FDOT Emergency Shoulder Use (ESU) & One-Way Corridors

FDOT Emergency Shoulder Use (ESU) & One-Way Corridors

District 5 Emergency Shoulder Use (ESU) I-75 Northbound

District 5 Emergency Shoulder Use (ESU) I-75 Northbound

District 5 I-75 Northbound ESU • I-75 ESU extends Northbound from SR-44 in Sumter

District 5 I-75 Northbound ESU • I-75 ESU extends Northbound from SR-44 in Sumter County Northward to the Florida/Georgia State line • D 5’s portion of the ESU extends 42 miles from SR-44 Northward to the Marion/Alachua County line

District 5 I-75 Northbound ESU D 5’s I-75 ESU Details: • Starts @ MM

District 5 I-75 Northbound ESU D 5’s I-75 ESU Details: • Starts @ MM 331. 47 and Ends @ MM 373. 74 = (42. 27 Miles) • 1 Stationary Law Enforcement Officer (LEO) placed prior to ESU start @ MM 330. 87 • • 2 Patrolling Emergency Assistance Vehicles • 2 Dynamic Message Signs (DMS’s) will display a static message unless traffic incident management messages take precedence • No Ramp Closures are planned 6 Interchanges 1 Weigh Station that will be closed @ MM 338 1 Rest Area that will remain open @ MM 345 No Pinch Points or Narrow Shoulder Locations All Permanent Flip Signs have been Installed 2 Portable Changeable Message Signs (PCMS’s) will be deployed per plan

I-75 ESU Implementation Flow Hurricane Approaching Region Secretary of FDOT District 5 AM Contractor

I-75 ESU Implementation Flow Hurricane Approaching Region Secretary of FDOT District 5 AM Contractor Dbi Services With input, Governor Directs ESU Implementation FHP Chief - Central FL FDOT District 2 FDOT Incident Command FHP Colonel FHP Incident Command ESU Unified Command ESU Implemented FHP Major Troop B Commander RTMC Updated Regularly FHP Major Troop C Commander

I-75 ESU Implementation Forces • • District 5 will utilize Dbi Services to implement

I-75 ESU Implementation Forces • • District 5 will utilize Dbi Services to implement the ESU with their forces • Dbi Services is equipped to provide Roadside Assistant Services to Stranded Motorists • Dbi Services procured and installed the ESU signage and has 26 PCMS’s available for deployment with only 2 needed for D 5’s ESU portion DBi Services assisted with the development and review of the Standard Operating Procedures to establish timelines for ESU setup and breakdown

District 5 Blue Sky Activities (Ongoing Maintenance) Activity Responsible Party Timeline Quality Control Check

District 5 Blue Sky Activities (Ongoing Maintenance) Activity Responsible Party Timeline Quality Control Check shoulder conditions to ensure that drop off standards are meeting MRP requirements AM Contractor June 1 Department AM Contract Manager & Inspector Check for pot holes and repair to meet MRP requirements AM Contractor As needed prior to June 1 Department AM Contract Manager & Inspector AM Contractor Department AM Contract Quarterly and immediately prior Manager & Inspector to implementation of ESU AM Contractor Monthly during hurricane season. Immediately prior to implementation of ESU Remove Vegetation to meet MRP requirements Remove Encroachments to meet MRP requirements Sweep the Shoulders to remove all loose materials and small debris Department AM Contract Manager & Inspector

District 5 Gray Sky Activities Activation) Activity Responsible Party Location (Pending Timeline (When) Timeline

District 5 Gray Sky Activities Activation) Activity Responsible Party Location (Pending Timeline (When) Timeline (How Long) Quality Control Pre-Storm Meeting with AM Contractor FDOT District 5 HQs 7 to 5 days out 4 hours Department Deploy Portable Changeable Message Signs AM Contractor Per Plans & SOP Equipment List Implementation of ESU is anticipated 6 hours Department AM Contract Manager & Inspector Sweep Shoulders to remove all loose materials and small AM Contractor debris Entire Corridor Length Implementation of ESU is anticipated 2 days Department AM Contract Manager & Inspector Notify FHP for removal of Abandoned Vehicles AM Contractor / FHP Entire Corridor Length Implementation of ESU is anticipated 8 -12 hours Department AM Contract Manager & Inspector Ride the Corridor AM Contractor & Department Staff Entire Corridor Length Implementation of ESU is anticipated 4 hours Department AM Contract Manager & Inspector Coordinate with FHP and D-2 staff AM Contractor & Department Staff Entire Corridor Length On-Going DME Implementation of ESU is anticipated

District 5 Implementation Activities (Activation & Setup) Activity Responsible Party Flip down permanent signs

District 5 Implementation Activities (Activation & Setup) Activity Responsible Party Flip down permanent signs AM Contractor Set display messages on Portable Changeable Message Signs Ride the Corridor final check and debris removal Location Per Plans and SOP Equipment List Timeline (When) Implementation of ESU AM Contractor Per Plans & SOP Equipment List AM Contractor & Department Staff Entire Corridor Length Coordinate with FHP AM Contractor & Department Staff Entire Corridor Length Position Law Enforcement Officers and Emergency Assistance Vehicles LEO & AM Contractor or Pre. Event Contractor Entire Corridor Length Implementation of ESU Deployment of Roadside Assistance AM Contractor Entire Corridor Length 4 to 8 hours prior to Implementation of ESU Timeline (How Long) Quality Control 1 hour prior Department AM Contract Manager & Inspector 4 hours prior Department AM Contract Manager & Inspector On-Going during Implementati on of ESU DME and Contract Manager

District 5 Deactivation Activities (Breakdown) Post Event Operations Responsible Party Location Timeline (How Long)

District 5 Deactivation Activities (Breakdown) Post Event Operations Responsible Party Location Timeline (How Long) 2 hours Reset Flip Down Panels AM Contractor Per Plans & SOP Equipment List Remove Portable Changeable Message Signs AM Contractor Per Plans & SOP Equipment List 2 hours Demobilize LEOs FHP Per FHP orders When ordered Demobilize EAVs AM or Pre-Event Contractor Circulation Route per Contract When ordered Ride Corridor AM Contractor Entire Corridor Length 2 hours Quality Control Department AM Contract Manager & Inspector FHP Department AM or Pre. Event Contract Manager & Inspector Department AM Contract Manager & Inspector Quality Control Department AM Contract Manager & Inspector Department AM Contract Manager & Inspector

District 5 Deactivation Activities (Cont. ) (Breakdown) Post Event Operations Responsible Party Coordinate with

District 5 Deactivation Activities (Cont. ) (Breakdown) Post Event Operations Responsible Party Coordinate with Local Agency Partners AM Contractor & Department Staff Coordinate with Social Media, Local News Partners Communications Office Coordinate with Decision Makers DME Location Entire Corridor Length Timeline (How Long) On-Going during post implementation of ESU Quality Control DME DME and Contract Manager

Motorist Support • Road Ranger Services • FHP Wrecker Rotation • Pre-Event Emergency Roadside

Motorist Support • Road Ranger Services • FHP Wrecker Rotation • Pre-Event Emergency Roadside Assistance Services Contract • • • Anticipated contract execution August 2017 • Dispatch will be done via the Traffic Management Center and Staging EAVs Assist motorists with minor repairs (< 15 min. ) and 2 gallons of fuel Move inoperable vehicles by pushing or relocating vehicles to roadside or staging areas

Coordination with District 2 • Working from south to north, asset maintenance contractor shall

Coordination with District 2 • Working from south to north, asset maintenance contractor shall implement ESU within 4 hours after order has been given and will coordinate their placements and timing of VCMSs with District 2.