FACILITIES, PLANNING, AND CONSTRUCTION April 14, 2014 Construction Report

FACILITIES, PLANNING, AND CONSTRUCTION April 14, 2014 Construction Report

Area Currently Under Construction/ Planning Facilities under Construction: V. R. Eaton High School Total

Area Currently Under Construction/ Planning Facilities under Construction: V. R. Eaton High School Total 540, 000 SF _____ 540, 000 SF Facilities in Planning/Bidding Stage: Peterson E. S. Addition Beck E. S. Addition NHS Chiller Replacement Prairie View Drainage Improvement Total Projects under Construction, Planning and Bidding: 14, 000 SF 8, 000 SF NA NA ______ 22, 000 SF 562, 000 SF

V. R. Eaton High School Architect: Corgan Associates Contractor: Pogue Construction Company Const. Start

V. R. Eaton High School Architect: Corgan Associates Contractor: Pogue Construction Company Const. Start Date: Spring 2013 Completion Date: August 2015 Status: Ø Ø Ø Ø Pier drilling is complete Geothermal wells are complete Grade beams are 95% complete Foundation slab is 50% complete Rough electrical and plumbing is being installed Site grading and utility installation is underway Steel erection is approximately 10% complete (Please note that the aerial photo was taken in March and does not reflect April progress)

May 2013 March 2014

May 2013 March 2014

Peterson Elementary School Addition Architect: SHW Architects Contractor: Northstar Builders Const. Start Date: Spring

Peterson Elementary School Addition Architect: SHW Architects Contractor: Northstar Builders Const. Start Date: Spring 2014 Completion Date: August 2014 Status: Ø Classroom concrete slabs have been poured Ø Steel has begun to be erected for classrooms Ø Grade beams have been poured for stage/cafeteria/gym expansion

January 2014 April 2014

January 2014 April 2014

Beck Elementary School Addition Architect: SHW Architects Contractor: Balfour Beatty Construction Const. Start Date:

Beck Elementary School Addition Architect: SHW Architects Contractor: Balfour Beatty Construction Const. Start Date: Spring 2014 Completion Date: August 2014 Status: Ø Pier drilling is underway Ø Site work is underway

Possible ONCOR Electric Power Distribution Line

Possible ONCOR Electric Power Distribution Line

Miscellaneous Maintenance Projects • Prairie View Elementary School Drainage Improvement – Water drains toward

Miscellaneous Maintenance Projects • Prairie View Elementary School Drainage Improvement – Water drains toward the front of the building during heavy rains and flows into the building – Project will be to route water to a retention pond and ditch adjacent to FM 3433 – Possible replacement of the front driveway • Northwest High School – – – Replace a 22 year old chiller Anticipating a major failure within the next year Current chiller contains obsolete R-22 refrigerant The repair cost does not justify the repair The efficiency of the replacement chiller will provide reduction in energy cost

Pending Project Close-Out Change Orders • Cox Elementary School • Love Elementary School •

Pending Project Close-Out Change Orders • Cox Elementary School • Love Elementary School • Subvarsity Stadium

FACILITIES, PLANNING, AND CONSTRUCTION April 14, 2014 Construction Report

FACILITIES, PLANNING, AND CONSTRUCTION April 14, 2014 Construction Report