Hard Labor Creek Regional Reservoir October 2019 Project
Hard Labor Creek Regional Reservoir October 2019
Project Location Apalachee River Intake Hard Labor Creek Reservoir
Reservoir Facts • Normal Pool Area: 1, 370 Ac. • Storage Volume: 12 Billion Gallons • Drainage Basin: 30. 2 Sq. Miles • Depth at Dam: 82 Feet
Reservoir Management Board
HLCRMB Oconee County Walton County Chuck Horton, Commissioner Timmy Shelnutt, Commissioner Mark Saxon, Chair Commissioner Kevin Little, Vice-Chair BOC Chairman Justin Kirouac, Lee Bradford, County Administrator Commissioner Brad Johnson, WCWSA Chairman
Project Permitting
Permitting • Water Source Site Selection Studies: 1992 - 1995 • Project Permitting: 1997 • Jurisdictional Waters Report and Protected Species Survey - 1997
Permitting • Safe Yield Computations and In. Stream Flow Protection Reports – March 2000 • Reservoir Alternatives Study – November 2000 • Compensatory Mitigation Plan – October 2001
Permit Approvals ✔U. S. Army Corps of Engineers 404 Permit (2004) ✔Water Withdrawal Permit, Hard Labor Creek Reservoir (2008) ✔Water Withdrawal Permit, Apalachee River Intake: (2008) Diversion to Reservoir) (Raw Water 9
Reservoir Facts • Construction: 2013 - 2016 • Fill Period: 2016 - 2018 • Reservoir Level: 700’ MSL (Full Pool) • 26 Years from Conception to Completion
Hard Labor Creek Regional Reservoir
12
13
14
15
16
Apalachee River Intake Site
Upper Dam Lower Dam Proposed Intake Site +/- 3. 48 Acres High Shoals Hydro Victoria Bracewell Presley 18
Apalachee Diversion Apalachee Withdrawal Permit: • Ga. EPD Approval: June 2008 • Permit No. 147 -0307 -03 • Maximum Day: 60 MGD (92. 8 CFS)
Apalachee Diversion Projected Withdrawals: • Typical withdrawals from the Apalachee will be made at high water level (Wet Weather) • During drought conditions, permit dictates minimum river flow to protect downstream habitat
Apalachee Diversion Protected Downstream Flows: • Typical Withdrawal Permits require protection of 7 Q 10 flows only • HLC Permit requires protection of % Mean Annual Flow (206 CFS) based on Reservoir Levels
Apalachee Diversion Monitoring Requirements: Upstream and Downstream • USGS Streamflow Gages • Continuous Water Quality Monitoring Stations (DO, Temp, p. H, and Turbidity) • Biological Monitoring Stations • Monthly Data Reporting
Apalachee Diversion Projected Withdrawals: • No Apalachee withdrawals anticipated through 2030 • Phased withdrawals following 2030 based on Water Demands • Demand Horizon: 50 -70 Years
Project Website hardlaborcreek. com