Fairgrounds Master Plan Fairgrounds Master Plan Objectives Replace
Fairgrounds Master Plan
Fairgrounds Master Plan Objectives Replace functionally and structurally outdated facilities Improve utility infrastructure Increase year-round utilization of the fairgrounds
7– 3/1 7– 2/1 e us Ho Up da er te ev Co Di iew un sc cil us of sio Ma Pr es n s ter en Pl ta an tio n er ns tio en Op gin Be ty ty gs tin ee s& en ta old es Pr ng oth e. M d ire rty er op pe Pr Pr ro dd dd ll P Bo eti Me on ak eh itte mm Co St n tio jor lec Ma –E nc il ou nfo ati itte mm Co Ju Ju nh sig De rm nfo c. I bli Pu –C 7– 1/1 /16 11 10 6– 9/1 ir I Fa rk ma on on os we se f. B eo rin g tee –S 6– 8/1 6 nd La as rch Pu ou se ou nh pe –O 6– 5/1 6 - /15 3/1 12 12 Plan Development Timeline
“Not our first rodeo” – 2000 Master Plan
Master Plan Maintains natural setting of the Fairgrounds Separates functions for better flow Provides for multipurpose amenities
Phasing Plan I. III. IV. Exhibit Hall & Livestock: 2017. $5 M Ballfield, Park & Parking: 2 -5 yrs. $4 M Arena & Fairway: 710 yrs. $5 M Contestant Parking: TBD. $300 K All estimates in 2016 dollars
Phase I is Priority for Fair Operations Replaces the two most obsolete facilities on site Quonset Hut is scheduled nearly every weekend Livestock Buildings host auction animals that raised $450, 000 for local youth in 2016. Annual participation average 250 youth.
Phase I Conceptual Drawings
Other Considerations Phased Project Approach Major Stakeholder Cooperation Property Considerations Chalk Creek Development Parking Issues
Contestant Parking Analysis