to 5 meter) •

Kaplan turbines • Low head (from 70 meter and down to 5 meter) • Large flow rates • The runner vanes can be governed • Good efficiency over a vide range