FACILITIES, PLANNING, AND CONSTRUCTION JANUARY 30, 2014 CONSTRUCTION REPORT

FACILITIES, PLANNING, AND CONSTRUCTION JANUARY 30, 2014 CONSTRUCTION REPORT

Area Currently Under Construction/ Planning Facilities under Construction: V. R. Eaton High School Total

Area Currently Under Construction/ Planning Facilities under Construction: V. R. Eaton High School Total 540, 000 SF _____ 540, 000 SF Facilities in Planning/Bidding Stage: Peterson E. S. Addition Beck E. S. Addition Total Projects under Construction, Planning and Bidding: 14, 000 SF 8, 000 SF ______ 22, 000 SF 562, 000 SF

V. R. Eaton High School Architect: Corgan Associates Contractor: Pogue Construction Company Const. Start

V. R. Eaton High School Architect: Corgan Associates Contractor: Pogue Construction Company Const. Start Date: Spring 2013 Completion Date: August 2015 Status: Ø Ø Ø Ø Pier drilling is complete Geothermal wells are being drilled Grade beams are 45% complete Foundation pours are underway Rough electrical and plumbing is being installed Site grading and utility installation is underway Steel erection will begin in March

May 2013 January 2014

May 2013 January 2014

Peterson Elementary School Addition Architect: SHW Architects Contractor: Northstar Builders Const. Start Date: Spring

Peterson Elementary School Addition Architect: SHW Architects Contractor: Northstar Builders Const. Start Date: Spring 2014 Completion Date: August 2014 Status: Ø Design Complete Ø GMP submitted for School Board approval Ø Construction begin in February

Beck Elementary School Addition Architect: SHW Architects Contractor: Balfour Beatty Construction Const. Start Date:

Beck Elementary School Addition Architect: SHW Architects Contractor: Balfour Beatty Construction Const. Start Date: Spring 2014 Completion Date: August 2014 Status: Ø Design Complete Ø GMP will be submitted for School Board approval in February Ø Construction begin in March

SECO Energy Grant • OLC- Wind Turbine and Solar Array Operational • Central Campus-

SECO Energy Grant • OLC- Wind Turbine and Solar Array Operational • Central Campus- Wind Turbine and Solar Array Operational