HV LV status DELIVERED AT BLG 904 4060
HV & LV status DELIVERED AT BLG 904 40/60 6/40 10/10 30/34 5/7 67% of the A 3009 (LV) 15% A 3512 N (HV) 100% A 3018 (T sens) 88% EASY crates 71% branch controllers 6 boards land to ALICE + 2 to the DT group P. Paolucci - I. N. F. N. di Napoli MTCC meeting May 06 1
BLG 904 test setup Hardware and Software Test 3 LV EASY Crate running 15 boards 180 channels 1 HV EASY Crate running 2 boards 12 channels 20 LV boards tested = 240 channels 2 broken (< 1%) 2 HV boards tested = 12 channels OK for more than 900 hours Board Temperature went up to 60 °C due to a bad air circulation. Now fixed and temperature around 40 °C DCS is always running (see Giovanni Talk) Lab. VIEW (D. Lomidze) test program is under installation P. Paolucci - I. N. F. N. di Napoli MTCC meeting May 06 2
HV-LV schema for MTCC LV RPC SY 1527 BC BC HV LV LV LV Control cable W+1 LV trigger 24 ch – HV - Barrel HV HV MAO rpc-dt HV multicond. 10 ch. PP service control 380 3 -phase 24 ch – HV - Endcap LV LV RPC HV HV W+2 MAJISTE HV service 380 3 -phase Balcony Barack 48 V - service MAO Rpc-dt LV trigger PP service control Detector 3
Rack From LV power supply with floating output ALV 1 AGND 1 DLV 1 DGND 1 ALV 2 AGND 2 DLV 2 DGND 2 LV ALV shielded cable AGND DLV DGND shield 4 pairs LV IRON – MAGNET safety ground copper AGND chip HVReturn Copper 2 chip Copper 1 Chamber metallic structure FEB 6 chip AGND DGND strip Double Gap 2 AGND kapton chip Double Gap 1 AGND FEB 1 distrib. board chamber GND RPC ground schema MTCC meeting May 06 4
Ground schema for MTCC EARTH rack GND reference on the chamber LV EASY LV EARTH rack SY 1527 Control shielded cable BC BC HV LV LV LV GND Iron W+1 Link Box 24 ch – HV - Barrel HV HV MAO rpc-dt HV multicond. shielded 10 ch. PP service control 380 3 -phase 24 ch – HV - Endcap LV LV RPC HV HV W+2 MAJISTE HV service 380 3 -phase 48 V - service MAO Rpc-dt LV trigger PP service control P. Paolucci - I. N. F. N. di Napoli MTCC meeting May 06 Balcony Barack 5 Detector
MTCC status LV hardware is ready for Barrel and Endcap HV hardware ready for May the 22 th LV LB hardware now at blg 904 LV EASY crates installation on the balconies started on May the 9 th. Crate insertion in the rack is difficult No space around the racks Balcony barrack 3 -phase installation is underway P. Paolucci - I. N. F. N. di Napoli MTCC meeting May 06 6
MTCC status HV multicond. cables 3 barrel cables are ready and have been tested by myself at CPE 2 endcap cables are in construction at CPE They will be sent at CERN on May 12 th to be installed on May 22 th Local EASY cables will be ready for May 22 th Service and Control long cables ready on May 22 th P. Paolucci - I. N. F. N. di Napoli MTCC meeting May 06 7
To be done LV hardware is ready for Barrel and Endcap HV hardware ready for May the 22 th LV EASY crates installation on the balconies started on May the 9 th. Crate insertion in the rack is difficult No space around the racks Balcony barrack 3 -phase installation is underway P. Paolucci - I. N. F. N. di Napoli MTCC meeting May 06 8
RPC DCS for MTCC P. Paolucci - I. N. F. N. di Napoli MTCC meeting May 06 9
To be done for MTCC ü Move to RPC condition db on SX 5 and test the performance. ü Release the CMS_RPCfw. Hardware Component ü Help our Warsaw friends, creating a control and monitoring system of the LB low voltage, and integrate it into the RPC DCS. ü Do we want to integrate it in the FSM ? ? It will be also discussed tomorrow in the DCS working group. ü Test all the system when the hardware will be ready at SX 5 (June 06). ü Write documentation and organize training in order to have more people ready to take data. P. Paolucci - I. N. F. N. di Napoli MTCC meeting May 06 10