ETSI EN APPROVAL PROCESS (ENAP) Production time for ENs is being reduced by shortening the duration of the Approval Process (AP) © ETSI 2015. All rights reserved
Summary of the presentation What is ENAP? • Who is involved? • Why do we reduce the duration of AP? How does it work? • AP will be shorter © ETSI 2015. All rights reserved
What is ENAP? An EN is adopted by the application of the EN Approval Procedure (ENAP). ENAP is comprised of a public enquiry and a weighted national vote performed in a single process, named Approval Process (AP) • Articles 13. 4 and 13. 5 of the Rules of Procedure. AP © ETSI 2015. All rights reserved
Who is involved? The Technical Body (TB), the ETSI National Standards Organizations (NSOs) and the ETSI Secretariat are involved in this process. • The draft, approved by the TB, is submitted to the ETSI Secretariat to be dispatched for the AP. YES ENAP (ENs) Comments resolution , draft revision, approval and submission to Secretariat Successful with technical comments Technical Body Draft preparation for submission to NSOs (within 30 days) ETSI Secretariat AP PE + National Consultations (120 days) NSOs Public Enquiry comments and votes compilation Vote Result? NO (within 60 days) Technical Body TB approved draft submission to Secretariat (within 14 days) Significant Changes? Revised draft preparation for submission to NSOs (within 30 days) TB Chairman’s decision ETSI Secretariat Unsuccessful (0 day) ETSI Secretariat Successful with no technical comments Approval Process Who? © ETSI 2015. All rights reserved Why? How does it work? Shorter duration National Consultations (60 days) NSOs
Approval Process (AP) e. g AP 20150723 The NSOs perform the AP (public enquiry and weighted national vote), which currently takes 120 days. The resulting national comments and the national position (vote) are then submitted to the ETSI Secretariat. Approval Process Who? © ETSI 2015. All rights reserved Why? How does it work? Shorter duration
Why are we reducing the duration of AP? Industry demands that the ENs be produced in a more timely fashion. Our target is to reduce the time for AP from 120 days to 60 days by 2020. As a first step, the time for AP will be reduced to 90 days from 1 st September 2015. Approval Process Who? © ETSI 2015. All rights reserved Why? How does it work? Shorter duration
How does it work? Until 31 st August 2015 all ENs are sent on an AP that will last 120 days • EXAMPLE 1: Approval Process Who? © ETSI 2015. All rights reserved Why? How does it work? Shorter duration
From 1 st September 2015 As from 1 st September 2015 the length of time for AP will be reduced to 90 days. • EXAMPLE 2: Approval Process Who? © ETSI 2015. All rights reserved Why? How does it work? Shorter duration
What does it mean in concrete terms? The process remains the same, only the time it takes is changing. Approval Process Who? © ETSI 2015. All rights reserved Why? How does it work? Shorter duration