Forensic IT System Governance Update March 27, 2017

Forensic IT System Governance Update March 27, 2017

Agenda • Introductions • Project Status § Project Updates • Review Project Plan •

Agenda • Introductions • Project Status § Project Updates • Review Project Plan • Issues update • Next Steps • Questions

Project Status

Project Status

Forensic Project Status • Project remains Green… • QA contract/SOW completed and Integrated Solutions

Forensic Project Status • Project remains Green… • QA contract/SOW completed and Integrated Solutions Group (ISG) on boarded. • Published Requirements Document (RD). • Completed Entity Relationship Diagram (ERD) review with DSE and BHA Architect. • Detailed Project Plan through implementation.

Forensic System Advisory Committee Recommendation to create this new advisory committee for project support

Forensic System Advisory Committee Recommendation to create this new advisory committee for project support through implementation. A biweekly committee appointed by Tom. Committee Objectives: • Business rule/process clarifications • Representatives of major system roles • Order Processors • Schedulers • Evaluators • Program Administrators • Testing/SME’s • Change Agents • Training support • Go-live support This committee would be advisory only. Decisions remain with Governance.

Decision Point: Do you approve the creation of a Forensic System Advisory Committee and

Decision Point: Do you approve the creation of a Forensic System Advisory Committee and Tom appointing the membership? • Yes • No

Imaging Solutions update. ESA/Electronic Case Record (ECR): • Meeting scheduled (3/28) with technical teams

Imaging Solutions update. ESA/Electronic Case Record (ECR): • Meeting scheduled (3/28) with technical teams to explore feasibility. DSHS/MODIS: • Conducted initial meeting (3/6) with technical teams. • Demo/Q & A scheduled (4/14).

Project Plan

Project Plan

Detailed Project Plan (status). • • Complete Requirements Document (RD) Complete Entity Relationship Diagram

Detailed Project Plan (status). • • Complete Requirements Document (RD) Complete Entity Relationship Diagram (ERD) Initiate prototype design 3/31/17 Initiate Modular design 5/8/17

Detailed Project Plan (moving forward) • Legacy Data analysis and recommendation to Governance. •

Detailed Project Plan (moving forward) • Legacy Data analysis and recommendation to Governance. • Iterative Modular Design • Integration Testing (IT) • Technical and User Documentation • Training • Go-Live 7/2/18 (Review Project Plan- Modular design)

Issues Update

Issues Update

 • Forensic Admissions Waitlist: In-process On track to have conceptual approval by 3/31.

• Forensic Admissions Waitlist: In-process On track to have conceptual approval by 3/31. • OFMHS has presented an AG reviewed format. • Project team has a formula to score and rank. • Transparent and defensible waitlist! Forensic Admission Waitlist workshop scheduled 3/28. • Run existing forensic admission waitlist ‘orders’ through new algorithm. • Analyze for flaws/GAPS. • Analyze for priority (TCEA/RTF) admissions. Forensic Admission Waitlist next steps…

Next Steps

Next Steps

Upcoming (this month) Project Activities Goal: Design C. A. R. L. A. Prototype §

Upcoming (this month) Project Activities Goal: Design C. A. R. L. A. Prototype § Conduct ESA/ECR feasibility session. § Demo/Assess MODIS Imaging solution with OFMHS. § Define/Review standard reporting requirements with OFMHS. § Data migration assessment and recommendation to Governance. § Complete and Submit Investment Plan. Technical Design § Design Prototype C. A. R. L. A.

Questions? ?