FORWARD PIPE SUB ASSEMBLY PIPE TO INSTALL ON
FORWARD PIPE SUB ASSEMBLY PIPE TO INSTALL ON 56 SIDE 19 m TAS 16, 3 m bellow module @18, 5 m forward pipe pump@18 m
FORWARD PIPE SUB ASSEMBLY PIPE TO INSTALL ON 56 SIDE TAS 19 m 16, 3 m F. I. N
FORWARD PIPE SUB ASSEMBLY PIPE TO INSTALL ON 56 SIDE modified telemanipulator tas Interface disk adjusting plate
FORWARD PIPE SUB ASSEMBLY TO INSTALL ON 56 SIDE Preparation work in the cavern: -install and align interface disk, adjusting plate, cantilevered support, and supports of 56 forward sub assembly. -modify roughness of TAS -install modified telemanipulator (5 days ) Preparation work in 927 lab: -make uhv assembly of forward pipe with pump@18 meter & bellow module, install permanent bakeout and make a full conditioning of forward sub assembly (7 days)
FORWARD PIPE SUB ASSEMBLY PIPE TO INSTALL ON 56 SIDE Interface disk adjusting plate ok ok Cantilevered support ok Support @16 m (not mandatory to be install)
FORWARD PIPE SUB ASSEMBLY TO INSTALL ON 56 SIDE
FORWARD PIPE SUB ASSEMBLY TO INSTALL ON 56 SIDE
FORWARD PIPE SUB ASSEMBLY TO INSTALL ON 56 SIDE
FORWARD PIPE SUB ASSEMBLY TO INSTALL ON 56 SIDE
FORWARD PIPE SUB ASSEMBLY TO INSTALL ON 56 SIDE -Before VAC work TAS need to be align and a platform need to be there for operators access in the 16 to 22 meter region -INSTALLATION SEQUENCES & TIME ESTIMATE 1 -telemanipulator installation @19 meter and TAS seal surface roughness modification (2 days) AT/vac 2 -interface disk installation with adjusting plate (1 day) AT/vac 3 -cantilevered support to fix (1 day) AT/vac 4 -pre-alignement of cantilevered support(1 day)AT/vac+TS/su 5 -install forward pipe sub assembly with bakeout(2 days)AT/vac 6 -pumping and leak detection to perform (2 days) AT/vac 7 -install cabling for 18 meter pump and test (3 days) AT/Vac