How to perform Time Impact Analysis Window Analysis

  • Slides: 11
Download presentation
How to perform Time Impact Analysis / Window Analysis in Primavera P 6

How to perform Time Impact Analysis / Window Analysis in Primavera P 6

A Time Impact Analysis is a method used to determine extent of impact from

A Time Impact Analysis is a method used to determine extent of impact from potential delay in construction process. This schedule analysis method involves the insertion or addition of activities indicating delays or changes into an updated schedule representing progress up to the point when a delay event occurred to determine the impact of those delay activities.

Types of Delays can be categorized in two main areas: Excusable Delays Non-Excusable Delays

Types of Delays can be categorized in two main areas: Excusable Delays Non-Excusable Delays Excusable delays occur when the affected party is allowed to claim for a time extension, compensation or both. Meanwhile, non-excusable delays are delays that the contractor or party affected will need to bear the responsibility. We have a simple project with the Planned schedule like this:

1 st month. We have delay (21 days) on Excavation due to Unforseen site

1 st month. We have delay (21 days) on Excavation due to Unforseen site condition

2 nd month. We have no delay.

2 nd month. We have no delay.

3 rd month. We have 2 delays: Owner change house design (14 days) Subcontractor

3 rd month. We have 2 delays: Owner change house design (14 days) Subcontractor left job (21 days) And those are concurrent delay. So 14 days charge to owner, and 7 day charge to contractor

4 th month. We have 1 delay from Contractor in “Garage Walls” but it

4 th month. We have 1 delay from Contractor in “Garage Walls” but it was not on the critical path. As long as the delay is within available float there is no effect on the final completion date.

5 th month. We have 1 delay (28 days) from Owner in Garage Doors

5 th month. We have 1 delay (28 days) from Owner in Garage Doors but it only affect 7 days in the critical path. Other 21 days were absorbed by available float.

Last month. We don’t have any delay.

Last month. We don’t have any delay.

So we can have the Time Impact Analysis report like this: 28 days for

So we can have the Time Impact Analysis report like this: 28 days for time and cost 14 days for time